MONTHYEARML20206S2911999-05-0505 May 1999 Informs That on 990420 Council Provided ten-day Comment Period on Council Order 731 Recommending Governor Approval of Amend of Site Certification Agreement for Satsop Power Plant Site ML20202C7671999-01-22022 January 1999 Forwards Order Terminating Construction Permit CPPR-154 for WNP-3/5 Site.Safety Evaluation Associated with Action Also Encl ML20198Q7131999-01-0404 January 1999 Forwards EA & Fonsi Re 960808 Application.Assessment Being Forwarded to Ofc of Fr for Publication ML20155J9731998-11-0505 November 1998 Forwards Addl Detailed Info Re Restoration & Renovation of Site Bldgs Re Util Plans to Renovate Site for Reuse as Industrial Park by Local Government Entity ML20155G7791998-11-0202 November 1998 Forwards Insp Rept 50-508/98-201 on 981027-28.No Violations Noted.Insp Included Review of Activities to Terminate Construction Permit CPPR-154 ML20116M7191996-08-0808 August 1996 Requests Termination of Construction Permit (CPPR-154) of Nuclear Project 3 & Withdrawal of Pending OL WNP-3 ML20082A7771995-03-28028 March 1995 Forwards WPPSS Nuclear Projects 1,3,4 & 5 Restoration Plan ML20078M4961995-02-0303 February 1995 Advises of Termination of Util Projects 1 & 3 ML20059B7681993-10-20020 October 1993 Requests Code Case N-520 Approval for Nuclear Projects 1 & 3 ML20057A6031993-09-0303 September 1993 Forwards Rev 6 to Procedure WMC-051, Preservation of Assets Program, Reflecting Installation of Two Desiccant Type Dehumidifiers for Controlling Relative Humidity within Reactor Auxiliary/Reactor Bldg Superstructure ML17286B2741991-10-0808 October 1991 Forwards Rev 0 to Washington Nuclear Plant 3 Seismic Design Basis Model Validation,Soil Variation Studies, in Response to Open Items in Draft Safety Evaluation Re Soil/Structure Interaction/Deconvolution Issue ML17286B2661991-06-0707 June 1991 Requests Approval to Revise Tornado Design Criteria,Per Reg Guide 1.76,Section C.1.2 for Rotational & Translational Velocities. Justification for Revised Tornado Design Criteria Encl ML20073P9471991-05-13013 May 1991 Forwards Rev 5 to WMC-051, WNP-3 Preventive Maint Requirements by Equipment Type ML17286A5361991-01-0202 January 1991 Discusses Interpretation of 10CFR73,App B,Paragraph Ii.B Re Security Records Retention Period ML17286A3571990-10-12012 October 1990 Requests That Name Be Kept on Mailing List & That Firm Name Be Changed to Winston & Strawn in Response to 900927 Ltr ML20062A8981990-10-0101 October 1990 Responds to NRC Re Wish to Remain on Mailing List ML20059M0901990-09-27027 September 1990 Informs That Name Will Be Removed from Mailing List Unless Notification of Wish to Remain on List to Continue to Receive Info Re Facility Received within 30 Days ML20059M0921990-09-27027 September 1990 Advises That Name Will Be Removed from Mailing List Unless Notification of Wish to Remain on List to Continue to Receive Info Re Facility Received within 30 Days ML20059A5411990-08-16016 August 1990 Provides Notice of Changes in Key Personnel ML20056A7171990-07-27027 July 1990 Forwards Partial Vol 1 & Vols 4,5,6 & 7 of FSAR Re Potential Subduction Zones Earthquakes in State of Wa Coastal Area.W/O Encls ML20044A4931990-06-0808 June 1990 Requests That NRC Review of Facility Seismic Rept Completed & SER Issued as Soon as Possible.Facility Seismic Issue Resolution to Minimize Uncertainties Surrounding Economic Evaluations of Deferred Plants Important ML20042G3971990-05-11011 May 1990 Forwards Revised WMC-051, Washington Nuclear Plant-3 Preservation of Assets Program, Incorporating Changes Noted Through Preservation Experience & Successes Achieved in Improving Environ within Plant Bldgs