Second Interim Rept on Significant Const Deficiency 66 Re GE Type Akr Breakers w/C-clips Which May Fall Off.Matls Will Not Be Shipped from Vendor Until Late Apr 1983.Final Rept Will Be Delayed Until 830630
ML20073K017
Person / Time
Site: Waterford Entergy icon.png
Issue date: 04/11/1983
From: Maurin L
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3I83-0117, W3I83-117, NUDOCS 8304190498
Download: ML20073K017 (2)


Text

  • % , .,4.*

LOUISIANA ,42 ocLARoNoe srneEr POWER & LIGHT P. O BOX 6008

  • NEW ORLEANS. LOUISIANA 70174 * (504) 366 2345 UE2iS$EsE L V. MAURIN April 11, 1983 Vice President Nuclear Operabons W3I83-0117 Q-3-A35.07.66

[

Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission ,

611 Ryan Plaza Drive, Suite 1000

APR I 51983 Arlington, Texas 76012 i ;r\ -

\\

~~

) Nub

SUBJECT:

Waterford SES Unit No. 3 I Docket No. 50-382 ,

Significant Construction Deficiency Report No. 66

" Defective G.E. Type AKR Breakers, C-Clips Fall Of f" Second Interim Report

Reference:

LP&L Letter W3I82-0109 from L. V. Maurin to J. T. Collins dated November 19, 1982

Dear Mr. Collins:

At the present time, materials needed to complete the corrective action will not be shipped from the vendor until late April,1983. A final report will therefore be delayed until June 30, 1983.

~

Very truly yours, g_

t/- 7 san.

L. V. Maurin LVM/ MAL /gf cc: 1) Director 3) Mr. E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555

2) Director 4) Mr. W. M. Stevenson Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D.C. 20555 8304190498 G3041i gDRADOCK 05000382 PDR

L

.4y ,o ' '

b EBASCO SERVICES INCORPORATED EBoSCO P. O. Box 70 Killona, Louisiana 70066-0070 W3QA-24045 April 7, 1983 Mr. R. W. Prados Louisiane Power & Light Company.

Nuclear Support Group Gretna Greens LOUISIANA POWER & LIGHT COMPAhT WATERFORD STEAM ELECTRIC STATION 1983 - 1165 MW INSTALLATION - UNIT NO. 3 SIGNIFICANT CONSTRUCTION DEFICIENCY NO. 66

" DEFECTIVE G. E. TYPE AKR BREAKERS, C-CLIPS FALL OFF"

Reference:

LP&L letter no. W3183-0109, dated November 19,-1982

Dear Mr.-Prados:

The above referenced letter indicated submittal of a Final Report to the USNRC no later than April 11, 1983.

At the present time, materials needed to-complete corrective action will not be shipped until late April, 1983. Additionally, this SCD can only be worked when a time slot is available during testing operations. It is our recommendation that LP&L give this SCD the utmost priority in expediting the completion of the corrective action prior to fuel load. As the attached

. schedule indicates, Construction and Scheduling anticipates the completion 'of corrective' action on June 15, 1983.

Unless -the present schedule is prioritized, Ebasco Quality Assurance needs an extension until June 30, 1983 for submittal of a Final Report by LP&L to the USNRC.

Very truly yours,

)') I

.\ b p [F% %.-

anager L.'A.,$tinson)

Site Quality Program LAS:JP:jmd i

Attachment - Rev. (0)

--