I?f.lli.Tfr April 13, 1983 SP

. j. . c

- ; ., jy r ,

Chairman C Bechhoefer Atomic Safety & Licensing Board Panel

'US Nuclear Regulatory Commission Washington, DC 20555 Dear Chairman Bechhoefer Attached heretc is a copy of a press release by Consumers Power Company addressing the new construction schedule and related matters. The press release announces a schedule consistent with my letter of yesterday.

Very truly yours km { /VW E Brunner CC OM/0L Service List i

i I

i oc0483-0410a100 8304180545 830413 PDR ADOCK 05000329

.-_ , G 5

._PDR . _ . _ _ .

1 n w~ ,

Consumers P0Wer Company bLiWha faicl:5%"=;;"W;;t;;;r FOR IM.1EDIATE RELEASE JACKSON, Mich., April 12, 1983 -- Officials of Consumers Power Company today announced new dates for the estimated completion of the Midland Nuclear Cogeneration Plant and a new cost estimate for the project.

Projected fuel loading for Unit 2, the first unit to go on line is October 1984, with commercial operation scheduled for February 1985. Fuel loading for Unit 1 is scheduled for February 1985, with commercial operation scheduled for August 1985.

The cost of the project is now estimated at $4.430 billion.

The new cost and schedule were announced at the company's annual meeting today by John D. Selby, the utility's board chairman.

Previously, Unit 2 had been planned to go into commercial operation in December 1983 and Unit 1 in July 1984. The cost estimate based on that schedule had been $3.39 billion.

Selby outlined the principal reasent for the changed schedule. He said the remedial work on the foundations of certain buildings at the Midland site is an important factor.

The foundation work, called underpinning, to resolve possible problems because of inadequately compacted soils in some areas of the site, had been delayed for many months because of technical and regulatory reviews.

Other elements responsible for the revised schedule are the remain-ing work to complete the plant and the implementation of revised quality

--more--

nr0483-0532a-05-23

2 control and quality assurance programs in order to satisfy concerns about those areas expressed by officials of the U.S. Nuclear Regulatory Commission.

The plant is 83 percent complete.

Selby said the underpinning work has been changed from the program originally announced by the company in January 1982. As a result of the completed regulatory reviews the design has become more conservative and the work sequence has increased in complexity. As a result, the time needed to accomplish the underpinning program has expanded by 8 months.

Selby said the soils remedial work has been under way on the auxiliary building underpinning for four months and the work is progressing well.

The official said the project's construction completion program (CCP), anncunced last December, should be completely under way sometime this spring.

The CCP involves design and test engineers, quality assurance personnel and construction engineers joined into coordinated teams to inspect work done on certain systems at the plant, to determine what work is needed to complete the systems and to oversee that work. A major objective of the CCP is to improve the project's performance in meeting the regulations and expec-tations of the NRC, Selby said.

The major construction work still to be completed is the installa-tion of pipe hangers which has traditionally been the most time-consuming aspect of completing a nuclear power plant project. I Selby described the major components of the increase in project

[

cost. The foundation support work will add $100 million. Remaining

--more--

nr0483-0532a-05-23

3 engineering, administrative and construction work will cost S538 million.

Additional financing costs and overhead are $402 million.

The chairman noted that about one-third of the total plant cost, or about $1.3 billion will cover the financing charges on the money raised to build the Midland facility.

The Midland plant will be the world's largest nuclear cogeneration energy producing facility. It will be capable of generating 1,345,000 kilo-watts of electricity for Consumers Power's electric system and up to 4,000,000 pounds of process steam per hout for The Dow Chemical Company. The steam to be sold to Dow contains energy equivalent to approximately 250,000 kilowatts of electricity.

April 12, 1983 nr0483-0532a-05-23

.) ,

Szav:cz L:sr

?rsnic J 7 "_iy, Esq Atc= tic Safety & '.icensi=g Atterney General of the Appeal ?scel Statacef Michigan 7 S Nucles: Reg-'a:Ory C---

Carole Steinberg, Isq 'Jashingtec.,. D C 20535 Assistant Atter:e7 General Invirchsal Prctection Dir Mr C R Stephens 720 Iaw 3tsd'A' g Chief, Dccheting & Services.

La: sing, E h8913 7 S Nuclear Reg 1 story Cc==L Office of the Secretary Myren M Che--s, Esq ~'inhd gec=, D C 20555 ruite 3700 hree First national Placa Ms Mary Sinclair Chicage, IL 60602 STil St==erset. Street Midla:d, XI h86h0 Mr W- a a" E Marshau.

R?D.10 'id " da:L D Ps; ten, Esq Midla:d,. E.h86h0 Ccunsel fer the NEC Sta:

U S Nuclear Reg'.:1stcry C=:=t Charles 3e^heefer, Zsq Washi=gte=, D C 20555 At* c Safety & Licensi=g 3 card Panel Atcmic Safety & Lice si=g U S Nuclear Resuls: cry Cc:=a Beard Fanel Yashi=gten,.D C 20555 7 S Nuclear Regula:m y Cc=m

'i==hd ten, D C 20555 Dr Frederick.? Cevan 6152 I Verde Trail Barbara Stamiris Atp 3-125 5795 Ncrth River Ecad.

3cca Rares,. FL 33h33 Rt 3 Freels=d, MI k8623 Je--g Harbcur Atc=ie Safety & Licensing 3c~ard ?ssel Carrell 2 Mahaney U S Nuclear Reg 'atery Cc=s 3abecek & 'Wilecz 'Ja=5 d g:c=, D C 20555 PO 3c= 1260 Lf chburg, 71rgd da 24505 Ime- L 31shcp Hac=:en & *ielss James 3 31.=:=er, Isq 1725 " " Street, 74 #5C6 Const=e s ?cver C% a=7 '4ashi= sten, DC 20006 c'9 'Jes: .* chigan Ave =ne Jachsen, MI k92C1 M I .Vd " er , Is q Isha=t , t' cc1= & 3eale Mr D 7 Judi ?ree.?:eticnal Placa 3abecek & 'Jilec . 52nd Ficer 70 3cx *260 Chicase, 2 6C603 ynchburg, 7A 2h505 Jch: CeMeester, Isq Steve Gadier, Isq Ocv Cha 'ca'. 3lig c'c0 02:-.er Avenne Michigan Ci--isic St ?sul,:C 55'C8 Midland, :C E86ko ,

._ _ . _ . _ _ _ _ _ _