BOSTON EpiMON C O M PANY GENERAL OFFIcts EDO 90VLaTON STREET BosTOF. MAmeAcMustTTm 02199 A. V. M O RISI MANAGER NUCLEAR OPERATIONB SUPPORT DEPARTMENT May 26,1982 BECo. Ltr. #82-157 Mr. Domenic B. Vassallo, Chief Operating Reactors Branch #2 Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Comission Washington, D. C.
20555 License No. DPR-35 Docket No. 50-293 Scram Discharge Volume Long Term Modification Reference (a) BECo. Letter #81-83 dated April 21, 1981 (b) BECo. Letter #82-105 dated April 16, 1982
Dear Sir:
Please be advised that the Reference (a) December 31, 1982 completion date for long term modifications to the Scram Discharge Volume (SDV) System at Pilgrim Station has been re-scheduled for completion in 1983. This schedule change is necessitated for reasons as follows:
1.)
Delivery of new equipment, instrumentation and valves cannot be prcaided by the manufacturers until early 1983.
2.) Total system design not yet finalized, i.e.
a.) Locating, piping and wiring new equipment introduces interferences with existing plant apparatus and systems.
b.) The added weight of new instrument volumes and their radiological shielding requires additional structural and seismic loading analvses of Reactor Building and possible building modifications.
We currently are completing the preliminary design work and are incorporating this modification into our integrated work plan (see Reference (b)) with an assigned priority to assure completion no later than December 31, 1983.
This extension is justified in that the mechanisms involved in the Browns Ferry incident (i.e. poor hydraulic coupling and system back pressure from combined systems drainage lines) are not present at Pilgrim Station because a) the piping and vent layout allows for pmper draining, b) SDV drains are dedicated with no system tie-in's which could provide a source of back pressure, c) Pilgrim has not experienced any significant problems with level instrumentation and d) sonic detectors have been installed to detect possible water buildup in the headers to further reduce any potential risk i
of this type.
8206000350 820526 i
PDR ADOCK 05000293 001 rs rm
WOOTEN EDICON COMPANY Mr. Domenic B. Vassallo, Chief May 26,-1982-Page 2 Please contact us immediately if this extension is not congruent with current staff. requirements-.
Very truly yours,
..