Certifies Interpretation of Radiological Effluent Tech Specs Re Functional Test Requirements,Per 840110 Telcon W/Nrc. Requests Response to Util Position Re Testing of Instrumentation W/O Control Room Annunciation Capability
ML20079H463
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 01/11/1984
From: Warembourg D
PUBLIC SERVICE CO. OF COLORADO
To: Wagner P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
P-84018, NUDOCS 8401230445
Download: ML20079H463 (2)


Text

.

public service company ce ochmde b

16805 WCR 19 1/2, Platteville, Colorado 80651

/0, 7

January 11, 1984 Fort St. Vrain Unit #1 P-84018 ag@MDMKp Mr. Philip Wagner, Project Manager Region IV gig g@ {

{

U.S. Nuclear Regulatory Commission qdj o 611 Ryan Plaza Drive Suite 1000 Arlington, TX 76011

~

SUBJECT:

RETS FUNCTIONAL TEST CLARIFICATION

Dear Mr. Wagner:

With reference to the %lephone conversation of January 10, 1984, between you and Messrs. Ft.ller, Borst, and Novachek of my staff, I

would like to clarify our interpretation of the functional test requirements as contained in Section 8.0 of the Fort St.

Vrain Technical Specifications.

As you know, Specification ESR 8.1.1 - Radioactive Gaseous Effluent, Surveillance Requirements and Specification ESR 8.1.2

- Radioactive Liquid

Effluent, Surveillance Requirements, specify quarterly functional tests for various activity monitors, recorders, flow rate indicators and measuring devices, etc.

The functional tests are intended to demonstrate a control room alarm annunciation in the event of:

"1)

Instrument indicates measured levels above the alarm setpoint.

2)

Circuit failure.

3)

Instrument indicates a downscale failure.

4)

Instrument controls not set in operate mode."

8401230445 840111 PDR ADOCK 05000267 g

P PDR D

j 0

\\ t e

D i

o.

2-As discussed with you on January 10, 1984, at Fort St. Vrain, the control room alarm annunciation / automatic action function is generally tested with the in:,talled radiation monitors and not with the flow indicators, recorders, or flow rate measuring devices.

Therefore it is our interpretation that if instrumentation requiring functional testing does not have control room annunciation capability, the functional test need not satisfy the four criteria listed above.

It is also our understanding that none of our installed instrumentation requires modification to incorporate control room annunciation capability.

Your timely response to this letter is appreciated; if you have any questions regarding this matter, please call Mr. Ted Borst or Mr. Frank Novachek at (303) 571-7436.

Very truly yours, h /Y A%d Don W. Warembourg Manager, Nuclear Production DWW/dkh l