Public Version of Revised Emergency Plan Implementing Procedures EP-103, Alert Response, EP-104, Site Emergency Response & EP-105, General Emergency Response. Revised Index Encl
ML20072K492
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 01/12/1983
From:
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To:
Shared Package
ML20072K469 List:
References
PROC-830112, NUDOCS 8303300594
Download: ML20072K492 (32)


Text

.

(, i ... .-. . . . . _

~

tY'OM-

= n e m c v F w se m m m I w :x t /

s N

. . ~

' RE EIVED mmm2m JAN 141983

% ,,yi,1, Date No. Date Ntaber

  • Title EP-101 Classification of Emergencies ,

06/11/P2 6 0(/11/82 r EP-102 Unusual Event Response 06/10/82 6 05/10/82 EP-103 Alert Response . 01/12/83 7 01/.12/83 * .

EP-104 Site Plmergency Response 01/12/83 7 01/12/83

  • EP-105 General Emergency Response 01/h.2/63 7 01/12/83

Activation C3/07/82 4 09/07/82 EP-202 Operational Support Center (OSC) Activation 09/07/82 3 09/07/82 EP-203 Emergency Operations r acility (EDF) Activation 09/07/82 4 09/07/82 EP-205 Radiation Protection 'nNun Activation 04/08/82 3 04/08/82

{

EP-205A Chemistry Sangling and Analysis Group 05/25/82 4 05/25/82 ,

EP-205A' Operation of Post Accident-

  • 1 Sampling Station 09/07/82 1 09/07/82 EP-205A Obtaining Drywell Gas Sanples .

from containment Atmosphere Dilution

.2 .

Cabinets 05/26/82 0 05/26/82 EP-205A' Retrieving and Changing Sanple

.3 Filters and Cartridges from the Drywell radiaticn Monitor Durirry Emergencies s 05/25/82 0 05/25/82 EP-205A Obtaining Drywell Gas Sanples

.4 frcun the Drywell Radiation Monitor Sampling Station . 05/25/82 0 05/25/82 .

EP-205A Obtaining Reactor Water Sanples .

.5 from Sanple Sinks Following Accident Conditions 05/25/87 0 05/25/82 EP-205A Obtaining Canal Discharge Water

.6 Sanples Following Radioactive Liquid Releases Af ter Accident Conditions 05/25/82 0 05/25/82 C,

EP- 205A Obtaining the Iodine and 8303300594 830324 05000277 k PDRF ADOCK PDR

- . , , a - .n . - . . . .

. 1 , .

ED IndeX

- . FNCRCFNCY PUW PROC?rXJRRS INrffDC Paq2 2 Rev. 27

  • PEACH BOTIO4 UNITS 2 AND 3 1/12/83
  • Review Rev. Revision C M*r e le Data =. =te

.7 Particulate Sanples from the Main Stack and Poof Vents Tollowing Accident Canditions 06/04/82 0 06/04/82 EP-205A Obtaining Liquid Radwaste Sancles

.8 from Radweste Sanple Sink Following Accident conditions 05/25/82 0 05/25/82 EP-205A Obtaining Samples from condensate -

.9 Sanple Sink Following Accident Conditions 05/25/82 0 05/25/82 EP-205A Obtaining off-Gas Samples from

.IO the Off-Gas Hydrogen Analyzer -

Following Accident Conditions 05/25/82 0 05/25/82 EP-205A Sanple Preparation and Chemical

.11 Analysis of Highly Radioactive Liquid Samples 05/25/82 0 05/25/82

~

En-205A Sanple Preparation and Analvsis

.12 of Highly Radioactive Particulate 0 05/25/82

{ Filters and Iodine Cartridges Sanple Preparatian and Analysis of 05/25/82 EP-205A

.13 Highly Radioactive Gas Sanples 05/25/82 0 05/25/82 EP-205B Radiation Survey Groups 10/20/R2 3- 10/20/82 EP-205C' Personnel Dosimetry Bionssay - .

and Respiratory Protection Group 04/08/82 2 04/08/82 5 06/04/82

'EP-206 Fire and Damage Team Activ'ation 06/04/82 EP-206A Fire Fighting Group 06/04/82 3 06/04/82 l

EP-206B Energency Repair Group 05/23/82 2 05/23/82 EP-207 Personnel Safety Team Activation 05/11/82 4 05/11/82 EP-207A Search and Rescue 04/14/82 2 04/14/82 EP-207B Personnel Accountability .