ML20012B6941990-03-0101 March 1990 Forwards Compilation of Responses to Regulatory Impact Survey Questionnaire,Per Generic Ltr 90-01 ML19325D1831989-10-12012 October 1989 Confirms That Seismic Design Data Submitted Under Separate Cover to R Pichumani,Per 891003 Request ML20246N3191989-08-30030 August 1989 Forwards Addl Info Re Plant Soil Structure Interaction Analysis/Deconvolution Issue,Per 890213 Request.Results Presented in Encl Supplemental Rept Demonstrate Overall Significant Level of Conservatism in Seismic Design Basis ML20247R6131989-05-25025 May 1989 Documents Understanding of Agreements Re Geosciences Review & Preparation of Draft SER & Requests That Staff Schedule Geoscience Review to Be Completed by Sept 1989 in Order That Work Accomplished Currently Not Lost ML20247L3141989-05-11011 May 1989 Forwards Insp Rept 50-508/89-01 on 890413-14 & 0508.No Violations Noted ML17285A2071989-01-23023 January 1989 Forwards Wppss 1988 Annual Financial Rept.W/O Encl ML20206L7671988-11-21021 November 1988 Submits Addl Info in Response to Questions on Geosciences Program Clarifying Rates of Erosion Along State of or & State of Wa Coastlines Re Formation of Modern Wavecut Platforms.Questions Arose from NRC Sept 1988 Visit ML20153F4041988-08-29029 August 1988 Forwards Sassi Analysis & Further Clarification of Elastic Half Space Analysis Providing Confirmation That Finite Element Methodology Used for Plant Design Basis Sufficiently Conservative ML20153E2801988-08-26026 August 1988 Forwards Corrected Page 1 of NRC Forwarding Insp Rept 50-508/88-02 Re Readiness Review Module C3-02 Concrete. Ltr Issued W/O Date Annotated on First Page ML20153G4231988-08-22022 August 1988 Forwards Readiness Review Module C3-02 Concrete Insp Rept 50-508/88-02.Concrete Const Completed at Time of Work Stoppage Deemed Acceptable Assuming Open Items Resolved. Listed Items Will Be Pursued During Future Reviews & Insps ML20207G5251988-08-10010 August 1988 Forwards Plots Showing Computed Distributions of Frequency of Exceedance Displayed in Terms of Fractile Hazard Curves in Seismic Hazard Rept ML20150G0441988-06-30030 June 1988 Forwards Response to Questions 230.1 & 230.2 Re Resolution of Key Licensing Issues Concerning Questions on Cascadia Subduction Zone ML20196C3091988-06-17017 June 1988 Defers Responses to NRC Bulletins & Generic Ltrs Unless NRC Specifically Requests That Util Respond for Facility.Util Will Reply to Outstanding Bulletins & Generic Ltrs That Require Response Following Resumption of Const ML20154D2661988-05-16016 May 1988 Forwards Order Extending Const Completion Date to 990701 for Plant,Per Util 841102 & 860310 Requests.Safety Evaluation & Environ Assessment & Finding of No Significant Impact Also Encl ML20154R9251988-05-13013 May 1988 Responds to NRC Bulletin 88-003, Inadequate Latch Engagement in Hfa Type Latching Relays Mfg by Ge. Action on Bulletin Will Be Added to Plant Tracking Sys as Work to Be Accomplished Following Restart of Const ML20154F5901988-05-13013 May 1988 Informs That Assurance That Program Implemented to Address Corrosive Effects of RCS Leakage at Less than Tech Spec Limits Per Generic Ltr 88-05 Will Not Be Provided Until After Restart of Const ML20154F3191988-05-13013 May 1988 Advises That Due to long-term Const Delay Status of Plant, Action Re Suppl 1 to NRC Bulletin 87-002, Fastner Testing to Determine Conformance W/Applicable Matl Specs, Will Be Deferred Until After Restart of Const ML20151S4161988-04-21021 April 1988 Responds to Generic Ltr 88-03, Steam Binding of Auxiliary Feedwater Pumps. Commitment to Developing Procedures & Training for Recognizing Gas Binding Conditions & Restoring