SNUPPS Stan:lerdized Nuclear Unit Power Plant System 5 Choke Cherry Road nockvaie. u rviend 20ss0 July 21, 1983 (301)869 8010 SLNRC 83-038 FILE: 0491.3.1 SUBJ:
Revision 7 to SNUPPS QA Program for Design and Construction Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Docket Nos. STN 50-482 and STN 50-483
Dear Mr. Denton:
By copy of this letter we are forwarding to Mr. W. P. Haass, Quality Assurance Branch, a copy of Revision 7 to the subject QA program document.
The enclosed revision reflects changes in the Callaway and Wolf Creek Site Addenda; no changes in the Standard SNUPPS QA Program are included in this revision. The changes in the Callaway Site Addendum reflect organizational updating which was in effect prior to the March 11, 1983 rulemaking date.
The basis for the changes.in the Wolf Creek Site Addendum, developed sub-sequent to the March lith date, were detailed by Kansas Gas and Electric in its letter of June 10, 1983 to the NRC; Ref. KMLNRC 83-068.
Controlled copies of this revision will be distributed to NRC Regions III and IV in accordance with standard document control procedures.
If you have any questions concerning the enclosed revision, please advise.
Very truly yours, 7
(
S. J Seiken Manager, Quality Assurance SJS/dck/18a28
Enclosure:
Revision 7 cc: W. P. Haass, NRC w/ encl.
D. T. McPhee, KCPL w/o G. L. Koester, KGE w/o D. F. Schnell, UE w/o H. W. Roberds, USNRC w/o J. H. Neisler, USNRC w/o o
qc 8307250309 830721 PDR ADOCK 05000482 A
--