Public Version of Rev 2 to Emergency Plan Implementing Procedure 1903.61, Communications Equipment Tests. Revised Index Encl
ML20072K567
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 03/16/1983
From: James M. Levine
ARKANSAS POWER & LIGHT CO.
To:
Shared Package
ML20072K519 List:
References
1903.61-01, 1903.61-1, NUDOCS 8303300633
Download: ML20072K567 (7)


Text

.

. ARKANSAS POWER & LIGHT COMPANY t- Arkansas Nuclear One

\ -" RECORD OF CRANGES AND REVISIONS FOW NO. 1000.06A ESTERdET)CY PLAN PROCEDURE REV. # 12_ PC #

7(* V l Safety Related YES d NO O C0!DIUNICATIONS EQUIPMENT TESTS "th .

1903.61 REV. 2 -,

l ,, f, -

-[\.] ,ll *

- yh ,.

.'sTUQ?,'_i iii*s p : jf{Jil.-f;}

" -i'.a1.1;.- -

e

.w . i .

.I ,1 ' , :{..

} 5,

-~

,4

'" PkGE REV PC# PAGE REV PC# PAGE REV PC# PAGE REV PC# PAGE REV PC#

J l 2 2 2 3 2 4 1 5 2 6 2 7 2 8 1 l

APPROVED BY: APPROVAL DATE

&/n 3,y/k Qgg REQUIRED EFFECTIVE DATE:

h / (General Manager) 8303300633 830325 PDR ADOCK 05000313 F PDR

PLANT MANUAL SECTION: PROCEDURElWORK PLAN TITLE: NO:

EMERGENCY PLAN Poorenttpr copMitMTrATTOMs egitTourMT Tr9TS 1003.61 PAGE 1 of 8 aavision ARKANSAS NUCLEAR ONE CHANGE 2 o*Te DATE

,1<20 a2 1.0 PURPOSE The purpose of this procedure is to provide the requirements for testing the emergency communications equipment and to identify the necessary. roster /

call lists that must be verified reriodically.

2.0 SCOPE This procedure applies to communications systems and roster / call lists that would be used during an emergency situation at ANO.

3.0 REFERENCES

3.1 References Used in Procedure Preparation 3.1.1 Arkansas Nuclear One Emergency Plan 3.2 References Used in Conjunction with this Procedure 3.2.1 None 3.3 Related ANO Procedures 3.3.1 None 4.0 DEFINITIONS None 5.0 RESPONSIBILITIES .

l 5.1 The Emergency Planning Coordinator is responsible for coordinating ANO emergency communications equipment tests as required by this procedure.

6.0 DESCRIPTION

6.1 The following communications equipment / systems are available for use -

during an emergency:

6.1.1 Continental Telephone system 6.1.2 ANO plant phone system 6.1.3 Gai-tronics paging system 6.1.4 ANO radio system 6.1.5 NRC ENS (Hotline) phone 6.1.6 NRC HPN phone 6.1.7 AP&L Microwave 7 - --. g. . w _

PROCEDURE / WORK PLAN TiiLE: NO:

PLANT MANUAL SECTION:

EMERGENCY PLAN conernitor ( nimf MT F3TTo'fc ronte'fe'P Tectc 1onS A1 PAGE 9 n cn n >o'a, ARKANSAS NUCLEAR ONE aavimoa CHANGE 2 o*T=

DATE 6.2 The following roster / call lists are maintained in each Control Room for use during an emergency:

6.2.1 Duty Emergency Coordinator Roster .

6.2.2 Staff Augmentation Group Roster / Call List 6.2.3 Beeper Assignment List 7.0 INSTRUCTIONS 7.1 The following items shall be accomplished on a monthly basis by the Emergency Planning Coordinator or'a designee:

7.1.1 Verify the operability of the direct Continental Telephone lines to each Control Room.

7.1.2 Verify the operability of the radios located in at least one of the following areas:

A. Unit One Control Room B. Unit Two Control Room C. Technical Support Center D. Emergency Control Center E. Site Vehicles (except Security vehicles)

