Advises That Plant Const Will Be Complete by Aug. Administrative Work Necessary for Fuel Load Will Not Be Complete Until Sept
ML20072M485
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 07/11/1983
From: Reveley W
HUNTON & WILLIAMS, LONG ISLAND LIGHTING CO.
To: Brenner L, Carpenter J, Morris P
Atomic Safety and Licensing Board Panel
References
ISSUANCES-OL, NUDOCS 8307140447
Download: ML20072M485 (1)


Text

-

. 1,, '.

IIU NTON & WILLI AM S N'p 7o7 East MAm STRett P. O. Box 1535 l..

v

. e a f.u, toe.o Racnwono, VIROINEA 23212 e.i..c o.pd

.sei..vt uc,.. w.

g

..oa retso m o..oa no.

_J

,o..,...,,,a u 1,; i

.:.e.......

-m................

3

'a='.; ;"; "'"" **"

July 11, 1983 S

[$k, f.,,,....o.,...

x Q, l

Lawrence Brenner, Esq.

Dr. James H. Carpenter Administrative Judge Administrative Judge Atomic Safety and Licensing Atomic Safety and Licensing Board Panel Board Panel U.S. Nuclear Regulatory U.S. Nuclear Regulatory Commission Commission Washington, D.C.

20555 Washington, D.C.

20555 Dr. Peter A. Morris Administrative Judge Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, D.C.

20555 In the Matter of LONG ISLAND LIGHTING COMPANY (Shoreham Nuclear Power Station, Unit 1)

Docket No. 50-322 (OL)

Gentlemen:

LILCO continues to believe that there is a high proba-bility that Shoreham will be physically complete in August.

It no longer appears likely, however, that all administrative work necessary for fuel load will have been finished by then; the Company expects that this work will carry over into September and be completed during that month.

Very truly, ours,