Rept on Significant Const Deficiency 42 R-1 Re Hma Auxiliary Relays.Completion of Corrective Action Delayed Due to Testing.Three Remaining Coils Will Be Installed During Outage.Final Rept Will Be Provided by 830923
ML20077C499
Person / Time
Site: Waterford Entergy icon.png
Issue date: 07/15/1983
From: Drummond F
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3I83-0238, W3I83-238, NUDOCS 8307260126
Download: ML20077C499 (1)


Text

LOUISIANA f 342 OctAnO~Oc srneer POW E R & L1G H T/ P O BOX 6008

  • NEW ORLEANS. LOUISIANA 70174 * (504) 366-2345

$uSN2ysNU July 15, 1983 W3I83-0238 Q-3-A35.07.42 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive Suite 1000 Arlington, Texas 76012

SUBJECT:

Waterford SES Unit No. 3 g

g g

l Docket No. 50--382 l

_p a

a Significant Construction Deficiency No. 42 R-1 "HMA Auxiliary Relays" i

g g lg

REFERENCE:

LP&L letter W3I83-0238 dated May 26, 1983 L

d

Dear Mr. Collins:

The above referenced letter indicated submittal of a Final Report to the USNRC by July 17, 1983.

At the present time, the completion of corrective action is being delayed due to testing. As a result, LP&L is waiting for an outage which will permit installation of the three (3) remaining coils.

A Final Report will therefore be submitted to the USNRC by September 23, 1983.

Very truly yours, W

ma N

'f*

F. J. Drumaand Project Support Manager - Nuclear cc:

1) Director 3)

Mr. E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555

2) Director 4)

Mr. W. M. Stevenson i

Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C.

20555 r307260126 030715

[b g

PDR ADOCK 05000382 C

PDR 1