Interim Deficiency Rept Re HVAC Damper Actuator Defects. Torque Tests & Analyses Still Required for 10 Damper Actuators in VP & Vq Sys.Tests Cannot Be Performed Until Ductwork Installation Complete.Next Rept by 830715
ML20072R020
Person / Time
Site: Zimmer
Issue date: 03/24/1983
From: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, LOZ-83-0005, LOZ-83-5, NUDOCS 8304050417
Download: ML20072R020 (2)


Text

o' 1"

s

,4+a h

$4 9 THE CINCINNATI GAS & ELECTRIC COMPANY suf^ '

' ~~

CINCINN ATI. OHIO 45201 March 24, 1983 LOZ-83-0005 E. A. BORGMAN N stNf0R veCC PRESIDENT Docket No. 50-358 U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 Attention:

Mr. J.G. Keppler Regional Administrator Gentlemen:

RE:

WM. H. ZIMMER NUCLEAR POWER STATION - UNIT 1 10CFR50.55(e) - ITEM M HVAC DAMPER ACTUATOR DEFECTS W.O. 57300, JOB E-5590, FILE NO. 956C,11-14 This letter constitutes a follow-up t,) our interim report, QA-2178, dated December 21, 1982, and provides the status of the corrective actions for the subject 10CFR50.55(e) deficiency.

As indicated in our previous report, actual field torque measurements on the damper actuators and analysis of the torque data by Sargent & Lundy has determined that:

1.

Three actuators require replacement; 2.

Two actuators require spring replacement; and 3.

Three actuators require spring height adjustment.

In addition, torque tests and analyses are still required on ten damper actuators in the VP and VQ systems. These tests cannot be performed until the VP and VQ system ductwork installation is complete. Progress on this work l

continues to be impacted by the NRC November 12, 1982 " Order to Show Cause I

and Order Immediately Suspending Construction". A follow-up report will be submitted by July 15,1983.

We trust the above will be found acceptable cs an interim report under I

10CFR50.55(e).

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY By E.A. BORGMANN SENIOR VICE PRESIDENT RNT/KRK/bef 8304050417 830324 MAR PDR ADOCK 05000358 S

PDR

_j_bl

Mr. J.G. Keppler 2

March 24, 1983 Regional Administrator LOZ-83-0005 cc: NRC Office of Inspection & Enforcement Washington, D.C.

20555 NRC Senior Resident Inspector Attn:

W.F. Christianson Zimmer Project Inspector Region III