Responds to NRC Re Violations Noted in IE Insp Rept 50-358/80-05.Alternative Approach for Documentation of Final Plant Configuration submitted.Red-lining of Design Drawings Will Indicate Differences
ML20073G101
Person / Time
Site: Zimmer
Issue date: 03/30/1983
From: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20073G081 List:
References
EAB-S01-41, EAB-S1-41, NUDOCS 8304180109
Download: ML20073G101 (1)


Text

'

y

-w _

THE CINCINNATI GAS & ELECTRIC COMPANY sAK-CINCINN ATI, OHIO 452Of March 30, 1983 EAB-SOL-41 L A. BORGMAN N SENIOR WCC PRESIDENT Docket No. 50-358 U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 ATTENTION:

Mr. J. G. Keppler Regional Administrator RE:

Wm. H. Zimmer Nuclear Power Station Unit 1 - I.E. Inspection Report 80-05 Docket No. 50-358, W.O. 57300, Job E-5590

REFERENCE:

CG&E Letter QA-1702 Dated May 6, 1982, NRC Letter Dated December 15, 1982 We are submitting for your consideration, an alternate approach for the documentation of final plant configuration. The approach is as follows:

1.

During the performance of walkdowns associated with design freeze, system turnover or final plant configuration, differences between the field installation and the design drawings shall be indicated by red-lining the design drawings, or other site originated drawings, if design drawings do not exist.

II.

These red-lined drawings will then be submitted to S&L for evaluation prior to incorporation into "as-built" project drawings.

III.

Should this evaluation determine that a condition represented by a red-lined drawing is a deficiency or otherwise unacceptable and requires subsequent field modification, such change will be documented on a non-conformance report.

We trust the above will be acceptable. Your early response to this proposal would be appreciated.

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY 8304180109 830412 By PDR ADOCK 05000350 0

pos E. A. Borgmann Senior Vice-President EDR:dw cc: NRC Site Resident Inspector Attn:

W. F. Christianson NRC Office of Inspection & Enforcement Washington, D.C. 20555 APR 4 G83

.... - -