F. Communications Equipment Locker G. AP&L Local Office

(

7.1.3 Verify the operability of the NRC-HPN phones in each one of the following locations:

A. Unit One Control Room .

l

B. Technical Support Center C. Emergency Control Center s

e

PLANT MANUAL SECTION: PROCEDUREiWORK PLAN TITLE: NO:

EMERGENCY PLAN eencentme cometmir a, Tmts vnmouruT tests 1903.61 PAGE 3 of 8 ARKANSAS NUCLEAR ONE aavisma CHANGE 2 oars DATE tu29e82 7.1.4 Verify the telephone numbers for the following groups:

A. Nuclear Regulatory Commission B. Arkansas Department of Health

.C . Little Rock Control Center D. Four - County Sheriffs E. National Weather Service 7.1.5 Verify the placement and correctness of the roster / call lists maintained in the following locations:

A. Unit One Control Fcom B. Unit Two Control Room 7.1.6 The following communications equipment / systems do not re-quire additional testing due to the indicated reasons:

A. NRC-ENS (Hotline) phone located in each Control Room (used daily by the Shift Supervisors).

B. ANO plant phone system, AP&L microwave system and the Gai-tronics paging system (used as a part of normal plant operation).

C. Early Warning System (tested by the State of Arkansas).

7.2 Form 1903.61A, " Monthly Communications Testing Record", should be com- ~

pleted to document the performance of the monthly test.

7.3 Communications links between the plant, federal, state and local emergency operation centers and field assessment teams shall be tested annually (this may be done as a part of the plant's annual exercise). Form 1903.61B should be completed to document this test. .

8.0 ACCEPTANCE CRITERIA 8.1 Tests shall be carried to a conclusion such that the test is adequate to verify equipment operability.

8.2 Upon discovery of inoperable emergency' communications equipment, ac-tion shall be taken to initiate repair of the equipment.

NOTE: If loss of radio communication with offsite agencies occurs then an Unusual Event Emergency Action Level must be declared per procedure 1903.10, " Emergency Action Level Response".

~

L _ _ --nam.

k PLANT MANUAL SECTION: PROCEDURE / WORK PLAN TITLE; NO:

c EMERGENCY PLAN dl Poot-enURt' COMMUNICATIOMO FOUIPF MT TESTS 1903.61 Al ! PAGE 5 of 8

' M ARKANSAS NUCLEAR ONE aEvi: ion 2 DATE 11/29/82 CHANGE DATE r

ATTACHMENT 1 l l l 4 l l l 6 ,I i i .l l l t  ! ! 1 l 1 I I x1 di l l l gl I Conusunication Links Available l l l l l l l l 8l gl l l w[ { l p-Between the Emergency Response l l l l l l l l gl al $1 l l Ul l l Centers l l l l 1 g) gl 31 m l l l l l 1 .1 l l 51 I El cl Cl l 1 glC15 li l i ,l E l 2 l e l ~.11 Il  ! lM i l I

I el l =l l

gl dj 01 : I I ;;l a l l IImgin i I i

I l di 5i $l di o I wl dl 31 l 1 81* 1,o I l il .lgd8J i t v I ul al i l 21 ~l di l l 2 D1 di el 2 l l el 21 51#1ElgdEM I 01 Sl ogud i i s2i "l :1 E I I=l*l i 1=l 31 il 8 l "l'.d 8 9 3 51I al il *ni ! llIdl*@Izlgl31 l El of il El I *IM .d si ml mlLIEld5=9 I

al i gl cl g l "5I l t gi 5 d 8l S I 81 o f o l "EI 8ltpo!

