UNITED STATES OF AMERICA \

NUCLEAR REGULATORY C0tWISSION DQGpU-BEFORE THE ATOMIC SAFETY AND LICENSING 80ARD AH :47 In the Matter of )

)

CONSOLIDATED EDISON COMPANY OF NEW YORK ) . Docket Nos. 50-247 SP (Indian Point Unit 2). ) 50-286 SP

. )

POWER AUTHORITY OF THE STATE OF NEW YORK ) A P ril 12, 1983 (Indian Point Unit 3) )

PARENTS CONCERNED ABOUT INDIAN POINT MOTION FOR APPROVAL OF STIPDTATION In order to complete the record, Parents Concerned About Indian Paint herelty respecfully moves the Board to approve the attached stipulations regarding the Intervenors' Observation of the March 9 radiological e:nergency preparedness exercise for Indian Point Unit 2.

These stipulations represent an agreed upon resolution of certain of Intervenors' requests in NYPIRG Motion for Preservation and Production of Certain Documents Relevant to the Exercise of March 9, 1983, dated February 22, 1983, and should be accepted by the Board.

1 Parents apologizes for the delay in submitting the signed l stipulation for approval by this Board, and trusts that no party has l been inconvenienced since all the agreed upon actions have been l

carried out by the respective parties.

1 Pat Posner B304180085 830412 Parents Concerned About Indien Point PDR ADOCK 05000247 P'.IO. Box 125 G PDR Croton-on-Hudson, New Yo rk 10520

'