Fifth Interim Rept Re Significant Const Deficiency 53 Concerning Possible Failure of GE Type Hfa Relays.Corrective Action Delayed Due to Testing.Coil Installation Completion Expected Early Sept 1983.Final Rept by 830930
ML20077H138
Person / Time
Site: Waterford Entergy icon.png
Issue date: 07/25/1983
From: Drummond F
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3I83-0245, W3I83-245, NUDOCS 8308090625
Download: ML20077H138 (1)


Text

. - .

I OUISIANA 242 oeLAnoNoe s1neer P O W E R & L 1 G H T! P O. BOX 6008

  • (504) 360-2345 July 25, 1983 W3183-0245 Q-3-A35.07.53 Mr. John T. Collins, Regional Administrator, Region IV T]@ ))\V][g 3 U. S. Nuclear Regulatory Commission  :

611 Ryan Plaza Drive, Suite 1000 g29@  !

Arlington, Texas 76012 dl

SUBJECT:

Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 53 "Possible Failure of General Electric Type HFA Relays" Fifth Interim Report

REFERENCE:

LP&L letter W3I83-0212 dated June 15, 1983

Dear Mr. Collins:

The above referenced letter indicated submittal of a Final Report to the USNRC no later than July 26, 1983.

At the present time, the completion of corrective action is being delayed due to testing. We are presently awaiting an opportunity to install the remaining coils without impacting the startup testing schedule. This installation is expected to be complete in early September, 1983.

A Final Report will therefore be submitted to the USNRC by September 30, 1983.

Very truly ours, I

l h *"

F. J. Drummond Project Support Manager - Nuclear FJD/RWP/ MAL:keh cc: 1) Director 3) Mr. E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555

2) Director 4) Mr. W. M. Stevenson Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C. 2055 1

I 0 iTGO8090625 830725 DRADOCK05000pB2 } {_