Updates Status & Confirms 910624 Telcon Notification of Completion of Installation of Containment High Radiation Isolation Signal on Containment Vent Line for Unit 1,per Tech Spec 3.6.1.8
ML20077G997
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 06/28/1991
From: Creel G
BALTIMORE GAS & ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
TAC-80609, NUDOCS 9107030314
Download: ML20077G997 (2)


Text

7 Al B ALTIMORE GAS AND ELECTRIC

\\

/

CHARI.ES CENTER

  • P.O. DOX 1475
  • BALTIMORE, 'MRYLAND '.12031475 GEORGE C CRttL VaCE PRE Sict hf NvCLt an [hteG v tsooeaa-44ss June 28,1991 U. S. Nuclear Regulatory Commission Washington, DC 20555 NITENTION:

Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50 317 & 50-318 Unit 1 Containment Vent System Operability; Technical Specif; cation 3.6.1.8 (TAC No. 80609)

REFERENCE:

(a),

Letter from h1r. G. C. Creel (BG&E) to NRC Document Control Duk, dated June 14, 1991, Unit 2 Containment Vent System Operability (b)

Letter from hir. D. G. hicDonald, Jr. (NRC) to hir. G. C. Creel (BG&E), dated June 18,1991, Deletion of Containment Vent System Technical Specification 3/4.6.1.8 Gentlemen:

Reference (a) reported the status of the containment vent paths for Calvert Cliffs Units 1 and 2. The status was acknowledged in Reference (b). This letter updates that status and confirms the telephone notification made to your staff on June 24,1991, that we had, on that date, completed installation of a containment high radiation isolation signal on the containment vent line (htOV-6900 and 6901) for Unit 1. With the completion of this work, we have satisfied the Technical Specification requirements for operability of this system.

The footnote associated with Technica' Specification 3.6.1.8 allows the deletion of the limiting condition of operation and its associsice surveillance requirement.

Now that work is complete on both Units, we will request a i administrative Technical Specification change to delete this page as part of a future submittal.

'Ihe containment vent valves will now isolate upon receipt of either a safety injection actaation signal or a high radiation signel. By completion of thi; modification, we have establishe( a containment vent path for Unit I which is in full compliance with Thfi Action Item II.E.4.2. This complete

  • the required actions for both Units in conjunction with this issue.

T YIJ/.7/f 9107030314 910628

$8 4

PDR ADOCK 05000317 N

p PDP ii tj

J r

Document Control Desk 36nc. 28,1991 Page 2 Should you have any further questions regarding this matter, we will be pleased to discuss them with yuu.

Very truly yours,

)

(/,/

/

3 GCC/ PSF / psf / dim cc:

D. A. Brune, Esquire J. E. Silberg, Esquire R. A. Capra, NRC D. G. Mcdonald, Jr., NRC T. T. Martin, NRC T. E. Nicholson, NkC R. I. McLean, DNR J. H. Walter, PSC I