JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2
' NARRATIVE
SUMMARY
OF OPERATIONS SEPTEMBER, 1983 During the raonth of September, there was one-unit shutdown on September 16, 1983 which initiated the Cycle II - III refueling outage.
The following safety-related maintenance was performed in the month of September:
1.
Performed miscellaneous maintenance on diesel generators.
2.
Repaired 2C CCW pump.
3.
Performed vibration analysis on 2A CCW pump.
4.
Cleaned out 2A, 2B and 2C charging pump oil coolers and service water lines.
5.
Commenced core offload.
av 8310180134 831004 PDR-ADOCK 05000364 R
r OPERATING DATA REPORT DOCKET NO. 50-364 DATE 10/4/83 COMPLETED BY W. G.
Hairston, III TELEPHONE (2051899-5156 OPERATING STATUS X. Unit Name:
J seph M. Farley - Unit 2 Notes
- 2. Reporting Period:
September, 1983
- 1) Cumulative data since 2652 7/30/81, date of
- 3. Licensed Thermal Power (MWt):
860 commercial operation.
- 4. Nameplate Rating (Gross MWe):
829
- 5. Design Electrical Rating (Net MWe):
854.7
- 6. Maximum Dependable Capacity (Gross MWe):
813.7
- 7. Maximum Dependable Capacity (Net MWe):
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
N/A f
- 9. Power Level To Which Restricted. If Any (Net MWe):
N7A N/A
- 10. Reasons For Restrictions. If Any:
This Month Yr to-Date
~ Cumulative 720 6,551 19,032
. I1. Hours in Reporting Period 383.1 6,214.I 16,998.6
- 12. Number Of Hours Reactor Was Critical 0.0 0.0 N
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On.Line 383.0 6.214.0 16.816.4
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH) 937.869 16,355,802 41,777,616
- 17. Gross Electrical Energy Generated (MWH) 288,648 5,153,680 13,826,914
- 18. Net Electrical Energy Generated (MWH) 269.658 4.897.656 13.I13,706
- 19. Unit Service Factor 53.2 94.9 88.4
- 20. Unit Availability Factor 53.2 94.9 88.4
- 21. Unit Capacity Factor (Using ilDC Net) 46.0 91.9 84.7
- 22. Unit Capacity Factor (Using DER Net) 45.2 90.?
83.1
- 23. Unit Forced Outage Rate 0.0 0.0 5.0
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date,and Duration of Eachi:
N/A
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup: October 24. 1983
- 26. Units in Test Status (Prior to Commercial Operationi:
Forecast Achieved i
5/6/81 5/8/81 INITIA L CRITICA LITY INITIAL ELECTRICITY 5/74/R1 5/25/A1 COMMERCIAL OPERATION 8/1/81 7/30/81 (u!!7 i
-we,...__-_-.___..
~
DOCKET NO, 364 UNIT 2-1
^
DATT.
10/4/83 CO5tPLETED BY W. G. Hairston, III
- TELEPHONE (205)899-5156 september, 1983 MONT11
-DAY AVERACE DAILY POWER LEVEL DAY-AVERAGE DAILY POWER LEVEL (MWe Net)
(SIWE-Net)
I.
37 0
774 2
775 13 0
4 0
770 g9 3
0 4
746 gg 0
738 21 5
0 6
734 22 0
722 23 7
g 24 0
709 702 9
33 o
693 10 26 0
0 687 27 gg 678 0
g2 3
O 679 a
g3 680 0
I4 30 IS 31 612 16 i
f l
EISTRUCTIONS On this form:t. list the sversge daily unit power levelin MWe Net for each day in she reporting rnurith. Compute to l-
, the neste:t whole me;swatt.
(9(77) t 1
l l
UNIT Sil01 DOWNS AND POWER REDUCTIONS DOCKETNo.
50-364 UNIT NAM E J.M.
Farley-Unit 2 DAIE Y4 /_83 COMPLETED lly W.G.Hairston,III REPORT MONill September. 1983
~(765)899-5156 TELLPilONE "L
,hg 3 s[5 Licensee
,E.t, Cause & Corrective No.
Date g
3j g
3 Action to Event gg go F
y.c 5
ygc Report #
u in U Pacvent Recur:ence o
t c5 001 830916 s
337.0 C
1 N/A N/A N/A Unit was taken off line for the Cycle II - III refueling outage.
I 2
3 4
1:: l'orced Reason:
Method:
Exhibit G. insitucti
.n-S: Scheduled A Equipment Failure (Explain) 1 -Manual for Preparation of I).ii.,
il Maintenance of Test 2 Mannal Scram.
Ent:y Sheets for I.icen...-
C Refueling 3 Automatic Scram.
Event Report (1.ER)I & INtlREG-D Regulatmy Restriction 4 Other (limplain) 0161)
E Operator Training A license Examination F Adminisisative 5
G 0.ciational Essor (Explain)
Esinbit I - Same Sone.
6
('J/17)
II Of hes (Explain)
VrF e
i JOSEPH M. FARLEY NUCLEAR ?LANT UNIT 2 NARRATIVE
SUMMARY
OF OPERATIONS SEPTEMBER, 1983
'During the month of September, there was one unit shutdown on September 16, 1983 which initiated the Cycle II - III refueling outage.
The following safety-related maintenance was performed in the month of September:
1.
Performed miscellaneous maintenance on diesel generators.
2.
Repaired 2C CCW pump.
3.
Performed vibration analysis on 2A CCW pump.
4.
Cleaned out 2A, 2B and 2C charging pump oil coolers and service water lines.
5.
