O ENTERGY We "' "" "'""* '
K m !A 70C06 k: iC.: in 6 n 4 R. F. Durski n n I,i y
>t
$1 f I'
'13 v
W3F1-94-0197 A4.05 PR November 11, 1994 U.S. Nuclear Regulatory Commission ATIN:
Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:
Attached is the subject monthly report which covers the operating statistics for the month of October, 1994.
This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.
Very truly yours, p
R.F. Burski Director Nuclear Safety RFB/DFL/ssf Attachment cc:
L.J. Callan (NRC Region IV)
C.P. Patel, NRC-NRR R.B. McGehee N.S. Reynolds F. Yost (Utility Data Institute, Inc.)
J.T. Wheelock (INP0 Records Center)
NRC Resident Inspectors Office
- Cisn c n 9411160247 941031 rStgJ i
PDR ADOCK 05000382 R
i 1
NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS WATERFORD 3 OCTOBER 1994 The unit operated at an average reactor power of 99.7% and experienced no shutdowns or significant pover reductions during the period.
p
PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3 During the month of October 1994, there were no pressurizer safety valve failures or challenges, I
d OPERATING DATA REPORT DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: NOVEMBER,1994 COMPLETED BY:
T.S. BECKER TELEPHONE: 504-739-6683 OPERATING STATUS 1.
Reporting Period: October,1994 Gross Hours in Reporting Period: ]45.
2.
Currently Authorized Power Level (MWt): 3390 Maximum Dependable Capacity (Net MWe): 1075 Design Electrical Rating (Net MWe): 1104 3.
Power Level to which Restricted (if any) (Net MWe): N/A 4.
Reasons for Restriction (if any): N/A THIS MONTH YR TO DATE CUMULATIVE 5.
Number of Hours Reactor was Critical 745.0 6,158.8 67,258.8 6.
Reactor Reserve Shutdown Hours 7.
Hours Generator was On-line 745.0 6,092.1 66,380.3 8.
Unit Reserve Shutdown Hours 9.
Gross Thermal Energy Generated (MWH) 2,518,011 20,346,243 219,374,720
- 10. Gross Electrical Energy Generated (MWH) 831,870 6,671,140_
73,091,920
- 11. Net Electrical Energy Generated (MWH) 796,287 6,356,247 69,666,692
- 12. Reactor Service Factor 100.0 84.4 84.3
- 13. Reactor Availability Factor 100.0 84.4 84.3
- 14. Unit Service Factor 100.0 83.5 83.2
- 15. Unit Availability Factor 100.0 83.5 83.2
- 16. Unit Capacity Factor (using MDC) 99.4 81.0 81.2
- 17. Unit Capacity Factor (Using DER) 96.8 78.9 79.1
- 18. Unit Forced Outage Rate 0.0 0.5 3.2
OPERATING DATA REPORT DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: NOVEMBER,1994 COMPLETED BY:
T.S. BECKER TELEPHONE: 504-739-6683 OPERATING DATA REPORT (Con'0 19.
Shutdowns Scheduled over next 6 Months (type, date and duration of each):
N/A 20.
If Shutdown at end of report period, estimat'ed date of startup:
21, Unit in Commercial Operation THIS MONTH YR TO DATE CUMULATIVE
- 22. Hours in Reporting Period 745.0 7,296.0 79,801.0
- 23. Unit Forced Outage Hours 0.0 31.5 2,210.2 24.
Nameplate Rating (Gross MWe): 1200 25.
If Changes Occurin Capacity Ratings (ltems Number 2 and 24) Since Last Report, Give Reason-s: N/A N
J
1 AVERAGE DAILY UNIT POWER LF. dL DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: NOVEMBER,1994 COMPLETED BY:
T.S. BECKER TELEPHONE: 504-739-6683 MONTH OCTOBER.199,_
2 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-NET)
(MWe-NET) 1 1068 17 1074 2
1068 18 1073 3
1067 19 1073 4
1068 20 1075 5
1068 21 1073 6
1069 22 1073 7
1068 23 1073 8
1068 24 1073 9
1068 25 1074 10 1070 26 1074 11 1069 27 1073 s
12 1069 28 1075 13 1071 29 996 l
14 1074 30 1072 15 1074 31 1074 16 1072 j
INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.
Compute to the nearest whole megawatt.
\\
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3
- DATE OF REPORT: NOVEMBER 1994 COMPLETED BY:
T.S. BECKER TELEPHONE-504-739-6683 REPORT FOR OCTOBER.1994 Type Method of Shutting I-2 Forced Duration Down the Reactor or Cause, Comments and Number Date S = Scheduled (Hours)
Reason (1)
Reducina Power (2)
Corrective Actions NONE (1) REASON (2) METHOD A=
Equipment Failure (explain) 1=
Manual B=
Maintenance or Test 2=
Manual Scram C=
Refueling 3=
Regulatory Restriction 4=
Continuation from Previous Period E=
Operator Training and 5=
Power Reduction License Examination 6=
Other (explain)
F=
Administrative G=
Operational Error (explain)
H=
Other (explain)
-