Forwards Application for Amends to Licenses DPR-42 & DPR-60, Revising TS 3.8 to Allow Containment Airlock Doors to Remain Open During Core Alterations Provided Certain Conditions Met
ML20077F130
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 12/05/1994
From: Wadley M
NORTHERN STATES POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20077F134 List:
References
NUDOCS 9412130274
Download: ML20077F130 (2)


Text

U p.

Northern States Power Company Prairie Island Nuclear Generating Plant 1717 Wakonade Dr. East Welch. Minnesota 55089 December 5, 1994 10 CFR Part 50 Section 50.90 U S Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 License Amendment Request Dated December 5, 1994 Channes in Containment Refueling Integrity Reauirements Attached is a request for change to the Technical Specifications, Appendix A of the Operating Licenses, for the Prairie Island Nuclear Generating Plant.

This request is submitted in accordance with the provisions of 10 CFR Part 50, Section 50.90. The requested amendment would revise Technical Specification 3.8 to allow containment airlock doors to remain open during core alterations provided certain conditions are met. This request is similar to the amendment for Calvert Cliffs Nuclear Power Plant which the NRC approved on August 31, 1994. In addition, this requested amendment would allow containment penetrations to remain open during core alterations provided certain conditions are met.

Exhibit A contains a description of the proposed changes, the reasons for requesting the changes, and the supporting safety evaluation /significant hazards determination. Exhibit B contains current Prairie Island Technical Specification pages marked up to show the proposed changes. Exhibit C contains the revised Technical Specification pages.

These proposed amendments are requested in support of the Prairie Island Unit 2 May 1995 outage. Accordingly, these changes are requested to be approved and issued by April 13, 1995 to allow time to issue the necessary implementing plant procedures. However, issuance of this amendment is not currently identified as required for outage completion or continued plant operation. We request segmented approval of these amendments if a portion, such as allowing the airlock doors to remain open, is ready for approval by April 13, 1995 and the balance is not ready.

9412130274 94120S PDR ADOCK 05000 2 yl

'It

l 1

USNRC Dec' ember 5, 1994 Page 2 Please consider this License Amendment Request as a Cost Beneficial Licensing Action (CBLA) item in that these amendments may reduce NSP costs by more than

$100,000 over the life of the plant and deal with changes which improve plant safety or have low safety significance.

Please contact us if you have any questions related to this License Amendment Request.

GL -

M. D. Wadley Plant Manager Prairie Island Nuclear C'enerating Plant ,

c: Regional Administrator-III, NRC NRR Proj ect Manager, NRC Set.ior Resident Inspector, NRC State of Minnesota Attn: Kris Sanda J E Silberg Attachments:

Affidavit Exhibit A - Description of Proposed Changes the Reasons for Requesting the Changes, and the supporting Safety Evaluation /Significant Hazards Determination Exhibit B - Technical Specification Marked Up Pages Exhibit C - Technical Specification Revised Pages l