Affidavit of Vs Boyer Re Review of Welds in 1976 Under Responsibility of QC Inspector.Certificate of Svc Encl
ML20078G050
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 09/29/1983
From: Boyer V
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To:
Shared Package
ML20078G048 List:
References
NUDOCS 8310110307
Download: ML20078G050 (6)


Text

- . -

_- .. . _=. _ . .

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board 4

! In the Matter of )

)

Philadelphia Electric Company ) Docket Nos. 50-352

) 50-353 (Limerick Generating Station, ) ,

Units 1 and 2) )

AFFIDAVIT OF VINCENT S. BOYER'

- SENIOR VICE PRESIDENT,. NUCLEAR POWER PHILADELPHIA ELECTRIC COMPANY Vincent S. Boyer being first duly sworn according to law

- deposes and states:

1. On September 16, 1983, I executed an affidavit which was submitted to the Atomic Safety and Licensing Board dealing with the Company's review of welds which in 1976 were the responsibility of 1 a certain Quality Control inspector. That affidavit indicated that the review was continuing. The purpose of this affidavit is to up-date and correct information previously reported.
2. To reflect the current status of the review, paragraphs 12 and 13 of the September 16, 1983 affidavit would be modified as set forth below with the reasons for these changes being discussed here-with and in subsequent paragraphs.

12' As a result of this extensive review, it waa determined t

that the subject inspector had responsibility for a total of 1

1235 safety-related weld inspections at the facility, of which 654 were structural welds and 581 were on components other than 8310110307 831004 gDRADOCK 05000352 PDR

2 -

structural steel, such as hangers (577), pipes (2), and electrical conduit supports (2).

13' It was also determined that the review program which was initiated as a result of NRC Inspection Report 76-06 and completed by the end of July, 1977 had identified 426 structural .. elds, 423 being accessible and 3 inaccessible.

The 423 accessible welds were reinspected with 6 minor defi-ciencies noted. Four of these werp reworked, and 2 were found acceptable by engineering analysis. The 3 inaccessible welds were found by engineering analysis to be acceptable.

The extensive August, 1983 review identified 228 additional structural welds, 16 being totally accessible and 212 partially or totally inaccessible. The 16 totally accessible welds have now been reinspected with one minor deficiency found. This weld, together with the 212 partially or totally inaccessible welds, have been found by engineering analysis to be acceptable.

The non-structural welds, totalling 581, are all totally accessible. Of these, 577 represent hanger welds with 534 of the 577 being welds of hangers which were completely reinspected prior to August, 1983 as part of a separate hanger inspection program. The remaining 43 hanger welds for which final in-spections had not yet been made, together with the 4 non-hanger welds, have now been reinspected. These hangers contained 19 l minor deficiencies which would have normally been dispositioned  ;

as part of the final hanger completion and inspection program. .

They, instead, will be specially dispositioned within one week.

3 -

3. The number of structural welds previously reported was reduced from 662 to 654 due to the elimination of 8 welds which, in 1976, were classified as safety-related welds but due to their location and function, were subsequently reclassified as non-safety related welds.

l

4. In the interest of reporting all possible safety-related welds which could be considered to be the responsibility of the subjectinspector,anumberoffweldswhichwereinitiallyexamined by him, but which were subsequently reinspected for programmatic reasons beginning in late 1980, are being included. This explains the increase, noted above, in the number of safety-related non-structural welds from 47 to 581. In December, 1980 a general hanger reinspection program was initiated due to job conditions which re-sulted in additional hanger work being required after partial in-spections had been performed. This reinspection program required a final sec inspection of all welds of all safety-related hangers regardless of their previous inspection status. The subject in-spector had made inspections of 534 welds on partially completed hangers which had subsequently been subject to modification and completely reinspected prior to August, 1983. A current reinspection by Philadelphia Electric Company of 60 of these 534 completed hanger welds was performed with one minor deficiency being detected which has been found by engineering analysis to be acceptable.
5. The reported numbers relating to the review program of safety-related structural welds completed by the end of July, 1977 are chang,ed due to the initial inclusion of non-safety grade welds in the inaccessible count and a corresponding error in the breakdown

4 -

of the number of accessible and inaccessible welds. The corrected count is that by the end of July, 1977, 423 accessible welds were reinspected (corrected from 403) and 3 inaccessible welds (corrected from 31) were identified and dispositioned satisfactorily where re-quired.