Operable Status of Safety Sys Still Valid ML20153G5781988-04-0505 April 1988 Advises That 880226 Changes & Corrections to Amend 7 of FSAR Section 17.3 Consistent W/Provisions of 10CFR50,App B & Acceptable ML20150D1301988-03-18018 March 1988 Forwards Responses to NRC 830503 & 11 Requests for Addl Info Re Application for Ol.W/Eight Oversize Drawings ML20148B5101988-03-15015 March 1988 Informs of Relocation of NRR to Stated Address in Rockville,Md ML20148G1241988-03-11011 March 1988 Forwards Insp Rept 50-508/88-01 on 880222-26.No Violations Noted ML20147J0341988-03-0707 March 1988 Responds to Sorensen Providing Proposed Schedule for Completion of Review of Geosciences Issues.Proposed Schedule Acceptable.Eforts Will Be Made to Accommodate Geosciences Issues for Facility ML20147H2741988-03-0404 March 1988 Informs That Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers, Delayed Until After Restart of Const ML20147D3841988-02-29029 February 1988 Forwards Seismic Hazards Assessment, Final Rept Per NRC 830503 Request for Addl Info Re Question 230.6 ML20147E1181988-02-26026 February 1988 Forwards Changes to FSAR Section 17.3, QA During Long-Term Preservation. Revised Section 17.3 Incorporated Into FSAR Amend 7 ML20149L9961988-02-23023 February 1988 Ack Receipt of 880205 Request for Info & Documents Re Certain Costs Billed to Util for June 1984 - Dec 1986 Review Period.Response Forthcoming ML20149M0031988-02-0505 February 1988 Requests Review of Details of Billings for Listed Periods & Transmittal of Copies of Billings for Periods of June 1984 - Dec 1984 & Dec 1984 - June 1985.Questions Delineated in Encl 1999-05-05
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20206S2911999-05-0505 May 1999 Informs That on 990420 Council Provided ten-day Comment Period on Council Order 731 Recommending Governor Approval of Amend of Site Certification Agreement for Satsop Power Plant Site ML20155J9731998-11-0505 November 1998 Forwards Addl Detailed Info Re Restoration & Renovation of Site Bldgs Re Util Plans to Renovate Site for Reuse as Industrial Park by Local Government Entity ML20116M7191996-08-0808 August 1996 Requests Termination of Construction Permit (CPPR-154) of Nuclear Project 3 & Withdrawal of Pending OL WNP-3 ML20082A7771995-03-28028 March 1995 Forwards WPPSS Nuclear Projects 1,3,4 & 5 Restoration Plan ML20078M4961995-02-0303 February 1995 Advises of Termination of Util Projects 1 & 3 ML20059B7681993-10-20020 October 1993 Requests Code Case N-520 Approval for Nuclear Projects 1 & 3 ML20057A6031993-09-0303 September 1993 Forwards Rev 6 to Procedure WMC-051, Preservation of Assets Program, Reflecting Installation of Two Desiccant Type Dehumidifiers for Controlling Relative Humidity within Reactor Auxiliary/Reactor Bldg Superstructure ML17286B2741991-10-0808 October 1991 Forwards Rev 0 to Washington Nuclear Plant 3 Seismic Design Basis Model Validation,Soil Variation Studies, in Response to Open Items in Draft Safety Evaluation Re Soil/Structure Interaction/Deconvolution Issue ML17286B2661991-06-0707 June 1991 Requests Approval to Revise Tornado Design Criteria,Per Reg Guide 1.76,Section C.1.2 for Rotational & Translational Velocities. Justification for Revised Tornado Design Criteria Encl ML20073P9471991-05-13013 May 1991 Forwards Rev 5 to WMC-051, WNP-3 Preventive Maint Requirements by Equipment Type ML17286A5361991-01-0202 January 1991 Discusses Interpretation of 10CFR73,App B,Paragraph Ii.B Re Security Records Retention Period ML17286A3571990-10-12012 October 1990 Requests That Name Be Kept on Mailing List & That Firm Name Be Changed to Winston & Strawn in Response to 900927 Ltr ML20062A8981990-10-0101 