Forwards Cycle 1 Startup Rept 3 & All Test Conditions 4 & 5 Covering Addl Portions of Testing Specified for Test Conditions by FSAR Figure 14.2-2 Not Included in to NRC
ML20078A883
Person / Time
Site: LaSalle Constellation icon.png
Issue date: 09/12/1983
From: Schroeder C
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20078A886 List:
References
7286N, NUDOCS 8309230450
Download: ML20078A883 (2)


Text

___ ..

i

'. Commonwealth Edison

' f/tNb 1 j > One First National Pitzs, Chic 4go, Ilknois

~

a i '

Address Reply to: Post Office Box 767 '

FRINCf PAL STAFF S

Chicago, tilinois 60690 RA djLggy I g gg September 12, 1983ch, 4D M'AA $C DF61SP OE Mr. James G. Keppler, Regional Administrator at Directorate of Inspection and .ot g te gg Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

LaSalle County Station Unit 1 Cycle 1, Startup Report #3 NRC Docket No. 50-373 References (a): License NPF-11, Technical Specifications 6.6.A.1, Startup Report.

(b): C. W. Schroeder letter to J. G. Keppler dated March 11, 1983.

(c): C. W. Schroeder letter to J. G. Keppler dated June 24, 1983.

(d): Regulatory Guide 10.1, Compilation of Reporting Requirements for Persons Subject to NRC Regulations.

Dear Mr. Keppler:

Reference (a) requires:

"A summary report of plant startup and power escalation testing shall be submitted following (1) receipt of an operating license, (2) amendment to the license involving a planned increase in power level, l

(3) installation of fuel that has a different design or has been

, manufactured by a different fuel supplier, and (4) modifications that may have significantly altered the nuclcar, thermal, or hydraulic performance of the plant. The report shall in general include a description of the measured values of the operating conditions or characteristics obtained during the test program and a comparison of these values with design predictions and specifications. Any corrective actions that were required to obtain satisfactory operation shall also be described. Any additional specific details required in license conditions based on other commitments shall be included in this report.

Startup reports shall be submitted within (1) 90 days following completion of the startup test program, (2) 90 days following resumption or commencement of coomercial power operation, or (3) 9 months following initial criticality, whichever is earliest. If the startup report does not cover all three events (i.e., initial 8309230450 830912 PDR ADOCK 05000373 P pop SEP 20 Gd3 f ol gl

~

r, .

. r

. ~

i

=,.

^

.c J. G.1Keppler. - 2;-- September'12,11983 criticality, completion of startup test program, and resumption or commencement ofl commercial; power-operation),' supplementary reports shall2 be : submitted "at' least- every 3 months until all three events have:been completed." i

" Initial criticality'on Unit 1 occurred on~ June 21,-1982.. Other

.. Unit-1, Cycle-1-Startup Reports were submitted to you.by Reference'(b) fand:(c).; '

iThel purpose-of.this' letter is to provide you with the test

. reports covering those additional portions of testing specified for Test LConditionsiby FSAR1 Figure-14.'2-2 which were performed. The attached

reports cover the portion of-Test Condition 3.not. covered in Reference (c)-and all'of Test Conditions 4'and 5. Reports. covering the remainder of,the-testing prescribed by1 Figure 14.2-2 at Test Condition 6 and Warranty ~Run will be submitted at 3 month intervals until testing is
complete.-~Please note that all required testing for. Test Numbers 8 and
21 have now been completed.

To the best of my knowledge and belief the statements contained

'herein and in the attachment are true and correct. In some respects these statements are not based on my personal knowledge but upon infor-mation furnished by other Commonwealth Edison and. contractor employees.

-Such information has been reviewed in accordance with Company practice and I believe it-to be reliable.

In accordance with the guidance of Reference (d), two (2)' copies are being-provided'to:the-Region'III' Office and, by copy of this. letter, thirty-six1(36) copies are being providedLdirectly to the Director, Office of Inspection and: Enforcement,.U.S.. Nuclear Regulatory Commission, fWashington, D.C. 20555, Attn: Document. Control' Desk.

~ If there are any questions regarding this-submittal, please contact this' office.

Very truly yours,.

v2.a =J - 9ja)g C. W. Schroeder Nuclear Licensing Administrator

~

fim .

_.cc:1-NRC. Resident Inspector - LSCS-1 Director, Office of. I&E - 36