l DUL2 H98 {j{
m l OUISIANA I
wa octanoNoe s1nter POWER & LIGHT P O. BOX 6008
- NEW ORLEANS LhUISIANA 7017A'96I
$iuSOsvsY$
July 15, 1983 W3I83-0236 Q-3-A35.07.60 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012
SUBJECT:
Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 60
" Turnover Documentation and Inadequate Hanger Weld Problems T-B" Fourth Interim Report
REFERENCE:
LP&L letter W3I83-0158 dated May 11, 1983
Dear Mr. Collins:
The above referenced letter indicated submittal of a Final Report to the USNRC no later than July 15, 1983.
At the present time, corrective action is ongoing and the supporting documentation review is in progress. Completion of the corrective action and documentation review is scheduled for August 17, 1983.
A Final Report will therefore be submitted to the USNRC by September 16, 1983.
1 Very truly yours, l
+fw+c2M F. J. Drummond Project Support Manager - Nuclear FJD/RWP/ MAL:keh cc:
- 1) Director 3)
Ms. E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D.C.
20555
- 2) Director 4)
Mr. W. M. Stevenson Office of Management Information and Program Control U. S. Nuclear Regulatory Commission i
Washington, D.C.
20555 i
i 8307260392 830715
,,_L b ~2 7 PDR ADOCK 05000382 S
.