October 1990 Responds to NRC Re Wish to Remain on Mailing List ML20059A5411990-08-16016 August 1990 Provides Notice of Changes in Key Personnel ML20056A7171990-07-27027 July 1990 Forwards Partial Vol 1 & Vols 4,5,6 & 7 of FSAR Re Potential Subduction Zones Earthquakes in State of Wa Coastal Area.W/O Encls ML20044A4931990-06-0808 June 1990 Requests That NRC Review of Facility Seismic Rept Completed & SER Issued as Soon as Possible.Facility Seismic Issue Resolution to Minimize Uncertainties Surrounding Economic Evaluations of Deferred Plants Important ML20042G3971990-05-11011 May 1990 Forwards Revised WMC-051, Washington Nuclear Plant-3 Preservation of Assets Program, Incorporating Changes Noted Through Preservation Experience & Successes Achieved in Improving Environ within Plant Bldgs ML20012B6941990-03-0101 March 1990 Forwards Compilation of Responses to Regulatory Impact Survey Questionnaire,Per Generic Ltr 90-01 ML19325D1831989-10-12012 October 1989 Confirms That Seismic Design Data Submitted Under Separate Cover to R Pichumani,Per 891003 Request ML20246N3191989-08-30030 August 1989 Forwards Addl Info Re Plant Soil Structure Interaction Analysis/Deconvolution Issue,Per 890213 Request.Results Presented in Encl Supplemental Rept Demonstrate Overall Significant Level of Conservatism in Seismic Design Basis ML20247R6131989-05-25025 May 1989 Documents Understanding of Agreements Re Geosciences Review & Preparation of Draft SER & Requests That Staff Schedule Geoscience Review to Be Completed by Sept 1989 in Order That Work Accomplished Currently Not Lost ML17285A2071989-01-23023 January 1989 Forwards Wppss 1988 Annual Financial Rept.W/O Encl ML20206L7671988-11-21021 November 1988 Submits Addl Info in Response to Questions on Geosciences Program Clarifying Rates of Erosion Along State of or & State of Wa Coastlines Re Formation of Modern Wavecut Platforms.Questions Arose from NRC Sept 1988 Visit ML20153F4041988-08-29029 August 1988 Forwards Sassi Analysis & Further Clarification of Elastic Half Space Analysis Providing Confirmation That Finite Element Methodology Used for Plant Design Basis Sufficiently Conservative ML20207G5251988-08-10010 August 1988 Forwards Plots Showing Computed Distributions of Frequency of Exceedance Displayed in Terms of Fractile Hazard Curves in Seismic Hazard Rept ML20150G0441988-06-30030 June 1988 Forwards Response to Questions 230.1 & 230.2 Re Resolution of Key Licensing Issues Concerning Questions on Cascadia Subduction Zone ML20196C3091988-06-17017 June 1988 Defers Responses to NRC Bulletins & Generic Ltrs Unless NRC Specifically Requests That Util Respond for Facility.Util Will Reply to Outstanding Bulletins & Generic Ltrs That Require Response Following Resumption of Const ML20154R9251988-05-13013 May 1988 Responds to NRC Bulletin 88-003, Inadequate Latch Engagement in Hfa Type Latching Relays Mfg by Ge. Action on Bulletin Will Be Added to Plant Tracking Sys as Work to Be Accomplished Following Restart of Const ML20154F5901988-05-13013 May 1988 Informs That Assurance That Program Implemented to Address Corrosive Effects of RCS Leakage at Less than Tech Spec Limits Per Generic Ltr 88-05 Will Not Be Provided Until After Restart of Const ML20154F3191988-05-13013 May 1988 Advises That Due to long-term Const Delay Status of Plant, Action Re Suppl 1 to NRC Bulletin 87-002, Fastner Testing to Determine Conformance W/Applicable Matl Specs, Will Be Deferred Until After Restart of Const ML20151S4161988-04-21021 April 1988 Responds to Generic Ltr 88-03, Steam Binding of Auxiliary Feedwater Pumps. Commitment to Developing Procedures & Training for Recognizing Gas Binding