ll #1 21 E l M al el 5 i g g a Il "Ikl gl

- li a'lai;l t

l ,igga tigl'lud=S m

I Si ol - ! of mi s I zi <lml mi 23ang 9

i i 11 11,5 li,e i il i i 11 e i 11 11 e 1 l CCNTROL ROOM l 13 l3,6 13,8 11 l 11 11 l l1,5'11 l6 16 11 l l 1- 14 14.8 (5 !6 16 17 12 18 18 I f8 18 I I I 11 i i i i l I i i 6 1 i i i l l ONSITE OPERATIONAL SUPPORT CENTER!3 l l3 13 11 l1 l1 l1 11 [1 l1 11 l1 l1 l l I4 1 - 14 I I I i 12 I I I f I I l 61,5 1 1 11,6 i i e il 1 i i i i i l CNSITE TECHNICAL SUPPORT CENTER 13,6 l3 l 13,8 11 11 11 12 11 11,8 11 11 l1 11 1 14,8 I4 1- 15 16 16 f7 1 15* 1 f6.Sf6,81 l l 11,6 l 11,6 l l 11 81 il - !8 il l 41 11 11 il l l EMERGENCY CONTROL CENTER l3.8 13 13,8 1 11 l l7 12 l l1,8 l l6,816,31 l l 15 i is  !- 16 6 I i 18 15* ! ! l t l l 1 4 i i l i i i i e i i 1 l l RUSSELLVILLE FIRE CEPARTMENT l1 l1 11 11 l 1 11 11 l1 l1 l1 l1 l1 l1 l

! l 16 1 i f - [6 I i i6 16 i !6 16 I I l 11 i il il i i i i il i 11 11 i l i POPE COWTY SHERIFF OFFICE l 1 1 1 6 l 11 l1 l1 l6 11 l6 l6 l1 l l 16 I I I- 1 I I I I I I I I il I il 6 i i i i e i i l l NRC REGICN IV 0FFICE AND BETHESDAl7 l l l7 i l 11 i - 11 11 1 11 l1 l1 11 l l l  !! 11.7 I I l l ! I l l l l l 4 i i i ,

i i i i i a e i l l AP&L CORPORATE OFFICES 11 l1 l1 l1 l1 11 'l 1 - l1 11 l1 l1 l1 11 l l LITTLE ROCK 12 12 (2 2 l l l l l l l l l 1 I il i i I i i 1 i il i 11 la l l STATE OF ARKANSAS l 11 11,8 , 1,8 [1 11 l1 l1 l-1 11 l6 l6 1 l l OFFICE OF EMERGENCT SERVTCES 8 l l (6 16 I I i [8 l 18 (8 l l l 1,*54 i*5.8 a5,811 11 6 i 11 i i il 11 i i i l DEPARTMENT OF HEALTH 8 l l l l l l1 11 l l- l1 l l 11 l

[1 11 !! l I I I le I i 18 18 I l l l l 1 e i i e i i i e i i i l i

l ST. MARY'S HOSPITAL 11 11 l1 11 11 11 11 11 11'l1 l - 11 l1 11 l l I I I I I I I l i I I I I I I l l 11 l l l l 1 1 1 61 it i i 11 6 l l POPE COWTY l6 lI l1,6 11 11 l1 11 Il 16 l6 11 l - 16 11 l l l EMERGENCY OPERATIONS CENTERS (8 1 18 16.8 16 16 l t 18 18 I i 18 I l .

l il 4 i 1 i i a i 11 11 i 11 i i !

l LOGAN, TELL*, AND JOHNSCN COWTT 16 11 l1,6 l1 l1 11 Il 11 16 l6 11 16 l - l1 l l EMERGENCY CPERATIONS CENTERS 18 ! (8 !6,8 16 16 I i 18 18 I (8 l l l l U.S. CEPARTMENT OF ENERGY j i i j i i i i l i i i i i l l OAK RIDGE RADIOLOGICAL l1 11 11 11 11 11 11 11 11 l1 11 11 11 1-I gg i COCRDINATING CFFICE I I I I l  ! I l l l l i I l l CCMMWICATION LIKKSr 1 - Continental Telephone 2 - AP&L Microwave Telephone 3 - Plant Phone System 4 - Gai-Ironics Paging System 5 - AN0 Radio Frequency 4_

6 - Pope County Sheriff's Radio / Frequency 7 - Hot Line 8 - CES RadioiFrequency 7 Number 8 not applicable.