05/11/82 3 05/1152

-EP-207C First Aid 04/14/82 2 04/14/82

- EP-207D Personnel Monitoring and Decontamination 04/08/82 2 04/08/82 O EP-207E Vehicle and Evacuee Control Procedure 04/08/82 0 04/08/82 y - - - --

_3

- - r- - r _ _ _ _ .

,. a i

Ep Index

"~

,- . FNERGFNCY MMI PROCEDURES INDTM Page 3' Rev. 27

  • PFJCH POTICM UNI 1S 2 AND 3 1/12/83 *

~

Review Rev. Revision

(.

, Nunber Title N Date No. Date x

EP-207F Vehicle Decentaminati'an Procedure 04/14/82 0 04/14/82 77 ~

EP-208 Security Team 04/01/81 0 04/01/81 EP-209 Telephone List For Bnergency use 12/23/82 6 12/23/82 EP-209 Immediate Notification Call List ~

Appendix A 12/03/82

/6 10/20/82 EP-209 Philadelphia Flectric Appendix B Company Officials- .

07/23/81 1 07/23/81 EP-209 Peach Bottom Station Supervision Appendix C ,

12/23/82 7 12/23/82 .

EP-209 On Site Bnergex:y Team Leaders Appendix D-1 12/03/82 4 07/13/82 -

EP-209 Radiaticn Protecticm Team _

Appendix D-2 12/23/82 7 12/23/87 EP-209 Fire and Damage Team C Appendix D-3 12/23/82 6 12/23/82 EP-209 Personnel Safety Team Appendix D-4 12/23/82 7 12/23/R2 EP-209 Security Team Appendix D-5 06/08/82 3 04/26/82 EP-209 . Re-Entry and Recovery Team ,

Appendix D-6

~

,12/03/82 2 .04/26/82 EP-209 Technical Support Center Group Appendix D-7 12/23/82 6 -12/23/82 EP-209 Corporate anergency Team Leaders and Appendix E Support Personnel 12/23/82 7 12/23/82 EP-209 U. S. Government Agencies

- Appendix F 12/03/82 3 .10/20/82 EP-209 Bnergency Management Agencies Appendix G 17/03/82 2 10/16/81 EP-209 Company Consultants Appendix H '12/23/82 4 12/23/82 "E h / EP-209 Field Supoort Personnel Appendix I-l 12/23/82 9 12/23/87 l

4- _ y=. , _

.=. - ~ _ = ---_=~:~:-m'tr .7-T3.=

. . EP Trylex TNrnCFNCY PTNI fifd.r.u!RTlS TNDFX Pago 4

-

  • Rev. 27
  • PFJCH BCm0M UNI'IS 2 AND 3 1/12/83
  • Review Rev. Revision Ntaber Title Date N6. Date EP-209 Chemistry & Health Physics Contractor Appendix I-2 Call List 12/23/82 6 12/23/82
EP-209 Nearby Public and Industrial Users Appendix J Of Downstream Waters 12/23/82 3 12/23/82 EP-209 Miscellaneous Appendix K 12/03/82 4 10/20/82 EP-209 Local PECo Phones Appendix L 12/01/82 1 07/23/81

. EP-209 DELETED DELETED Appendix M

, EP-209 Medical Support Groups Appendix N 12/01/82 4 07/13/82 EP-209 Staffing Augmentation - 60 Minute Appendix P Call Procedure

~~

12/23/82 4 12/23/82

('

EP-301 Operating the Evacuation Alarm and Pond Page System 12/23/82 1 12/23/82 EP-303 Partial Plant Evacuation -12/22/81 1 12/22/81 EP-304 D P. L E T E D EP-305 Site Evacuation . 09/07/8'2 4 09/07/82 EP-306 Evacuation of the Informat. ion Center 05/25/Q2 2 05/25/82 ,, ,

l EP-307 Reception and Orientation of Support

! Personnel -

04/12/82 0 04/12/82

! EP-311 Handling Personnel with serious Injuries, Radioactive Contamination Exposure, or Excessive Radiatiicn Expoenre i0mergency Director Functions 04/08/82 3 04/08/82 1

i EP-312 Radioactive Liquid Release (Onergency ,,

j ~ Director Functions) . 04/01/81 0 04/01/81

EP-313 Control of 'Ihyroid Blocking (KI)

Tablets 04/08/82 0 04/08/82 EP-316 Cumulative Population Dose '

l I

h _.

calculations 05/06/82 2 05/06/82 l

EP-317 Direct Recwn.erdations to County i .