Conditions & Restoring Operable Status of Safety Sys Still Valid ML20150D1301988-03-18018 March 1988 Forwards Responses to NRC 830503 & 11 Requests for Addl Info Re Application for Ol.W/Eight Oversize Drawings ML20147H2741988-03-0404 March 1988 Informs That Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers, Delayed Until After Restart of Const ML20147D3841988-02-29029 February 1988 Forwards Seismic Hazards Assessment, Final Rept Per NRC 830503 Request for Addl Info Re Question 230.6 ML20147E1181988-02-26026 February 1988 Forwards Changes to FSAR Section 17.3, QA During Long-Term Preservation. Revised Section 17.3 Incorporated Into FSAR Amend 7 ML20149M0031988-02-0505 February 1988 Requests Review of Details of Billings for Listed Periods & Transmittal of Copies of Billings for Periods of June 1984 - Dec 1984 & Dec 1984 - June 1985.Questions Delineated in Encl ML20150C4591988-01-13013 January 1988 Describes Basic Aspects of 871221 Meeting W/Util in Bethesda,Md Re Ssi/Deconvolution Issues Re Audit Finding 1 & Provides Recommendations for Resolving Associated Issues ML20234D7321987-12-21021 December 1987 Proposes Deferral of Response to Compliance Bulletin 87-002 Until After Restart of Const ML20236S9331987-11-23023 November 1987 Discusses Violation Noted During Insp Rept 50-508/82-04 Re Questionable Welds.Items Identified on Nonconformance Rept (Ncr 15313) & Implementation of Corrective Action Will Be Entered Into Site Tracking Sys & Accomplished at Restart ML20236X2531987-11-20020 November 1987 Forwards Addl Info Re Geosciences Program for Resolution of Key Licensing Issues on Seismicity of Western Area of State of Wa,Per NRC 870708 Request.Responses to Seismic & Ground Motion Questions Will Be Submitted Soon ML20236Q4451987-10-28028 October 1987 Requests Supporting Documentation Providing Basis for OL Application Review Costs for Period of 860622-1220. Documentation & Verification Requirements for Public Fund Expenditures Exist Since WPPSS Is State Municipal Corp ML20236A8001987-10-0808 October 1987 Forwards Description of Status of Plant Seismic Review,Per Request.Meeting Will Be Requested W/Util to Resolve Audit Finding 1 Issue ML20235J8801987-09-30030 September 1987 Forwards Revised FSAR QA Program Description (Section 17.3) Re Organizational Realignments,Effective on 870701,per Util .Qa Program During Plant Asset Preservation Stage Discussed ML20237H6771987-08-19019 August 1987 Proposes to Defer Response to Generic Ltr 87-12 Re Loss of RHR While RCS Partially Filled Until After Const Restart, When Resources Will Be Available.Deferral Will Allow Util to Consider in Response Info Gained by NRC ML20237H4791987-08-0707 August 1987 Requests Response to Re NRC Billings for OL Review & Insp Fees ML20235B8211987-08-0707 August 1987 Requests That Sending of Unneeded Circular Info Be Discontinued.School No Longer Has Nuclear Reactor ML20236N3711987-07-31031 July 1987 Forwards Addl Info Re Soil Structure Interaction Deconvolution Issue,Per NRC 870417 Request ML20236F6121987-07-29029 July 1987 Responds to Request for Info Re NRC Bulletin 87-001, Thinning of Pipe Walls in Nuclear Power Plants. Util Not Able to Submit Info at Present Time Due to Const Delay.Const Activities Will Not Resume Before 1994 ML20237G3911987-07-20020 July 1987 Requests Supporting Documentation Providing Basis for NRC Billing & Operating License Reviews & Insp Fees for 850623 Through 860621 ML20235M4401987-06-25025 June 1987 Forwards EGG-NTA-7673, Conformance to Generic Ltr 83-28, Item 2.2.2--Vendor Interface Programs for All Other Safety- Related Components:WNP-1/-3, Final Informal Rept 1999-05-05
[Table view] |
Text
-
h o .
