J BOSTON EOisON COMPANY bod BOYLSTON STREET BOSTON, M AssAcHusETTs 02199 WILLIAM D, MARRINGTO N toeso m viss Passier> r N W o BEAR July 19, 1983 BECo Letter No.83-192 Mr. Thomas E. Murley Office of Inspection and Enforcement Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 License No. OPR-35 Docket No. 50-293 Report of Changes, Tests, and Experiments Performed at Pilgrim Nuclear Power Station
Dear Sir:
In accordance with 10CFR50.59(b), Boston Edison hereby submits a report contain-ing a brief description and safety evaluation for the changes, tests and experi-ments performed at Pilgrim Nuclear Power Station for the time period of July 1, 1982 thru January 21, 1983.
Submittal of this seven month report is in accordance with our letter of January 27, 1983 (BECo Letter #83-28) stating our intention of changing the reporting dates of the annual 10CFR50.59 report to be consistent with the FSAR Update submittal.
Consequently, all future annual submittals will be for tile years ending January 21 and will be filed at a maximum of six months later (July 22).
We trust that this will be acceptable. However, should you have any questions or concerns, please do not hesitate to contact us.
Very truly yours, W.
c MTL/ mat cc:
Director Office of Inspector and Enforcement U.S. Nuclear Regulatory Commissinn c/o Distribution Service Board, DCC, ADM Washington, D.C.
20555 8307280399 830719 f6 g PDR ADOCK 05000296 R