\

= =. __-w _

e,

. .* . imIrWx FW.RtTNCY PTAN Pfor2Tf1RPS TNDIM Parte 'i

. Rev. 27

  • PPACFI BO7KM UNITS 2 AND 3 1/12/83
  • Review Rev. Revision C- Mtaber ' Title Date No. Date Bnergency Management and Civil Defense Agencies 04/14/82 0 04/14/82 EP-318 Liquid Release Dose Calculation Method for Drinking Hater 05/06/82 0 05/06/P2

.E F319 Liquid Release Dose Om1mlation Method -for Fish 05/06/82 0 05/06/82 EP-320 Procedure for Leaking Chlorine 03/12/82 1 03/12/82 EP-325 Use of the Containment .

Radiation Monitor to Estimate Release Source D.rm '

06/09/82 0 06/09/82 EP-401 Entry for Emergency Repair, Operations, and Search and Rescue . 04/08/82 3 04/08/82 EP-500 Review and Revision of Emergency Plan (FSAR Appendix 0) - -

04/01/81 0 04/01/81 s

m.

6 F

o N

O

./

Paq21 Cf 9, Rev. 7

. . co ,. y,} 33 fig

~

TS 2 A 3 . .

C. sa control

- say ,IL. e -

- m.taem ,nocm,,r. ~s j st .t ton ceper. -.--

j offiac --

FP-m s KWP RF.qtgNgy,

. . ei~

Pt N

'Itidefine site resoonse to an Alert.

wr ..vrnTi ,

'l. Peach %ttom Atomic Powc 9tation anergency Plan

2. hTRm 0694
3. Go-15 Iccal Evacuation
4. F.P-101 Plassification of Emergencies APFNDICRC _. .

s EP-103-1 Elert ?!otification Checkoff List

f. EP-103-2 Personnel Call Record EP-103-3 nnergency Fxposure Limits (Rnergency Plan Table 6.1)

PRTN.MCPE 1.. Planned. radiation expnsures should be limited to the ,

administrative guide levels in Appendix EP 103-3, Emergency Expnsure Limits.

4 IrNPnIAw. xmov, 1.0 Shift Suoervision shall:

1.1 Assume the role of Interim Emergency Director.

1.2 Activate Emergency meams as necessary.

I

! 1.3 Direct the evacuation of affected areas as necessary.

l' P.efer to the following procedures: .

GP-15 Taal Evacuation l Fa-303 Partial Plant Evacuation no 305./ Site Evacuation l O 2" . s' .

i _.. _

_._.._______....___[._..-.u.

r_ - - - - . - - - . . . . ~ . . _ . . .,.. .

.._.,n . , .

EP-103'

- . Paq2 2 cf 9, Dev. Y EP 306 Evacuation of the Information Center .

CJ. 1.4 Contact the 9tation 9uperintendent and the Shift wchnical Advisor, inform them of the situation; ,

1.5 rill out the Standard Prompt Notification mssage check-off Accendix EP 103-1 and give it to the comunicator (C or higher classification) and direct the Cceunicator to comence notification of the appropriate parties as soecified in Section 2.1 of this procedure. We Cbmmanicator shall man the IGC RED telephone on a continuous basis if required by procedure A-31. If comunicater is required for urgent plant operations related to the emergency, the concurrence for securing the phone should be obtained from the NRC prior to securing this telephone.

t 1.6 nirect the Shift Clerk to activate the 60 minute call list using EP 209 APP P. If Shift Clerk is not available, this function shall be assigned to any available individual.

1.7 Direct one of the on-shift Isc Technicians to activate the mechnical Support Center and Emergency Operations Pacility in accordance with EP 201 and EP-203.

Inform shif t clerk which Isc technician will activate the centers at Unit 1 in order that-the clerk will know which remaining IAC technician to call for the prmnt mobilization proce6ure.