WASHINGTON PUBLIC POWER SUPPLY SYSTEM Po. Box 968
- 3000 George washington way e Rkhland, Washington 99352-09t? (SO9) 372 5000 February 3,1995 GO1-95-0004 GO3-95-0026 Docket Nos. 50-460 and 50-508 Mr. James M. Taylor ,
Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Taylor:
Subject:
TERMINATION OF WASIIINGTON PUBLIC POWER SUPPLY SYSTEM NUCLEAR PROJECTS NOS.1 AND 3 In a letter of May 20,1994, I informed you that the Washington Public Power Supply System
(" Supply System") Board of Directors voted on May 13, 1994, to formally terminate the partially completed, and previously deferred, Supply System Nuclear Projects Nos.1 ("EP-1")
and 3 ("WNP-3"), at least in their current concept. This action resulted in termination of contract provisions between the Supply System and the Bonneville Power Administration
("BPA") for the two projects.
At that time, BPA agreed to assure funding, at least through January 13,1995, for WNP-1 and WNP-3 project preservation programs and maintenance of all state and federal permits and licenses in effect. This allowed the Supply System to study possible alternatives for completion, use, or disposition of the projects, while maintaining them in a deferred status consistent with the NRC's " Policy Statement on Deferred Plants" (52 Fed. Reg. 38,077 (1987)).
Since May 1994, the Supply System has studied alternatives for the projects, including the concept of completion of WNP-1 to burn mixed-oxide fuel made from the Department of Energy's weapons grade plutonium stockpile? The Supply System also offered the WNP-1 and WNP-3 projects for sale to any interested party. As of the present date, no new owner or alternative use for these projects has been identified.
9 This concept is discussed in the U.S. Depanment of Energy Plutonium Disposition Study, Technical Review Committee Report, July 2,1993 (two volumes). Sg: als2
" Notice ofIntent to Prepare a Programmatic EnvironmentalImpact Statement for Storage and Disposition of Weapons-Usable Fissile Materials," U.S. Department of Energy, 59 Fed. Reg. 31985 (June 21,1994). 7 j gRo214ojoo 9502os p ADOCK 0500046o "( Q PDR 4
u Mr. James M. Taylor TERMINATION OF NIiCLEAR PROJECTS NOS.1 AND 3 Page 2 Tna Supply System and BPA previously executed WNP-1 and WNP-3 Post-Termination Agreements, effective June 14,1994. The Post-Termination Agreements required the Supply System to p epare amended budgets for each of the two projects, to prepare Project Disposition Plans, and to comrience asset disposition activities after January 13,1995,in the event that the projects had not been redefined or sold in their entirety as NRC-licensed facilities prior to that date. Accordingly, on January 26,1995, the Supply System Executive Board approved amended :
Fiscal Year ("FY") 1995 Budgets and the related Asset Disposition Plans for WNb1 and WNP-3. The WNP-1 and WNP-3 amended FY-95 Budgets provide for the transition of the WNP-1 and WNP-3 projects from Plant Preservation Programs (Lt., " Deferred Status") to .
