__
- CCN 91-14043 i
PIIILADELPIIIA ELECTRIC COMi%NY
, h$8' piacit turnm1 ATONHC POWER STATION L'
It D 1, llox 208 a3g pf#
Delta. Pennsylvania 17314 r
umno _na mm onum,sa cl7)1 4 7014 Docket Nos.
50-277 50-278
- n. e. umer, Jr.
Wee PrMent April lo, 1991 License Nos. DPR-44 DPR-56 Director, Office of Enforcement U. S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, DC 20555
SUBJECT:
Revision to Commitment Due Date for the Training of Peach Bottom Atomic Power Station Units 2 and 3 Licensed Operator Personnel and Pla'it Staff on Technical Specification 3.0.0
REFERENCE:
Letter from D. M. Smith (PECo) to The Director, Office of Enforcement, dated August 15, 1990; Peach Bottom Atomic Power Station, Units 2 and 3 Response to a Notice of Violation and Remittance of Civil Penalty - NRC Inspection Report Hos. 50-277/90-200; 50-278/90-200 and 50-277/90-06; 50-278/90-06
Dear Sir,
In the referenced letter, Philadelphia Electric Company (PECo) committed to formally train Peach Bottom licensed operator personnel and plant staff on Technical Specification 3.0.0 using the involved incident and other industry events to reinforce Technical Specification compliance and operability determinations, it was intended that this training would be incorporated into licensed operator continuing training by December 1, 1990.
Upon further review, it was determined that procedural guidance for Technical Specification 3.0.D would be more beneficial than training alone.
Therefore, the above training was postponed until the procedure could be developed and approved. The procedure has been approved and is now in effect.
Additionally, the requirements of the procedure has been disseminated to the appropriate licensed personnel through the required reading program, it is now projected that training on Technical Specification 3.0.0 will be implemented during the second quarter of 1991.
Sincerely,
)
(y)003 9104160392 910403
{DR ADOCK0300g{7
/
d Director, Office of Enforcement
,Page 2 cc:
R. A. Burricelli, Public Service Electric & Gas T. M. Gerusky, Commonwealth of Pennsylvania J. J. Lyash, USNRC Senior Resident inspector T. T. Martin, Administrator, Region 1, USNRC H. C. Schwemm Atlantic Electric R. 1. McLean, State of Maryland J. Urban, Delmarva Power bcc: J. A. Basilio 52A-5, Chesterbrook G. J. Beck 52A-5, Chesterbrook J. A. Bernstein 51A-13. Chesterbrook R. N. Charles 51A-1, Chesterbrook Commitment Coordinator 52A-5, Chesterbrook Correspondence Control Program 618-3, Chesterbrook J. B. Cotton 53A-1, Chesterbrook E. J. Cullen S23-1 Main Office A. D. Dycus A3-IS, Peach Bottom E. P. Fogarty A4-4H, Peach Bottom J. F. Franz A4-1S, Peach Bottom A. A. Fulvio A4-1S, Peach Bottom D. R. Helwig 51A-11, Chesterbrook R. J. Lees, NRB 53A-1, Chesterbrook C. J. McDermott 513-1, Main Office D. B. Miller, Jr.
SM0-1, Peach Bottom PB Nuclear Records A4-2S, Peach Bottom J. M. Pratt B-2-S, Peach Bottom L. B. Pyrih 638-5, Chesterbrook J. T. Robb 51A-13, Chesterbrook D. M. Smith 52C-7, Chesterbrook