Requests That Status of Inspector Followup Item 2 from IE Insp Rept 50-348/81-05 Re Pressurizer Inservice Insp Indications,Be Reviewed & Rept Corrected,Based on Disposition of Indications Per Util
ML20072M417
Person / Time
Site: Farley 
Issue date: 04/05/1983
From: Clayton F
ALABAMA POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8307140427
Download: ML20072M417 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _

Memng Address

600 North 18th Street Post Offici Box 2641 Birmingham, Alabama 35291 Telephone 205 783-6081

-WRC pE F. L Clayton, Jr.

Senior Vice President Alabar11a Nwn Flintridge Building 33 APR 13 A10 : 32 ee soonern seanc s-,

April 5,1983 Docket No. 50-348 Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Commission Region II, Suite 3100 101 Marietta Street, N.W.

Atlanta, Georgia 30303 Joseph M. Farley Nuclear Plant - Unit 1 NRC Region II Inspection Report No. 50-348/83-02

Dear Mr. O' Reilly:

The subject inspection report transmitted on March 10, 1983 discusses the review and disposition of Inspector Followup Item (IFI) 348/81-05-02 entitled " Pressurizer ISI Indications."

The report correctly stated that "during the current outage the indications were re -ex ami ne d.

The inspectors reviewed the record of the re-examination and discussed the matter with the licensee's cognizant plant engineer.

The licensee's findings were that the indications showed no growth."

However, the report then stated that "this item will remain open for followup by Region II in review of further examinations to be performed by the licensee at the next refueling outage."

This statement does not accurately describe Alabama Power Company's intended disposition of these indications as discussed during the audit.

Alabama Power Company reported the disposition of these indications to Region II by Mr. F. L. Clayton's letter of February 21, 1983.

Thi s report provided the re-examination results, characterization of the indications and an evaluation of results.

In conclusion, this report stated that " based upon the re-examination data which showed no significant change from the previous data and the acceptability of the uncorrected indication dimensions under the construction Code requirements, Alabama Power Company considers this item complete and no further action is required."

The information reported was consistent with the discussions held with the NRC inspectors during the inspection of January 31 through February 4,1983.

fo$o jg PDR l

/e 1 Eof

1 i

Mr. J. P. O'Reilly

^P U. S. Nuclear Regulatory Commission Pag 2 Alabama Power Company respectfully requests that Region II review the status of IFI 348/81-05-02 and correct the subject inspection report accordi ngly. As previously stated, Alabama Power Company considers this item complete. Examination of the Pressurizer Weld No. 4, in which the indications were found, will be continued in accordance with the NRC approved Farley Nuclear Plant Inservice Inspection Program.

Yours truly, F. L. Clayton Jr.

FLCJr/ STB:ddr-D18 cc: Mr. R. A. Thomas Mr. G. F. Trowbridge Mr. S. A. Varga Mr. E. A. Reeves M:'. W. H. Bradford l