1

' ' , ' o '.,

i UNITED STATES OF AMERICA -

NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board l

In the Matter of )

)

j. THE CLEVELAND ELECTRIC ) Docket Nos. 50-440 ILLUMINATING COMPANY, ET AL. ) 50-441

)

(Perry Nuclear Power Plant, )

Units 1 and 2) )

AFFIDAVIT OF CYRIL M. SHUSTER

' County of Lake )

State of Ohio )

Cyril M. Shuster, being duly sworn, deposes and says as follows:

1. I, Cyril M. Shuster, am Manager, Corporate Nuclear Quality Assurance Department (CNQAD), The Cleveland Electric Illuminating Company. My business address is 10 Center Road, Perry, Ohio 44081. A statement of my professional qualifications and experience is attached hereto. I have personal knowledge

! of the matters set forth herein and believe them to be true and correct.

2. I have reviewed NRC Inspection Report No. 50-440/

83-13(DE); 50-441/83-12(DE)(the Inspection Report), which

[ was transmitted to CEI by letter dated July 25, 1983. The l

I I

B308120130 830810 PDR ADOCK 05000440 0 PDR t - - _ _ _

( . .

Inspection Report resulted in a severity level V violation, as indicated in the Notice of Violation attached to the Report.

i i

I am the Chairman of the Quality Assurance Advisory Committee (QAAC) and have personal knowledge of matters relating to i

the QAAC issues that were the subject of the Notice of Violation.

j In addition, I have the responsibility for preparing CEI's response to the Notice of Violation. That response is now in preparation, and will be filed not later than August 24, l

1983, as required-in the Notice.

3. A description of the QAAC is set forth in CEI's prefiled testimony in the above-captioned proceeding, following Tr. 1031, at page 24. As described in the testimony, CEI established the QAAC to provide consultation and advice to CEI's Vice-President, Nuclear Group, on significant QA policy issues. The QAAC reviews a variety of QA program documents, including CNQAP quarterly reports, performance analysis reports (PARS), selected internal audits, NRC inspection reports, I significant nonconformance reports, audit reports, corrective l action requests, and stop work notifications. QAAC members also observe site activities and interview site personnel involved in quality related activities.

L

4. The Notice of Violation identifies procedural discrep-ancies in connection with QAAC activities in 1981 and 1982.

The first finding described in the Notice is that the QAAC held two, rather than four, formal meetings in 1981, contrary i

to the QAAC Charter. A third " informal undocumented" meeting was held in September 1981. See Inspection Report, p. 5.

This consisted of site tours of three nuclear plants by three members of the QAAC. The purpose of the site tours was to evaluate various aspects of the quality assurance programs at those plants for possible applicability to Perry. The December 1981 QAAC meeting was postponed until January 1982.

The QAAC held four formal meetings in 1980.

5. The NRC's second QAAC scheduling concern is that "two conflicting procedure instructions appeared to be in effect for approximately two months in 1982." See Report, pp. 4-5; Notice of Violation. During these two months one instruction provided for biannual meetings and another provided for quarterly meetings. Despite the discrepancy in the 1982 QAAC scheduling instructions, the QAAC held eight formal meetings i Thus far the QAAC has held six formal meetings in in 1982.

1983. Although the QAAC charter currently provides for quarterly meetings, we intend to continue to meet on a frequent basis.

6. The remaining QAAC item discussed in the Notice of Violation and the Inspection Report concerns the QAAC's review of PARS and other Perry quality documents. The Inspec-tion Report at page 5 does acknowledge the statement of the QAAC member interviewed that PARS were available and reviewed by the QAAC in 1981, although this review was not documented. As

indicated in 53, above, the QAAC has and will continue to review PARS and other quality documents, and will continue to monitor individual contractor performe.nce. ,

I 4/24 cyril M, /Snuster Subscribed and sworn to before me this 9 & ay d of August, 1983

/ W '

NOTARY PUBLIC

/

  1. 7 '

9 BAROUNE M. WfLDE Rotary Public, State of Ohio Ny Commission Expires April 17,1985 (Recorded in Lake County) e

.,-.-,---,,r.- , , , - , - -,,---,-.-e---- - - , nn . ..--

7s *

' ^

    • CYRIL M. SHUSTER I

i l MR. CYRIL M. SHUSTER, General Supervising Engineer, Nuclear Project Training Section of CEI, is a 1954 graduate of Case Institute of Technology with a B.S. degree in Electrical Engineering, and a 1963 graduate of Case Institute of Tech-nology with an M.S. degree in Engineering Administration.

He joined CEI in 1954 as an Engineering Assistant, in the System Planning Department. He was later assigned to the J, position of Associate Engineer. In 1962, he was appointed 1

Engineer, where he was responsible for designing protection systems for the electrical power system. In 1963, he served l for eight months as Electrical Test Foreman, (on Rotation of Assignment) where he was responsible for the testing and maintenance of electrical control and relay equipment.

l

In 1967, he was assigned to the position of Senior Engineer.

i He was responsible for the direction and design of protection

[ plans for power system applications. He participated in a series of Rotation of Assignments from 1975 to 1977, as General i Supervisor of Customer Engineering responsible for the design

of the facilities required for Commercial and Industrial cus-tomers. As General' Supervising Engineer for Electrical Projects l Engineering, he was responsible for the overall design of
all company transmission and distribution stations. He served as Acting Manager of Plant Substation Engineering Department responsible for the design of all company transmission and distribution substations and all plant electrical facilities.

In 1977, he was assigned to General Supervising Engineer, System Protection Section, responsible for automatic protec-tion systems and automatic control systems for application ,

on the Electrical Power System.

Concurrent with his other responsibilities, Mr. Shuster served l as Engineering Training Coordinator from 1968 to 1976. He was responsible for coordinating the training program for i new engineering personnel to provide broad training on power

[ system design methods.

In 1982, he was named to the position of General Supervising Engineer, Nuclear Project Training Section. He is responsible for directing the development and coordination of training to assure that the Perry Plant is staffed with trained, qual-ified individuals capable of supporting, maintaining and operating the Perry Plant.

In December 1982, he was named to his present position of l Manager, Nuclear Quality Assurance Department. He is responsible l for directing all quality assurance and quality control.activ-ities for the Perry Plant.

ra e -

w4 ewgr-w-, g. *w- -n, r w , e-r---e- =g y - - = ,p- v-i--.-e==w==m,w* e-*w w1,- r--r >c a S- ds y v -y* t*-w1- ww e-

a, .

Mr. Shuster is a registered professional engineer and holds -

professional memberships in the following organizations:

The Electric Power Research Institute, Institute of Electrical and Electronic Engineers, and the Cleveland Engineering Society.

In addition, he is the CEI representative on the Power System Planning and Operations Task Force. He is Chairman of Under-frequency Protection Working Group of Power Relay Committee.