Text

-

l_OUISIANA 142 ORARONDE SWEET POWER & LIGHT P O BOX 6008

  • NEW ORLEANS. LOUISTANA 70174 * (504) 366-2345 MIDDLE SOUTH umnes sYST April 29, 1983
t. v MAvain Vice President Nuclear Operations W3183-0142 Q-3-A35.07.53 Mr. John T. Collins Regional Administrator, Region IV

_N,g 4

611 Ryan Plaza Drive, Suite 1000 j

Arlington, Texas 76012 g

SUBJECT:

Waterford SES Unit Number 3 y

Docket Number 50-382 Significant Construction Deficiency Report Numt = 5' "Possible Failure of General Electric Type HFA Relays" Third Interim Report

^

REFERENCE:

LP&L Letter WI82-0051 dated September 30, 1982 jg_-27

Dear Mr. Collins:

The above referenced letter indicated submittal of a Final Report to the USNRC no later than April 30, 1983.

At the present time, corrective action is scheduled for completion on May 20, 1983. This is due to the fact that corrective action cannot be performed during plant testing. A final report will therefore be delayed until June 15, 1983.

Very truly yours, 5%

f~~,

l/'

L. V. Maurin LVM/ MAL /sm cc:

1) Director
3) Mr. E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555

2) Director
4) Mr. W. M. Stevenson Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C.

20555 7 830429 S