-_ _ _ _ _ _ _ _ _ _ _ _ - _ - _ _ _
I OUISIANA P O W E F1 & L 1 G H Ij P o nox 0000 24,ouonoNOc sin m
. NEW OHLI ANS LOUISIANA 70174 ISO 4) 366 2345
[ITIi 5s(S$rYU July 29, 1983 W3183-0259 Q-3-A35.07.79 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission gg g'
i gj 611 Ryan Plaza Drive, Suite 1000
=
Arlington, Texas 76012
SUBJECT:
Waterford SES Unit No. 3 i
Docket No. 50-382 L
d
[6 Significant Construction Deficiency No. 79
" Unqualified Components in liydrogen Analyzers" Third Interim Report
REFERENCE:
LP6L letter W3183-0211 dated June 15, 1983
Dear Mr. Collins:
l The above referenced letter indicated submittal of a Final Report to the USNRC no later than July 29, 1983.
At the present time, documentation is being prepared to initiate the installation of the qualified replacement pump motors. This installation is expected to be complete by the end of August.
A Final Report will therefore be submitted to the USNRC by September 16, 1983.
Very trul
- yours,
/l
{d w n-F. J. Drummond Project Support Manager - Nuclear FJD/WAC/ MAL:keh cc:
- 1) Director 3)
Mr. E. L. Blakc Offico of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
20555
- 2) Director 4)
Mr. W. M. Stevenson Office of Monagement Informertion and Program Control
- 0. S. Nuclear Reguletory Commist. ion Waohington, D. C.
20555 0308160407 030729 PDM ADOCK 05000302 s