Rev 1 to Monthly Operating Rept for Jul 1983
ML20078K633
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 09/08/1983
From: Sarsour B
TOLEDO EDISON CO.
To:
Shared Package
ML20078K615 List:
References
NUDOCS 8310190170
Download: ML20078K633 (2)


Text

-

REVISION 1 OPERATING DATA REPORT DOCKET NO.

50-346 DATE Seotember 8, 1983 COMPLETED BY Bilal Sarsour TELEPHONE 419-259-5000, Ext. 384 OPERATING STATUS

1. Unit Name:

Davis-Besse Unit 1 Notes

. 2. Reporting Per".t:

July, 1983

3. Licensed Thermal Power (MWt):

2772

4. Nameplate Rating (Gross MWe):

925

5. Design Electrical Rating (Net MWe):

ons

6. Maximum Dependable Capacity (Gross MWe):

918

7. Maximum Dependable Capacity (Net MWe):

874

8. If Changes Occur in Capacity Ratings (Items Nuraber 3 Through 7) Since Last Report. Give Reasons:
9. Power Level To which Restricted. If Any (Net MWe):
10. Reasons For Restrictions.If Ar.y:

This Month Yr to-Date Cumulative

11. Hours In Reporting Period 744.0 5,087.0 43,848.0 12.- Number Of Hours Reactor Was Critical 588.4 4,591.2 25,486.7
13. Reactor Reserve Shutdown Hours 155.6 469.5 3,833.6
14. Hours Generator On.Line 588.4 4,538.8 24,298.4
15. Unit Reserve Shutdown Hours 0.0 0.0 1.732.5
16. Gross Thermal Energy Generated (MWH) 1.202.826 11.534.142 56.906,903
17. Gross Electrical Energy Generated (MWH) 394.838...

3.841.150 18,946,804

18. Net Electrical Energy Generated (MWH) 366.862 3,631,352 17,746,792
19. Unit Service Factor 79.1 89.2 55.4
20. Unit Availability Factor 79.1 89.2 59.4
21. Unit Capacity Factor (Using MDC Net) 56.4 81.7 46.3
22. Unit Capacity Factor (Using DER Net) 54.4 78.8 44.7 l 1l
23. Unit Forced Outage Rate 12.4 9.5 18.7 i
24. Shutdowns Scheduled Over Next 6 Months (Type. Date,and Duration of Each):

i

25. If Shut Down At End Of Report Period. Estimated Date of Startup:

September 20, 1983

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achiesed INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIA L OPER ATION (9/771 8310190170 830908 PDR ADOCK 05000346 R

PDR

,w,,_,

REVISION 1 50-346 UNIT SHUTDOWNS AND POW:dt REDUCliONS DOCKET NO.

UNIT NAME Davis-Besse Unit 1 DATE September 82,1983 COMPLETED ilY Bilal Sarsour REPORT MONTil July 1983 TELErilONE (419) 259-5000. Ext. 384 "E

-b, h

.! ?

3 h.!f k Licensee

,E*

Cause & Corrective No.

Date k

3g

.g jg5 Event 3,7 Attion to 8-

$5 jigg Repor y

Prevent Recurrence 8r mu i

6 t

1l 7

83 07 25 F

83.6 A

3 The reactor tripped due to Steam and Feedwater Rupture Control System (SFRCS) actuation.

1 8

83 07 29 s

72.0 C

9 A unit outage was initiated to per-e form scheduled maintenance and refueling work, i

Sce Operational Summary for further details.

t t

I 2

3 4

l F: Forced Reason:

Method:

Exhibit G. instructions S: Schedu!cd A Equipment Failure (Explain) 1-Manual for Preparation of Data 1

B-Maintenance of Test 2 Manual Scrarri.

Entry Sheets for Licensee C Refueling 3-Automatic Scram.

Event Report (l.ER) File (NUREG-D-Regulatory Restriction 4-Continuation from Previous Month 0161)

E. Operator Training & License Examination l 5-Load Reduction j

F Administrative 9-Other (Explain)

S G Operaniunal Eirur (lixplain)

Exliibit i Same Saurce (9/77) ll-Other (E xplain)