Interim Deficiency Rept Item M-14 Re HVAC Damper Actuators. Initially Reported on 800312.Projected Schedule for Corrective Actions Will Be Submitted Following Release of 821112 Show Cause Order
ML20076M682
Person / Time
Site: Zimmer
Issue date: 07/11/1983
From: Williams J
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, LOZ-83-0079, LOZ-83-79, NUDOCS 8307210040
Download: ML20076M682 (2)


Text

.

!~

'i e

ISh= I' i.

m THE CINCINNATI GAS & ELECTRIC COMPANY CINCINNATO,OMIO 45201 July ll, 1983 LOZ-83-0079 J, WILLIAMS. JR stNaon vice passeDENT 3eUCLEAN OPERafMNs i

Docket No. 50-358

-U.S.

Nuclear Regulatory Commission

-Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention:

Mr. J.G. Keppler Regional Administrator Gentlemen:

RE:

WM. H. ZIMMER NUCLEAR POWER STATION - UNIT 1 10CFR50.55(e), ITEM M HVAC DAMPER ACTUATOR DEFICIENCIES W.O.

57300, JOB E-5590, FILE NO. 956C, M-14 This letter constitutes an interim report concerning the subject condition initially reported to the Commission on March 12, 1980- under the requirements of 10CFR50.55 (e).

As indicated in our previous report, LCZ-83-0005, dated March 24, 1983, actual field torque measurements on the dampers and analysis of the. torque data by Sargent & Lundy Engineers has determined that:

1.) Three actuators require replacement; 2.) Two actuators require spring replacement; and 3.): Three actuators require spring height adjustment.

~

Torque testland analysis are still required on ten (10) dampers in the Primary Containment Ventilation (VP) and Primary Containment Purge.(VQ) _systamc.. These. tests cannot be performed until the VPz and VQ system ductwork'is complete.

Completion of this work 'is contingent upon the release 'of the NRC November 12, 1982 " Order to Show Cause and Order Immediately Suspending Construction" for work in this area.

Upon this release, a projected schedule.for completion of the corrective actions will

'be submitted.

g7ggO

[

$b O

S

.~

r6 I

Mr. J.G. Keppler Rentonal Administrator July 11, 1983 LOZ-83-0079 Page 2 We trust the above will be found acceptable as an interim report under 10CFR50.55 (e).

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY i

By g#r :1J

~

. WILLIAMS, J SENIOR VICE P SIDENT DJS/sfr cc:

NRC Office of Inspection & Enforcement Washington, D.C.

20555 NRC Senior Resident Inspector ATTN:

W.F. Christianson NRC Zimmer Project Inspector, Region III-ATTN:

E.

R.

Schweibinz l

l

<-