ML20076M929

From kanterella
Jump to navigation Jump to search
Ro:On 830712,engineering Calculations Performed During Piping Walkdown Identified 3/4-inch Hle Pipe Exceeded Design Basis Code Allowable Pipe Stress.Design Change Will Be Implemented to Return Line to within Allowable Conditions
ML20076M929
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 07/12/1983
From: Mineck D
IES UTILITIES INC., (FORMERLY IOWA ELECTRIC LIGHT
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
DAEC-83-540, NUDOCS 8307210151
Download: ML20076M929 (1)


Text

lowa Electric Light and Ibwer Company July 12, 1983 DAEC-83-540 Mr. James G. Keppler Regional Administrator Region III U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Duane Arnold Energy Center Docket No. 50-331 Op. License DPR-49 Prompt Notification of a Reportable Occurrence File: A-118a, TE-2

Dear Mr. Keppler:

This letter, telecopied to your office, provides prompt notification of a Reportable Occurrence in accordance with Specification 6.ll.2.a.(9) of the Duane Arnold Energy Center Appendix A Technical Specifications.

Specifically, engineering calculations performed following a piping walkdown has identified a 3/4" HLE pipe that exceeds design basis code allowable pipe stress.

Calculations show that the maximurn stress under design basis conditions which could be applied to the pipe would not have exceeded the ultimate strength of the material.

The piping in question is a vent line that is attached to the full flow test return line for the RHR system. The RHR return line stresses have been reviewed and found to be acceptable.

We have initiated prompt engineering corrective action to restore the 1

code design margin. A design change will be promptly implemented to return the line to within design basis code allowables conditions.

In addition, a full investigation has been initiated into the circumstances surrounding this event. We will keep both the DAEC NRC Resident Inspector and your office informed as these activities progress.

truly yours,

&W Daniel L. Mineck Plant Superintendent - Nuclear Duane Arnold Energy Center DLM/WJM/pf

[b cc: NRC Resident Inspector N

B307210151 830712 M 15192

\\-

PDR ADOCK 05000332 S

PDR Duane Arnold Energy Center o P.O. Bo,x 351. Cedar llapids, Iowa 52406 e 319 8517611