Advises That Plans Associated W/Accelerating 840101 Refueling Outage to Permit Earlier Insp of Recirculation Sys Piping Reviewed,Per NRC Request.Alternate Date of 831210 Developed
ML20076E204
Person / Time
Site: Pilgrim
Issue date: 08/22/1983
From: Harrington W
BOSTON EDISON CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
83-223, NUDOCS 8308240224
Download: ML20076E204 (2)


Text

ar e

BOSTON EDINON COMPANY 800 BOYLBTON STREET BOSTON, M AESACHUS ETTs 0 2199 WILLIAM O. HARRINGTON asmose vies posesosast

~,.s.

August 22, 1983 BECo 83-223 Mr. Darrell G. Eisenhut, Director Division of Licensing Office of Nuclear Reactor Regulation J.S. Nuclear Regulatory Commission Washington, D.C.

20555 License No. DPR-35 Docket No. 50-293

Subject:

Acceleration of 1984 Refueling Outage

References:

(A) Boston Edison letter dated August 4, 1983 from Mr. W.D. Harring-ton to Mr. D.G. Eisenhut (B) Boston Edison letter dated August 10, 1983 from Mr. W.D. Harring-ton to Mr. D.G. Eisenhut l

Dear Sir:

As you requested, Boston Edison has again reviewed the plans, assumptions, and costs associated with accelerating the January 1,1984 refueling outage to permit earlier inspection of the recirculation system piping.

We have developed an alternate date of December 10, 1983. This date will disturb the planning which has been prepared in support of January 1, 1984, and will com-plicate acquiring the necessary personnel to perform the work.

The plan for December 10 includes a 3 day Christmas weekend when outage and inspection work will come virtually to a halt.

This will cost our customers approximately $1.8 million dollars of lost savings.

We believe that the increasing safety margins inherent in our coastdown, which will begin in October, coupled with our interim surveillance measures, more than serve to justify continued operation until January 1,1984.

In past discussions with you, we have detailed our short and long term plans to comprehensively address this issue. We are confident that our actions are adequate 9308240224 830822 g

PDR ADOCK 05000293 G

PDR k0

a a

COSTON EDIEDN COMPANY Mr. Darrell G. Eisenhut, Director Page 2 and afford both safety and service.

We believe that your review of our actions has lead you to share that confidence. However, if you find it to be necessary, we can accommodate a December 10, 1983 date.

Ve trul PMK/ mat Commonwealth of Massachusetts)

County of Suffolk

)

Then personally appeared before me J.M. Ballentine, who, being duly sworn, did 4

state that he is Vice President - Nuclear Operations of Boston Edison Company, the applicant herein, and that he is duly authorized to execute and file the submittal contained herein in the name and on behalf of Boston Edison Company and that the statements in said submittal are true to the best of his knowledge and belief.