Corrects Erroneous Statement at 830817 Hearing.State of Ma Civil Defense Agency Received Draft Area Plan on 830805.Work on Plan Is Still in Progress & Target Date for Submission to ASLB & Parties Is 831015
ML20076H693
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 08/30/1983
From: Boulay R, Shotwell J
MASSACHUSETTS, COMMONWEALTH OF
To: Harbour J, Hoyt H, Luebke E
Atomic Safety and Licensing Board Panel
References
ISSUANCES-OL, NUDOCS 8309060131
Download: ML20076H693 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. k THE COMMONWEALTH CF MASSACHUSETTS ,

I h EXECUTIVE DEPARTMENT DOCKCTED A%

QYIL DEFEMSE AGENCY AND OFFICE OF EMERGENCY PREPAREDNESyS N AC 71 &W

- 400 WOmCESTER ROAD 1 , /

P.O. 80X 1att

( F=...."'""

33 SEP -2 A10:44 'M WCHAEL S. NKAKIS . ROBERT J. BOULAY om - -deCRtiAn r 1 DinEcToa August 30, gNG & SERvict 3 RANCH i

l Helen Hoyt, Esq., Chairman Dr. Jerry Harbour Administrative Judge Administrative Judge Atomic Safety and Licensing Board Atomic Safety and Licensing Panel Board Panel U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Washington, D.C. 20555 Dr. Emmeth A. Luebke Administrative Judge Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washir.g ton , D.C. 20555

) In the matter of -

Public Service Company of New Hampshire, et al.

(Seabrook Station, Units 1 and 2)

Docket Nos. 50-443 OL and 50-444 OL

Dear Administrative Judges:

We are writing to correct for the record and for the benefit of the Board and parties to this proceeding a statement which was made at the August 17 hearing which has subsequently been determined to have been in error. At that hearing it was reported that the Massachusetts Civil Defense Agency had not yet received a draf t of the Massachusetts Area Plan for the Seabrook Station f rom Yankee Atomic Electric Company and that a draf t was not expected for at least a month. That report was based on conversations with an employee at the State Civil Defense Headquarters in Framingham, Massachusetts, who is involved in the planning process for the Seabrook vicinity. It has subsequently been determined, however, that the Area 1_ Headquarters of the Massachusetts Civil Defense Agency in Tewksbury, Massachusetts, did receive a draft Area Plan on August 5, 1983. Work is stil:.

in progress on the plan and the target date for submission to the Board and parties to the proceeding remains October 15, 1983, as indicated at the August 17 hearing.

8309060131 830830

{DRADOCK 05000443 PDR

_ - - - _ _ - _ _ Tso 3 )

We regret any-inconvenience this may have caused any party.

Sincerely,

$6.sc. A-R bert J. %y) lay, Director MassachusMsCivilDefense[jN k

Ann Shotwell Assistant Attorney General cc: Service List 9