  • In order for the Cept. of Health to communicate via the ANO radio frequency, the ANO radio **

a scranoler off" position.

must te tn the

- . 4 E

PLANT MANUAL SECTION: PROCEDURE / WORK PLAN title: NO:

EMERGENCY PLAN concenf te r c0?m?"fTr2TTO?fc rOf tTourMT Tt'STS 1003.61 PAGE 6 of 8

^

ARKANSAS NUCLEAR ONE aE - N CHANGE 2 DaTE DATE 11,29,82 y . ARKANSAS POWER & LIGHT COMPANY L Arkansas Nuclear One mte ..-.- - - . ~ , , . . - . . . - . . - . . . . . . - - - _ l a ao. , -

REV. # y PC i Page 1 of 2 1.0 COF21UNICATIONS EQUIPMENT OPERABILITY TEST Date 1.1 Direct Continental felephone Line I i l l Location i Results l l AS0-l l l l ANO-2 I l 1.2 ANO Radios I l l l l Location l Channels Tested l Results l 1.2.1 l ANO-l/ANO-2/ l 1,2,3,4,5,6,7,8 i I l TSC/ECC l 1,2,3,4,5,6 l l 1.2.2 l ANO Van l 1,2,3 l l 1.2.3 l AN0 Packup l 1,2,3 l l 1.2.4 l GM Car l 1,2,3 l I 1.2.5 l 4bD Vehnete l 1,2,3 l l 1.2.6 (Portable Radtos:l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 l Unit l l l 1,2,3 -

l Unit l l l 1,2,3 l Unit l l l 1.2.7 i SCBA Bone i l  !

l Phones l l l l (4 Total) l NA I i 1.3 NRC-HPN Phones C:

l l l l Location l Results l l ASU-l'ANu-2/ISC/ECC l l W E %m b .4

G PLANT M ANUAL SECTION: PROCEDURE / WORK PLAN TITLE.; NO:

EMERGENCY PLAN DQncentfor COMMitMTcATTOM9 enftTpupIT trSTS 1901.r1 PAGE 7 of g

~

ARKANSAS NUCLEAR ONE armia CHANGE

> o*Te DATE

=9m y ARKANSAS POWER & LIGHT COMPANY L Arkansas Nuclear One l

N .......,. --,,,,. ..-,..-,.- . ,,..,.- -----, I F0" ""

~

~

REV. # i FC s ',

Page 2 of 2 1.4 Key Button Pbnes j Locatton l Lines Tested i Results . l I I I i 1.4.1 }l l l lANO-1(Sta.

l l I l

1.4.2 lANO-2(Sta. }l l l 1 1 1 1 1.4.3 (Sta. )l l l lTSC 1 I i 1

1.4.4 (Sta. )l l l lECC 2.0 TELEPHONE NLHEER VERIFICATION I I I Agency l Phone No. l 2.1 l_C l NR l l 2.2 i Department of Health l i 2.3 l Little Rock Control Center l l 2.4 l Nattonal Weather Service l l 2.5 l Pope County Sheriff l l 2.6 l Yell County Sherif f l l 2.7 l Johnson County Sheriff I l 2.8 l Logan County Sheriff I l 2.9 i Pope Co. AM ulance Service l I 2.10 l Russellville Fire Department  ! l 2.11 i St. Marv's Hospital l l 2.12 1 Millard Henry Clinic l l

! I 2.13 l Babcock & Wilcox 2.14 l Combustton Engineering i i 3.0 ROSTER / CALL LIST VERIFICATION I I 1- 1 l List l ANO-1 l ANC L i 3.1 l Duty Emergency Coordinator l l l g i Staff Augmentation Group I l l 3.2 i Engineertng (T.S.) l l l l Health Physics l l l l l 3.3 i Beeper Asstenment List l 4.0 CORRECTIVE ACTION REQUIRED (IF ANY):

'=

I I

l l

l 1

Performed By

" m ;

[

  • L = L =