Forwards Scope of Participation & Exercise Objectives for 831115 Emergency Exercise.Encl Satisfies Exercise Milestone Commitment
ML20077M167
Person / Time
Site: Byron  Constellation icon.png
Issue date: 08/30/1983
From: Jonathan Barr
COMMONWEALTH EDISON CO.
To: Hind J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20077M160 List:
References
1290D, NUDOCS 8309120236
Download: ML20077M167 (3)


Text

.

/

\\ Commonwealth Edison O

/ 72 Wast Adtms street. chic 790. Ilknois Fil;!CIRAL Eri/ #~

.(/ O ~J Address R; ply to: Post Office Box 767 l

IFT gj Chicago, Illinois 60690 Q

- g 1 k.f August 30, 1983 7,

jac !

i

'Y/

N7N l

Mr. Jack Hind, Director dreb fi

/M I

Radiological Materials Safety Program v ^

I M

U.S. Nclear Regulatory Commission Region III ut t

W LE I/2 '

799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Byron Station Emergency Exercise, November 15, 1983 NRC Docket Wmbers 50-454, 50-455 Please find enclosed the Scope of Participation and Exercise Objectives for the Byron Exercise scheduled for Tuesday, November 15, 1983.

This suomittal satisfies the 75-day prior to the exercise milestone committment.

Should you have any questions regarding the Byron Exercise please contact me at (312) 294-8145 or Carol Nellis at (312) 294-8154.

Sincerely, BL James R. Barr Lead Emergency Planner North Team Technical Services Nuclear JRB/CAN/kjn

  1. 06940/27 Enclosures cc: Mr. Dan Bement, Acting Chief Technological Hazards Branch FEMA, Region V Federal Center Battle Creek, MI 49016 Mr. E. Erie Jones, Director, Illinois ESDA 110 E. Adams Street Springfield, IL 62706 Mr. David Wlse, Deputy Director, Illinois ESDA 110 E. Adams Street Springfield, IL 62706 Mr. Steve Dunas Illinois Dept. of Nuclear Safety 1035 Outer Park Drive Springfield, IL 62704 CECO:

J. C. Golden, Technical Services W clear G. P. Wagner, Technical Services Nuclear Wclear Station Division D. L. Farrar, Nuclear Licensing Aoministration R. E. Querio, Superintendent, Byron Station 8309120236 030907 PDR ADOCK 05000454 SEP 1123 F

PDR

Byron Exercise OBJECTIVES PRIMARY OBJECTIVE:

Demonstrate the capability to implement the Commonwealth Edison Generating Stations Emergency Plan in cooperation with the Illinois Plan for Radiological Accidents to protect the public in the event of major accident at the Byron Station.

SUPPORTING OBJECTIVE:

1.

Demonstrate the capability to classify accident conditions and make timely reports in accordance with the GSEP.

2.

Demonstr5 te the capability to activate the TSC, EOF, & CCC with directors and appropriate staff in accordance with procedures.

3.

Demonstrate the capability to interface in a timely and effective manner with the principal offsite organi::ations responsible for responding to a radiological emergency.

4.

Demonstrate the capability to exercise initial control of off-site environmental activities, transfer control to appropriate state agencies and coordinate employnent of CECO.

environmental resoun:es in support of state controlled environmental activities.

5.

Demonstrate the capability to conduct in-plant radiation protection activities and collect and simulate anclysis of air or liquid samples.

6.

Demonstrate the capability of environmental fiald teams to conduct field radiation surveys and collect air, liquid, vegetation and soll samples.

7.

Demonstrate the capability to calculate off-site dose projections in coordination with governmental agencies.

8.

Demonstrate the capability to communicate reports, information and assessments of the situation among all participating principal command and control centers.

9.

Demonstrate the capability to process infornation and take appropriate action in accordance with plans and procedures.

10.

Demonstrate the capability to contact organizations that would normally assist in the given emergency situation, but are not fully participating in this exercise.

11.

Demonstrate the capability to provide initial care of a radiologically contaminated casualty, arrange transport and assist the medical treatment facility with contamination control in accordance with plans and procedures.

  1. 1290D

=~

SCOPE OF PARTICIPATION Commonwealth Edison will participate in the Byron exercise by activating the on-site emergency response organization and the off-site

' emergency response organization as appropriate, subject to limitations that may become necessary to provide for safe efficient operation of the Byron and other CECO nuclear generating stations.

Activation of the -TSC and other on-site participants will be conducted on a real time basis during the day time hours. The shif t on duty will receive the initial scenario information and respond accordingly.

The Nuclear Outy Person and the balance of the Recovery Group will be prepositioned close to the Dixon EOF to permit use of Recovery Group personnel from distant locations.

The Corporate Command Center will be activated.

Commonwealth Edison will demonstrate the capability to make contact with contractors whose assistance would be required by the simulated accident situation, but will not actually incur the expense of using contractor services to simulate emergency response except as prearranged specifically for the exercise.

_ Commonwealth Edison will arrange to provide actual

. transportation and communication support in accordance with existing agreements to.the extent specifically prearranged for the exercise.

Commonwealth Edision will provide unforeseen actual assistance only to-the extent the resources are available and do not hinder normal operation

'of the company.

On-site assembly and accountability will be simulated during this exercise. Assembly and accountability will be demonstrated by Byron Station at a date and time selected to minimize disruption of construction work in progress.

  1. 12900/2 I