6. The company's physical reinspection program, as reported in paragraph 14 of the September 16, 1983 affidavit, involved further 9

physical reinspection of 67 safety-related structural welds. Fifteen of these were from the 1983 reinspection group of 16 accessible welds discussed in paragraph 13 of the Septenber 16, 1983 affidavit and 52 were from the 1976/77 reinspection group of 423 accessible welds.

Six deficiencies were identified from the latter group, and these have been found by engineering analysis to be acceptable.

__ q Vincent S. Boyer Sworn to me this M date of Ei9TEMI6f/D - , 1983 Notary Public Ok PATRICIA D. SCHOLE Notwy Put,l.c Philadelphia. Philadeichia Co.

My Commission Expires February 10, 1936

T UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

Philadelphia Electric Company ) Docket Nos. 50-352

) 50-353 (Limerick Generating Station, )

Units 1 and 2) )

f CERTIFICATE OF SERVICE I hereby certify that copies of " Applicant's Second Interims Report to Licensing Board Relating to Contention VI-1" dated October 4, 1983, in the captioned matter have been served upon the following by deposit in the United States mail this 4th day of October, 1983:

Judge Lawrence Brenner (2) Docketing and Service Section Atomic Safety and Licensing Office of the Secretary Board U.S. Nuclear Regulatory U.S. Nuclear Regulatory Commission Commission Washington, D.C. 20555 Washington, D.C. 20555 Ann P. Hodgdon, Esq.

Judge Richard F. Cole Benjamin H. Vogler, Esq.

Atomic Safety and Licensing Counsel for NRC Staff Board Office of the Executive U.S. Nuclear Regulatory Legal Director Commission U.S. Nuclear Regulatory Washington, D.C. 20555 Commission Washington, D.C. 20555 Judge Peter A. Morris Atomic Safety and Licensing Atomic Safety and Licensing Board Board Panel U.S. Nuclear Regulatory U.S. Nuclear Regulatory Commission Commission Washington, D.C. 20555 Washington, D.C. 20555 Atomic Safety and Licensing Philadelphia Electric Company Appeal Panel ATTN: Edward G. Bauer, Jr.

U.S. Nuclear Regulatory Vice President &

Commission General Counsel Washington, D.C. 20555 2301 Market Street Philadelphia, PA 19101

Mr. Frank R. Romano David Wersan, Esq. Consumer 61 Forest Avenue As'istant s Advocate Ambler, Pennsylvania 19002 Office of Consumer Advocate 1425 Strawberry Square Mr. Robert L. Anthony Harrisburg, PA 17120 Friends of the Earth of the Delaware Valley Steven P. Hershey, Esq.

P. O. Box 186 Community Legal 103 Vernon Lane Services, Inc.

Moylan, Pennsylvania 19065 Law Center North Central Beury Bldg.

Mr. Marvin I. Lewis 3701 North Broad Street 6504 Bradford Terrace Philadelphia, PA 19140 Philadelphia, PA 19149 Angus Love, Esq.

Judith A. Dorsey, Esq. 101 East Main Street 1315 Walnut Street Norristown, PA 19401 Suite 1632 Philadelphia, PA 19107 Mr. Joseph H. White, III 8 North Warner Avenue Charles W. Elliott, Esq. Bryn Mawr, PA 19010 Brose and Postwistilo 1101 Building Robert J. Sugarman, Esq.

lith & Northampton Streets Sugarman & Denworth Suite Easton, PA 18042 '

510 North American Building 121 South Broad Street Jacqueline I. Ruttenberg Philadelphia, PA 19107 Keysteon Alliance 3700 Cnestnut Street Director, Pennsylvania Philadelphia, PA 19104 Emergency Management Agency Basement, Transportation Thomas Y. Au, Esq. and Safety Building Assistant Counsel Harrisburg, PA 17120 Commonwealth of Pennsylvania DER Martha W. Bush, Esq.

505 Executive House Kathryn S. Lewis, Esq.

P.O. Box 2357 City of Philadelphia Harrisburg, PA 17120 Municipal Services Bldg.

15th and JFK Blvd.

Thomas Gerusky, Director Fhiladelphia, PA 19107 Bureau of Radiation Protection Spence W. Perry, Esq.

Department of Environmental Associate General Counsel Resources Federal Emergency 5th Floor, Fulton Bank Bldg. Management Agency Third and Locust Streets 500 C Street, S.W., Rm. 840 Harrisburg, PA 17120 Washington, DC 20472 Jay M. Gutierrez, Esq.

U.S. Nuclear Regulatory Commission Region I G31 Park Avenue King of Prussia, PA 19406

/

Marl ( Jf Wetterhahn