.l 1.8 Direct the Personnel 9afety Team Leader to initiate cite radiation surveys as necessary, in accordance with EP-l 2059, Padiation Survey Groups. ,

f 1.9 Assign an Ooerations Support Center Coordinator (senior shift "O or A?O available)' and direct available shift personnel to l

report to the Operations Support Center on 135" elev.' turbine ,

bldg. and to activate it.in accordance with EP 202, if habitable. ~

If this Onerations Suppcirt Center is NOT habitable, direct ' shift personnel to report to the Control Room.

1.10 closely monitor conditions to determine present hazards

  • to personnel aM potential accident conditions that may develoo. .

1.11 If release has occurred, dispatch a plant survey team member to obtain a site boundary' dose rate as soon as practicable.

l 1.12 If necessary, initiate inplementation of EP-317 & EP-316.

Direct recomraenr3ations to Cbunty Emergency Management Agencies ~

nnd c'tatlative ponulation dose calculhtions.

l i

2.0 Corminicator shall:

~

?.1 Perform notifications on Appendix 103-1 using the alert

{  ??otification Check Off Appendix EP 103-1. See EP 209, Annendix A for a&.itional telephone numbarn.

\

1 ..._.-.,7- ,. a , ,, ._+._____,-

m.

. e . . ,

t ,- Paqa 3 cf 9, Rev. 7 2.2 -Penort to the Emer'aency Director or Interim Emergency

{"'. ~ Director when notifications are ocznplete. -

2.3 ?'an the REr$ NBC telephone if required by A-31 until situation stabilizes and RED telephone comunication may be secured.

3.0 Operations supnort center coordinator or his designee shall:

3.1 Activate the operations Support center on 135' elev. turbine bldg, if it is habitable, in accordance with EP 202. If this Operations 9upport Center is not habitable, report to the control Foom.

4.0 Personnel Safety Team Leader shall:

{

4.1 Tnitiate site radiation surveys in accordance with EP-20SN, Padiation Survey Groups when directed by the Emergency Director. ('rhe MP field office on 116' elev. turb. b1dg.

will serve as the HPrc OSC).

5.0 Shift Irc Technician shall:

5.1 ,ctivate

  • the 'mc and WF when directed by Interim Faergency director in accordance with EP 201 using Appendix EP-201-2. -

k*

6.0 Shift Clerk shall:

6.1 contact iMividuals on En 209 APP P to call in those inclividuals to man TSO and required Emergency Teams (60 ninute call list) . Document contacts on EP.209 ADP P.

6.2 Inform Interim Emergency Director or Emergency nirector

.when contacts are corfoleted. .

m o

WEG

/

f

" ' * * ' ' ' ' ~ ~'* '""

8 ..2. _ , _

. + . **

,.-..-,,_-..-..._..-......-~~*- ,'----'.

  • ~

~. . . . . . - . - , . . - . , . - ,

- EP-103 Paga 4 of 9, Rev. 7 Por/J74-UP 7CTIOW h~-

1.0 Paernency nirector shall: .

1.1 Periodically evaluate the event classification in accord-ance with EP 101, Classification of Emergencies, and escalate or deescalate the classification, as necessary. .,

1.2 nhtain the results of the cumulative Population pose calculations from the Radiation Protection Team TAader and onsite radiation surveys from the Personnel Safety Team Leader, as necessary. -

1.3 verform actions as necessary to mitigate condittms of the emergency situation. -

1.4 Determine which ac'k!itional support personnel are necessary for emergency functions and direct the Shift Clerk or other I assigned connunicator in TRC to contact those personnel.

1.5 Provide site personnel with P.A. s.peaker announcements for l

any major changes in plant emeroency status, such as changing emergency action levels and evacuations.

l

~-

2.0 Station 9ucerintendent shall: - -

s f 2.1 Peport to the Technical Support Center or control

( Poom for a briefing of the situation. -

[ 2.2 Assume the role of Fergency Director by formally relieving the

, Interim Bneraency Director (Shift 9uperintendent). Announce that he .

l- has assumed the role of Emergency Director to the ascembled Technical l nupport Center personnel. <

~

2.3 v erify the emergency classification.

2.4 verify that the Technical Supnort Center, the Fmergency Operations 'acility, and the Operations

~

Support Center have been activated.

I 3.0 Operations Suopxt Center coordinator shall:

3.1 $1otify the Interim Emergency Director when their resoective operations 9upport Center is activated.

3.2 Sunport. the Control Room and shift Supervision as -

necessary.

