ML20073F063

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Feb 1983
ML20073F063
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/02/1983
From: Hairston W
ALABAMA POWER CO.
To:
Shared Package
ML20073F049 List:
References
NUDOCS 8304150417
Download: ML20073F063 (4)


Text

-

n I

1 JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1 NARRATIVE

SUMMARY

OF OPERATIONS FEBRUARY, 1983 The Unit 1 Cycle 4 - Cycle 5 refueling outage continued through the month of February.

The following safety-related maintenance was performed in the month of February.

1. Performed miscellaneous maintenance on diesel generators.
2. Pressurizer pressure controller 444A was repaired.
3. Replaced charcoal filters in the "A" train Penetration Room Filtration System and the "A" train Control Room Filtration Unit.
4. Replaced "0" rings in Containment Penetration Q1T52B038.
5. Replaced root isolation valves on 1A, IB and IC Steam Generator level and flow transmitters.
6. Adjusted packing on #2 and #3 River Water Pumps.

1 i

SCN>4150417 83KX311 i PEWt ADOCK 050D03NHB I O PDR

~ . , t t

5

('

s J OPERA flNG DATA REPORT DOCKET NO. 50-348 DATE 3/02/83 COMPLETED BY W.G.Hairston,III t, TELEPl!ONE (205)899-5156 OPERATING STATUS ,

J ScPh M. Farley - Unit 1 Notes -

I. Unit Name:

2. Reporting Period: February, 1983 1) Cumalative data since .
3. Licensed Thermal Power (MWt): 2652 12/01/77, date of
4. Nameplate Rating (Gross MWe): 860 commercial operation.

S. Design Electrical Rating (Net MWe): 829

6. Maximum Dependable Capacity (Gross MWe): 844.6
7. Maximum Dependable Capacity (Net MWe): 803.6
8. if Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:

N/A

9. Power Level To which Restricted,if Any (Net MWe): N/A
10. Reasons For Restrictions.If Any: N/A

(~ .

% This Month Yr. to Date Curisulative

[

672 1,416 45,984 lI. Ifours in Reporting Period

12. Number Of Hours Reactor Was Critical . 0 332.5 28,480
13. Reactor Resene Shutdown Hours 0 0 3,614.5
14. Hours Generator On Line 0 332.5 27,600.7
15. Unit Resene Shutdown Hours 0 0 0 sti. bross t he al Energy Generated (MWH) 0 794.698 J9.284.747 -
17. Gross Elec al Energy Generated (MWH) 146_ _ _ _ _ ,

253,094 22.026,642

18. Net Electri Energy Generated (MWH) -4.086 229,978 20,670,198
19. Unit Service Factor 0.0 23.5 60.0
20. Unit Availability Factor 0.0 23.5 60.0
21. Unit Capacity Factor IUsing MDC Net) .8 20.2 55.9
22. Unit Capacity Factor IUsing DER Net) 7 19.6 54.2
23. Unit Forced Outage Rate 0.0 0.0 18.0
24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Eacht:

N/A

25. If Shut Down At End Of Report Period. Estimated Date of Startup: March 25, 1983
26. Units in Test StatusIPrior to Commercial Operation): Forecast Achiesed INITIA L CRITICA LITY 8/06/77 8/09/77 INITI AL ELECTRICITY 8/20/77 8/18/77 COMMERCIAL OPER ATION 12/01/77 12/01/77 (0/77)

~,.g. , 3 , , . . . , , ,,

DOCKL. 50-348 I

UNIT DATT. 3/02/83 COStPLETED BY W. G. Hairston, III TELEPl!O 5 (205) 899-5156

\.

FEBRUARY

\. .' t, 310 Nill DAY AVERACE DAILY POWER LEVEL DAY' AVERAGE DAILY POWER LEVEL (SIWE Net) (,\lwe-Net)

I, O g7 0 -

2 0 gg 0 l 3

0 19 0

4 0 20 0 5

0 21 0

  • 0 6 0 22 0 0 7 - 23

+g 0 24 0 9 0 25- 0' 10 0 26 0 il 0 27 0 12 0 23 0 1

13 0 ;9 -

0 '

14 30 IS 0 3g -

16 0 INSTRUCDONS On this fonnst. list the sversge daily umt power levelin MWe Net for esch d:y in the reporting inonth. Compute to

, the nearest whole ne;2 wait.

(907)

O 4g, hy s' ww"N p

  1. ^

~4 SIWE e ,

. , ,s -

O O O

~

'i UNIT SilUTDOWNS AND POWER REDUCTIONS NhE 'J . lev-Unit 1 DATE 3/02/83 COMPLETED BY W.G.Hairston,III REPORT hf 0NTil FEBRUARY l TELEPfl0NE (205) 899-5156

. "i -

No. Date R

.! ?

58

};; )Ek

.3 s 5 Licensee Event

,Ev,

y h4
a. ]

Cause & Corrective Action to M

$5 5 j g5 g Report # ,

v70 $U Prcvent Recurrence 6

012 830201 S 672 C 3 N/A N/A N/A The Unit 1 Cycle 4 - Cycle 5 l

refueling outage continued from c 1/31/83.

s t

41

  • I r.

I

(

l 2 3 4 F: Forced Reason: Method: Exhibit G. Instructions '

S: Sclieduled A Equipment Failure (Explain) 14tanual for Preparation of Data B4taintenance or Test 24fanual Scram. Entry Sheets for Licensee 8

C Refueling 3 Automatic Scrain. Event Report (1.ER) File (NUREG-D Regulasany Restriction 4-Other (Expla;a) '

0161)

E-Operator Training & license Examination -

F Administutive 5 G Opciation.al Luor (linplain) lisinbis I Same Sinuce (9/17) 110:hes (thpl.iini i

. w