Responds to NRC Re Violations Noted in IE Insp Repts 50-321/83-13 & 50-366/83-13.Corrective Actions:Carbon Filter Replaced & Criteria for Carbon Filter Testing Being Evaluated.Results & Schedule Will Be Available by 830714
ML20072M561
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 06/16/1983
From: Gucwa L
GEORGIA POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20072M550 List:
References
NED-83-352, NUDOCS 8307140472
Download: ML20072M561 (2)


Text

4 n.*

Georgia Power Company 333 P,edmont Avenue Atlanta, Georg.a 30303 Tetephone 44; S26 6526 U S N R C R E GIO N.'I Yls'tJn N 4 sis ATLA M NOPGlA Atlarta, Georg a 30302 j

83 J'JN 21 A 9 : 4 6 Georgia Power L T. Gucwa

!* ^? T" " " N 5 **

Chret tbclear Engineer Power Generat on Department ED-83-352 June 16, 1983 U. S. Nuclear Regulatory Commission

REFERENCE:

Office of Inspection and Enforcement RII: JPO Region II - Suite 2900 50-321/50-366 101 Marietta Street, NW Inspection Report Atlanta, Georgia 30303 83-13 ATTENTION:

Mr. James P. O'Reilly GENTLEMEN:

The following information is submitted in response to Inspection Report 83-13 concerning the inspection conducted by Mr.

R.

V.

Crlenjak and Mr.

P. Holmes-Ray of the PRC office on March 26 - April 23,1983.

One apparent violation was identified.

Violation Technical Specification 4.12.A.2.a.

requires that DOP, halogenated hydrocarbon, and carbon sample analysis shall be performed at least once per operating cycle, not to exceed 18 months, or after every 720 hours0.00833 days <br />0.2 hours <br />0.00119 weeks <br />2.7396e-4 months <br /> of system operation or following painting, fire or chemical release in any ventilation zone communicating with the system.

Contrary to the above, no samples were taken following extensive control room modifications which included painting and gluing.

Routine samples (18 month) were taken in March 1981 and again in February 1983.

The February 1983 samples showed a degraded system in train "A" of control room ventilation.

This is a Severity Level IV Violation (Supplement I).

Response

Adnission or denial of alleged violation: The violation occurred.

Reason for violation:

Control room filter trains were not tested because personnel responsible for performing the surveillance test were not notified when painting, fire, or chemical releases had occurred in the ventilation zone communicating with the control room filter train system.

8307140472 830627 PDR ADOCK 05000321 O

PDR

Georgia Power A U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region II - Suite 2900 June 16, 1983 Page Two Corrective steps which have been taken and the results achieved:

The carbon filter of control room filter train "A" was replaced with new activated carbon and satisfactorily tested on March 25, 1983.

An evaluation is in progress to determine the need for, and scope of, criteria for carbon filter testing following painting, fire, or chemical releases in any ventilation zone comunicating with a carbon filter train system.

Future corrective steps which will be taken to avoid further violations:

Final corrective actions will be based on the results of the evaluation discussed above.

Results of the evaluation and a schedule for future corrective actions will be determined by July 14, 1983.

Date when full compliance will be achieved:

Full compliance was achieved on March 25, 1983, when the "A" filter train was replenished with new activated carbon and successfully completed the surveillance test.

Very truly yours, L. T. Gucwa SCE/mb xc:

J. T. Beckham, Jr.

H. C. Nix, Jr.

J. P. O'Reilly (MIC-Region II)

Senior Resident Inspector

.,,,