4.0 Radintion Protection Team Leader shall:

4.1 neport proaress and results of Cumulative Population Pose Calculations to the Fmergency Director,as necessary.

h l 5.0 Per.vnnel 9afety Team Leaier shall:

E _ - -'

= e= ew=w--e=., = , .m . J eg-w w mi ,9 ag w- . v . . -- ., . a, .-

.,=-e. ,, e m p- .,. , , , , , , 9

r- -

. ,~ .

. . EP-103

. . . page 5 of 9, Rev. 7 5.1 Paport progress and results of onsite radiation surveys to

{ the Emergency Director as necessary.

6.0 Shift Clerk or assigned T9C conmunicator shall: -

5.1 tv>tify additional support personnel to report to the plant as directed by the Interim anergency Director. Refer to EP 200 Document on At? EP-103-2.

5.2 Notify the Tnterim Emergency Director when the additional support personnel have been notified.

i 7.0 Shift I&C %chnician shall:

' 6.1 Tnform the Interim % rgency Director when the TSC and FDP are activated.'

6.2 Station himself at the 1SC as data display (CCP7) operator as directed by the Energency Director.

l 1

!I i

,I I s IC I

I f .I m .

l -

ll lI I

C

,I .

I 4

n;

.I

\

....-.3-_;;- _-- - --": 7'~- :L:IQ

. T~T:

EP-103 Page 6 cf 9, Bev. 7 ADPF.MDIX EP 103-1 -

ME.PT C5aDOFF LIST

{

$6:km: Wis (is) (is not) a drill. mis (is) (is not) a .

drill. . Wis is Peach Pottom Atomic Power' Station calling to report an Alert has been declared on finit No. . Time and date of Alert classification is . We basic problem is

%e plant status is (stable) (inproving) (degradim) (Et known) .

%ere (is presently) (has not been) (is potential for) (has been) a radioactive (airborne) (liquid) release from the plant (at a leyel -

below that considered a public hazard) (at a level at which protective action is advisable). Reconrcended protective actions are (none)

. We affected pooulation area is (none) . My name is

. %is (is) (is not) a drill. %is (is) (is not) a drill.

N3TIFICATION9: -

3 PrRSCN TINE OF CnWIICNIOR'S PARTY TimPONDIW; NOI'IFICNPICN IMITTMS Station Superintendent

. toad ninnatcher v .

(Tell him to initiate s call list "C")

C Pennsylvania "mergency

. Management Agecv*

(Blue Phone or .

Maryland Civil Defense Mency (Blue Phone or .

' York County Emergency -

Mana' g ement Mency

. (Blue Phone or Lancaster rounty Emergency Management -

1 MmW -

4 (Rlue Phone ot i

I Chester County.. .

Emergency Managetrent -

Agency (Blue Phone or .

I Harford County Civil I

Defense Agency m ~,

j

{ (Blue Phone or' .

]-

I

. . -T '

\" ' EP-103

, Paga 7 cf 9, Rev. 7 t

ADPFNnIX FP.103-1 (cont'd)

{, w omCKow LIs?

\

Cecil County Civil Defense Acency l (Blue Phone or .

NPC Operations Center

.(Red Phone)

PA BRP (White Phone or PRADS Guard Sergeant .

Time notifications of carties above completed .

I Date Verified 9y__ Faergency Di. rector *

  • Must notify PN hv use of coninercial telephone no. on backshifts. (Blue Phone not manned by-P5;a on backshif ts) .

File under Sys-3-1 I

e i

I .

en I .

D p e

I O sc I

I I _.

EP-103

. . , Paga 8 cf 9, Rev. 7 ADPFNDIX ED 103-2 ,

{ PERSONNFL CN 4 RRODRD Diseosition of Call Name of Time No Estimated Call Person Called Called Answer Busy Time of Arrival Conpleted By I

L 9

l l

1 i

4 4

! b i.

l .

~ .I l '

l I

f I

l l

File Sys-3-1 i

O I

/

.y... . - - _ _ . . _ . . _ ,.

y; -~: a- _ _ - -- _ _

.:-;- _-_ _._: 2__ L _--- E L --~C ~-

~

EP-103 -

. - s. Page 9 of 9, Rev. 7 ADPENDIX EP 103-3 . -

C- .Fneroency Exposure Limits x.