~ Commenced core offload.
i a
P
)
a OPERATING DATA REPORT DOCKET NO. 50-364 DATE 10/4/83 COMPLETED BY W. G. Hairston, III TELEPHONE (205)899-5156 OPERATING STATUS '
- l. Unit Name: J seph M. Farley - Unit 2 Notes
- 2. Reporting Period:
September, 1983
- 1) Cumulative data since
- 3. Licensed Thermal Power (MWt):
7/30/81, date of 2652 860
- 4. Nameplate Rating (Gross MWe):
commercial operation.
829
- 5. Design Electrical Rating (Net MWe):
854.7
- 6. Maximum Dependable Capacity (Grcss MWe):
813.7
- 7. Maximum Dependable Capacity (N A MWe):
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since.Last Report. Give Reasons:
N/A
- 9. Power Level To Which Restricted. If Any (Net MWe):
N7A N/A
- 10. Reasons For Restrictions.If Any:
This Month Yr. to-Date
' Cumulative
~
720 6,551 19,032 II. Hours in Reporting Period 38 6,214 16, 6
- 12. Number Of Hours Reactor Wu Critical
- 13. Reactor Reserve Shutdown Hours
- 14. liours Generator On Line 383.0 6 214.0 16.816.4
- 15. Unit Reserve Shutdown Hours 0.0
, O.0 0.0
- 16. Gross Thermal Energy Generated (MWH) 937,869 16,355,802 41,777,616
- 17. Gross Electrical Energy Generated (MWH) 288,648 5,153,680 13,826,914
- 18. Net Electrical Energy Generated (MWH) 269.658 4.897.656 13.I13,706
- 19. Unit Service Factor 53.2 94.9 88.4
- 20. Unit Availability Factor 53.2 94.9 88.4
- 21. Unit Capacity Factor (Using MDC Net) 46.0 91.9 84.7
- 22. Unit Capacity Factor iUsing DER Net) 45.2 90.2 83.I
- 23. Unit Forced Outage Rate 0.0 0.0 5.0 j
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date,and Duration of Eacht:
N/A
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup: October 24. 1983
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved 5/6/81 5/8/81 INITIA i. CRITiCAi.lT,
INITIAL ELECTRICITY s/74/R1 5/25/R1 COMMERCIAL OPERATION 8/1/81 7/30/81 pn
50-364 DOCKIT NO.
UNIT 2
Il DATE 10/4/83 I
W. G. Hairston, III COMPLETED BY TELEP110NE (205)899-5156 September, 1983 blONTil DAY AVERAGE DAILY POWER LEVEL DAY' AVERAGE DAILY POWER LEVEL (MWe Net)
(MWe-Net) 0 774 37 I.
775 13 0_,
2 0
770 g9 3
0
~
746 20 4
0 738 21 5
0 6
734
. E c
7 722 23 709 0
g 74 702 0
9 25-693 0
10
- g 0
687 27 11 0
678 3
12 0
679 29
(
13 680 0
l 14 30 IS 31 612 16 M UCEONS On this form:t. list the sversge daily umt power levelin MWe-Net for esch d:y in the reporting month.Campute to
, the neare:t whole mepwatt.
(9(77) 2
~
~
DOCKET NO.
50-364 UNIT Silll1 DOWNS AND POWER REDtEllONS UNIT NAhlE J.M. Farley-Unit 2 i
I)AIE Y4 /$6_3 COMPLETEI) IlY W.G.Hairston,III REPORT MON iil _ September, 1983 D S)899-5156 TEl.EP110NE I.
E E
jg
}
E
- Licensee
,E r,
" e.
Cause & Corrective
} s a}c g
.g Event g-gl Action to No.
Date g
3g mO o
p,,,en, geco,,coc, H
fE 3 gg c Repost
- oo l
e 6
j 1,
j 001 830916 s
337.0 C
1 N/A N/A N/A
, Unit was taken off line for the Cycle J
11 - III refueling cutage.
)
i, i
i i
1 i
I i
I
}
I 2
3 4
l': 17orted Reason:
hiettu>d:
Exhibit G. Instructin" S: St heiluted A Equipment Failure (Explain) 1 -klanual for Picparation of Data j
li Maintenance of Test 2 Manual Scram.
Entry Sheets for I.iten -
C Refocling 3 Autoniatic Scram.
Event Report (l.ER)14 iNilRfG-D Hegulatosy Resteiction 4 Odies (limplain) 0161) l~ Opciator Tealning A license Examination F Aihninistsative 5
G Opciational I.isor (limplain) thinbit 1 Same Soue.
l'8/17) 11 Othes (E xpl.iin)
Mdhg hMmp Alabama Power Company 600 North 18th Street Post Offica Box 2641 Birmingham Alabama 35291_
Telephone 205 783-6081 F. L Clayton, Jr.
%%;';0;Tf,*"'
A!abamaPbwer the southern electnc system October 12, 1983 Docket No. 50-364 Director, Office.of Management Information and Program Control U. S.: Nuclear Regulatory-Commission
. Washington, D.C.
20555
Dear Sir:
RE: Joseph M. Farley Nucicar Plant Unit 2 l,
Monthly Operating Data Report Attached are two (2) copies of the September, 1983 Monthly Operating Report for Joseph M. Farl ey Nucl ear Pl ant, Unit 2, required by Section 6.9.1.10 of the Unit 2 Technical Specifications.
As requested by letter from Mr. John F.
Stol z to Mr. Alan R. Barton, dated Octaber 21, 1977, a " Narrative Summary of Operating Experience" is included in the attached report.
If you have any questions, please advise.
Yours very truly, b6CId"(
'F.
Clayton J r.'
FL CJ r/KWM : n ac Enclosures xc: Mr. Ted Cintula (1 copy)
Director, IE (10 copies)
Director, RII (1 copy) t t
..-...