Termination Programs (albeit on different schedules). .
Under thm plans, budgets and resources for continued preservation of WNP-1 and WNP-3 will be reduced in a phased approach that maximizes presavation of assets. At WNP-3, the project preservation and maintenance program commitments, effective immediately, will be significantly reduced and re-directed to that end. The Supply System will concentrate its resources primarily '
on preserving the equipment for re-sale by maintaining storage environments. Maintenance will no longer be focused on equipment types (g4, maintaining mar.ufacturers' recommendations) t or on ultimate licensability of the project.
At WNP-1, storage environments will be preserved and maintenance of equipment by type will continue, although the latter often on a reduced fmquency. Because commencement of demolition and asset sales at the WNP-1 site at Hanford are dependent upon lessons learned at WNP-3, qualification of code equipment will be maintained longer at WNP-1. One incidental benefit of this plan, in addition to cost effectiveness, is that the viability (including licensing !
viability) of the WNP-1 project as a nuclear uni; is maintained for a period of time into the future.
In parallel with the Asset Disposition Plans, the Supply System has also been developing a revised comprehensive Site Restoration Plan for WNP-1 and WNP-3, as well as for the previously terminated Supply System Nuclear Project Nos. 4 ("WNP-4") and 5 ("WNP-5"). The Site Restoration Plan is being prepared to meet the requirements of the State of Washington Energy Facility Site Evaluation Council ("EFSEC") and is expected to be submitted to EFSEC ;
l in the near future. The Site Restoration Plan will call for demolition of structures and restoration of the sites to a level satisfying EFSEC mquirements. Initial restoration will occur l at the WNP-3/5 site.
The Supply System has begun an approximately six month process which includes the reduced staffing and disposition of assets at WNP-3, as described abov::, and selection of a contractor for the demolition and site restoration activities at WNP-3/5. Work will begin at WNP-3/5 as .
soon as a contractor can be selected and mobilized.
9 9 c. gr g. ,, , _ . , . - - -
j w .
l l
Mr. James M. Taylor -
i TERMINATION OF NUCLEAR PROJECTS NOS.1 AND 3 Page 3 ;
4 Site restoration at the WNP-1/4 site will not begin until after experience has been gained at l WNP-3/5 and confidence in the demolition process has been established. There is, thus far, no !
schedule for demolition at WNP-1/4. As wiously described, preservation will continue on l the WNP-1 project to the extent possible to maximize value of the assets, and incidently will j preserve the WNP-1 project for possible alternative uses.
In view of all of the above, from the psgtive of the Deferred Plant Policy Statement, both l the WNP-1 and WNP-3 projects are being transitioned _ towards final termination status. .!
I However, the Construction Permits (" cps") remain in effect and, in order to maximize the value i
of the projects and the equipment prior to site restoration, the Supply System is not yet requesting their termination. 'Ihe Supply System will retain the CP for each project until the commencement of site restoration. For WNP-3 this could begin later this year. For WNP-1 this will occur on a later schedule still to be determined.
i i We will keep you apprised of further developments on this subject, and intend to provide for your information a copy of the revised Site Restoration Plan when finalized and submitted to EFSEC. Should you have any questions or desire further information, the Supply System point :
of contact for this matter is Mr. D.W. Coleman, (509) 377-4342. l l
Very truly yours, l l4h W.G. Counsil I
Mrmaging Director (Mail Drop 387) cc: WT Russell - Director, NRR LJ Callen - NRC RIV KE Perkins, Jr. - NRC RIV, Walnut Creek Field Office MM Mendonca - NRR l