Projected 14 hole Plody Thyroid Authorized Function Dose nose Mv

1. Life Faving and Reduction of Injury 75 rem
  • 375 rem 1Dnergency**

Director

2. Operation of Fmipnent to Mitigate an Emergency 25 rem * -125 rem Emergency **

. Director

3. Protection of Fealth and Safety of the Public 5 rem 25 rem Emergency Director
4. Otlwr mergency 10 C'PR 20 10 CPR 20 Emergency Activities limits limits Director

'! 5. Re-entry / Recovery -Administ Adminis-l Activities tive Guide- trative

(- lines Guide-lines N/A

Reference:

Fi%-520/1-75-001 Table 2.1 l **Such exposure shall be on a voluntary basis t

I .

1 . .

l -

l l

ll 1

l l

l C

=

. . 7 - - _ ;_ .

. . f. ~ _3.-.-

.; -.7-~~. - - . - .

. . . . . - ~

~ , _

En-104

\ ' Page 1 of 9, nev. 7

~ * -

GG21hd CONTROLLED APPROV2D C M - ,

VOID FRsVI0sS IdSuE DIS tRIBlJTION:-

M i2 W C Fil I N SS - SSV N W3I TS 2 3 ControlR$U M h W PIOCEDURR

\N Station Supe'r.

PP *104 S N EA,.x m , -%

PURPOSE

'Ib define the site response to a Site anergency.

RFEERPNCFS

1. Peach Bottom Atomic Power Station Emergency Plan
2. NUREG 0654
3. EP-101 Classification of Emergencies APPDMICITi EP 104-1 Site Emergency Notification Checkoff List EP-104-2 Personnel Call Record s EP 104-3 Emergency Exposure Limits (Onergency Plan Table 6.1)

PRRCNTPIONS

1. Planned radiation exposures should be limited to the administration guide levels in Appendix EP 104-3, Emergency Exposure Limits.

IMEDIA1E ACTIONS ,

.10 Shift Supervision shall: '

l.1 Assume the role of Interim Emergency Director.

1.2 If not already done at an earlier emergency action level, activate Emergency Teams as necessary.

1.3 contact the Station Superintendent and the Shift Technical Advisor, inform them of the situation.

1.4 Fill but Appendix EP 104-1 Standard Prompt Notification Message and give it to the Connunicator (PO or higher classification) and Direct the Cbnnunicator to comnence notification of the appropriate parties as specifie1 in Section 2.1 of this procedure. ihe communicator shall man the NRC RED Tele-phone on a continuous basis, if required by A-31. If

{'t Conmmicator is required for urgent plant operations related to the emergency, the concurrence for securing

-.e..- ee . , .

  • e.- .m. -e*. ==y= = *-e - * - -* *** -*-^ W =o=- vamp -

yp_zy .

Paqa 2 of 9, Rev. 7 the phone should be obtained from NRC prior to securing this telephone.

~

C. 1.5 If not alremly accenplished at the ALERT stage, direct' the shift clerk to activate the 60 minute call list using EP 209 APP P. If shift clerk is not available, this function may be assigned to any available individual.

1.6 Direct one of the on-shift I&C technicians to activate the Technical Support Center and anergency Operations Pacility in accordance with EP 201 and 203 if not already activated.

If not already performed previously, inform the shift clerk which I&C Technician will activate the centers at Unit 1 in order to let the clerk know which remaining IEC Technician to call for the l pronpt mobilization procedure.

1.7 Direct the Radiation Protection Team Leader to initiate

. on- and off site radiation surveys, as necessary, if not

. already done in accordance with EP 2059, Radiation Survey Groups.

1.8 Assign an Operations Support Center coordinator (Senior PO or APO available) if not already done and direct available shift personnel to report to this operations Support Center and to activate it in accordance with EP 202 if habitable. If this i

Operations Support Center is not habitable, direct shift personnel to report to the control Room. s

. 1.9 Closely monitor conditions to determine present hazards to personnel and potential accident conditions that may develop.

1.10 If release has occurred, dispatch a plant survey team mentier to obtain a site boundary dose rate as soon as

- practicable. -

1.11 If necessary, initiate inglementation of EP-317 and EP-316,

- Direct Reconmendations to County Bnergency Management Agencies, and Cumulative Population Dose Calculations.

2.0 Comm2nicator shall:

2.1 - Perform notifications on Appendix 104-1 using the Standard Pronpt Notification Message included.

