CENTERDOR ENERGY PEDRY NUCLEAR POWER PLANT Mad Address:
PO. Box 97 Michael D. Lyster
% O HIO 44081 VICE PRESIDENT NUCLEAR ER, OHIO 081 (216; 259 3737 October 11, 1991 PY-CEI/0 EPA-0137L j
Mr. Richard Hagni OEPA Division of Vater Pollution Control P.O. Box 1049 1800 Vatermark Dr.
Columbus, Ohio 43266-0149 Re; Director's Final Findings and Orders for use of H-130 and CL-37 Cooling Vater Additives for the Perry Nuclear Power Plant 4
OEPA Permit No. 3IB00016DD 9
Dear Mr. Magni,
[
In accordance with the Director's Final Findings and Orders, the following is a report of the monitoring and toxicity data obtained during the Perry Nuclear Power Plant's H-130 treatment, conducted pn September 12, 1991.
Grab samples of the effluent vere collected every two hours during the treatment from a point downstream of the detoxification site. Analysis of these samples demonstrated that the concentration of active H-130 discharged into Lake Erie was maintained at <0.02 mg/1.
/ composite sample of the effluent was collected during the H-130 treatment and used to conduct acute toxicity tests. Control samples were collected at both the intake and discharge prior to treatment. Mortality was not found to be at a statistically significant level for any test.
Test results are attached.
The use of CL-37 to reduce foam vas not required.
Please call Louise Barton (216) 259-3737 ext. 5512, if_you have questions or necd additional information.
Sincerely, f/h Michael D. Lys %r Attachment MDL:LKB cc: USNRC Document Control Desk NRR Project Manager Sr. Residen-Inspector 150085 g;Aogel Msgo J