Interim Deficiency Rept Re Rosemount Model 1151 Pressure Transmitters (Item M-16).Transmitter Replacement Program Scheduled to Commence 3 Months After NRC 821112 Order to Show Cause Lifted.Next Rept Will Be Submitted by 830720
ML20072S611
Person / Time
Site: Zimmer
Issue date: 03/25/1983
From: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, LOZ-83-0009, LOZ-83-9, NUDOCS 8304070262
Download: ML20072S611 (1)


Text

M' -

THE CINCINNATI GAS & ELECTRIC COMPANY ME CINCINNATI. OHIO 45201 March 25, 1983 LOZ-83-0009 L A. 80 AGM ANN SENeon veCf PRE &sDENT Docket tio. 50-358 U.S. Nucl ear Regulatory Commission Ragion III 799 Roosevelt Road Glen Ellyn, IL 60137 Attention:

Mr.

J. G. Keopler Regional Administrator Gentl emen :

RE:

WM.

H.

ZIMMER NUCLEAR POWER STATION - UNIT 1 10CFR50 55(e) - ITEM F ROSEMOUNT 1151 PRESSURE'

_57300 _Jgg_E-5590 _f,ILE_21h(z_E-10 1RAN1311TERS -

W.Q._

1 1

This letter constitutes an interim report concerning the subject condition ini tiall y reported as 10CFR50.55(e), Item M-16.

Our intention is to provide updated information to our final report, OA-1738, dated May 6, 1982.

The Rosemount Model 1153 transmitter replacement program is scheduled to commence approximately three (3) months after the NRC November 12, 1982 " Order To Show Cause and Order I mmed i atel y Suspending Construction" is lifted in this area.

A follow-up report will be submi tted by Jul y 20, 1983.

We trust the above will be found acceptable as an interim report under 10CFR50.55(e).

Very truly yours, THE CINCINNATI GAS C ELECTRIC CO.

=-

By E.

A.

BORGMANN SENIOR VICE PRESIDENT FHS/JRS/cse cc: NRC Office of Inspection C Enforcement Washington, D. C.