See EP-209 Appendix A for additional telephone numbers, if required.

2.2 Report to the anergency Director when the notifications '

are coupleted.

2.3 Man the Rm NRC telep'me if required by A-31 until situation stabilizes and RE telephone ccmunications may be secured.

e 3.0 Operations support Center coordinator or his designee shall q -.m .. . , _ . . . , .

- - . . - , - -- . , , , . , . - .- m

v - - , - . -

yw104 .

r Pag 2 3 of 9, Rev.47

~

3.1 Activate the Operations Support Center on 135' elev turb

- b1dg, if it is habitable, in accordance with EP 202. "

If this Operations Support Center is NDP habitable report

{ to the Control Rocan. .

4.0 Radiation Protection Team Leader shall: . .

4.1 Initiate on- and off site radiation surveys in accordance with EP 205B, Radiation Survey Groups, when directed by the Emergency Director. If this person is the HP Fagineer he should report to the EDP to coordinate this function.

5.0 shift Isc Technician shall:

5.1 Activate the TSC and E0P (if not already activated during ALERT stage) in accordance with EP 201 using Appendix En-201-2 and procedure PP-203. ,

~

6.0 Shift Clerk shall:

6.1 If not already inplemented during ALERT stage, contact individuals on EP 209 APP P to call in those individuals to man TSC and EOP (60 minute call list). Document contacts on EP 209 APP P.

~

6.2 Inform Interim Phergency Director or Emergency Director '

when contacts are completed.

N "" .

1.0 anergency Director shall:

1.1 Periodically evaluate the event classification in

. accordance with EP 101, Classification of Emergencies and e= alate or deescalate the classification, as necessary. . -

l 1.2 Obtain results of the Caulative Population Dose l Calmlations and offsite radiation surveys fra

- the Radiation Prdtection Team Leader. Obtain Onsite and Plant Radiation Surveys from the Personnel Safety Team Leader, as necessary.

1.3 Provide approndate information from the previous evaluations to Ctemnunicator in the EOF for notifi-cation of the Rureau of Radiation Protection.

. 1.4 Perform actions as necessary to mitigate conditions of the emergency situation.

l 1.5 Determine which additional support personnel. are necessary for emergency functions and direct the

""' "'" " '"*' **""*d " " " " ' ** '

C' to contact those personnel.

=,---ee-

.,,9=a'*ga=*= --u====="**==**--*-a- -** ** *w e-+-* -*w ee eper ee - =*eao me-r a = e=-e . - - * -

we--+- . . - . . .

m, , a ,-_ ---- -- - + n - -- , -- - _ - -_- - _ - - - -

. . ~

EP.-104 Pags,4 cf 9, Rev. 7 1.6 Provide site personnel with P.A. speaker announcements for ,

any major changes in plant emergency status, such as changing C emergency. action levels and evacuations.

1.7 Direct the Evacuation of affected areas-as necessary.

Refer to the following procedure: - N-

\

GP 15 reval Evacuation EP 303 Partial Plant Evacuation EP 306 Evacuation of the Information Center 4 2.0 Station Superintendent shall -

2.1 Report to the mechnical Support Center or Control Pcan, for a briefing of the situation.

2.2 Assume the role of Emergency Director (if not already done) by formally relieving the interim anergency Director

. of this responsibility. Announce that he has assumed,the role of Bnergency Director to the assembled Technical Support

, Center personnel.

2.3 verify the emergency classification.

2.4 Verify that the Technical Support Center, Emergency Operations Facility and the Operations Support Center' i have been activated. -

s

. 3.0 Operations Support Center Coordinator shall 3.1 Notify the Interim Emergency Director or Mnergency i Director when the Operations Support Canter is activated.

3.2 Support the Con, trol Moom and Shift Supervision as necessary.

~ 4.0 Radiation' Protection Team Leader shall:- ,

l 4.1 Notify the Emergency Director when the Mnergency -

Operations Facility is manned.

4.2 Report progress and results of Cumulative Population Dose Calculations and off site radiation surveys to the site Mnergency coordinator ard Mnergency Director as necessary.

4.3 Notify the Site Emetgency Coordir ator of the need for - -

assistance from Radiation Management dorporation.

t 5.0 Shift Clerk or other assigned person shall

. 5.1 If not already done, notify additional support personnel

'. to report to the plant as directed by the Mnergency (U Director. Fefer to EP 209. Document on APP EP 104-2

-e e*+*e4=+-- ew e -- se gn, g my g4 g g -+yg u yo ena g--me  ; p em. - -

- - 4 3 em d _

_-w- - -- - ~ -- - -- ~ 4,.

~ ' *

. . En_104

. Taiga 9 of 9, Rev. 7 5.2 Notify Bnergency Director' or Site Faergency Coordinator when the additional support personnel have been notified.

C 6.0 Isc Technicians shall: '(if not already performed as per EP-103) 6.1 Inform the Emergency Director when the centers are activated, if not previously done. -

6.2 Man the 73C or E0? data display (E:TV) positions as directed by the Snergency Director.

7.0 Personnel Safety Team Leader shall Report progress and results of onsite and inplant radiation surveys to the Site Emergency Coordinator and Emergency Director as necessary. .

9 e

b m...

9

  • en e

O .

d .- nk . . ~. -- -- ._ - - - . ~ . - . - - - - . - - - - - - --~~.-.~~,-am--.. .~

~

EP-1U4 ~

, Paqa 6 of 9, Rev. 7 3

AP'PENDIX 10'4-1

~

ST'IE DERG5NCY N:yrIFICATION CHECKOW LIST Message: his (is)- (is not) a drill.. Wis (is) (is not) a drill. Wis is Peach Bottom Atcrnic Power Station calling to report a site emergency has been declared on Unit

. Time and date of site emergency classification is .

We basic problem is '

2e plant status is (stable) (improving) (degrading) (not known) .

Were (has not been) (is potential for) (has been) (is presently) a rMioactive (airborne) (liquid) release from the plant (at a level below that considered a public hazard) (at a level at which protective action is advisable). Recomt. ended protective actions are (none) .

%e affected population area is (none) . .

My name is . Wis (is) (is not) a drill. '

% is (is) (is not) a drill.

Notificaticns:

1 Person Time of Conmunicator's Party Responding Notification Initials Station SuperinteMent Ioad nisaatcher (Tell him to initiate call list "C")

. Pennsylvania Emergency

  • Management Agencv*

(Blue phone or .

Maryland Civil Defense Agency *

.(Blue phone or ,

. ' York County Emergency -

Management Agency

- (Blue phone or ' ,-

~

Lancaster-County Emergency Manage-

- ment Agency

. (Blue phone or.

Chester County Emer-gency Management- -

Agency -

(Blue phone or ,, -

. _s-Harford County Civil Defense Agency -

{. (Blue phone or

- ...e .e 4. -..=-e- . . . . . . . . . . - . .

. . ry-1 t) A

  • - - Paqo 7 of 9, R3v. 7 /

ADPENDN 104-1 (Cont'd)

SI'IE D1 ERGO 1CY NC7PIFICATION O&rKOFF LIST .

C -

Cecil County Civil Defense Agency --

\ '

\

(Blue phone or' Pennsylvania State Pol 4~ . York -

p. . . -

PA. BRP -

(White Phone or .

NRC Operations Center **

(Red Phone)

PBAPS Guard Sergeant Tine notification.of parties above completed.

Verified by Date Emergency Director ~

(s File Sys-3-1 ~

  • Must retify PR% by use of carmercial telechone no. on backshifts.

(Blue phone not manned by PDtA on backshifts) .

    • If NFC previously notified during ATERT condition, the assigned PO communicator continuously manning red phone in control room s' hould handle this notification autanatically However, check with Control Room to be sure. 'Ihis notifi-cation is made.

e 6

/

% ,

  • We O

O

. . . . - -, . . . - . -.....*w ,. , . . .. ,

, , - , - - 4- -

w~-

FP-104 e.

Paga R of 9, Rev. 7 APPhNDIXEP104-2

~

N C .

'- Disposition of Call Estimated Name of Time No

  • Time of- Call Person Called Called Answer Busy Arrival Completed Bv-

~

,/ .

's C.s 9

File Sys-3-1 s

. ._  ; _ .. . . . . . . _ - -. - . - - .e---- - - - - - - ----- .

. . . . . , . _ . _ . . . _ . . _ . , . _ . . . . - _ - - - - . ~ - - .- - - -

. - _ _ . . . . _ . _ . _ _ - - - __ ----~-~"~.

. . - , . . ~

, , e FD-104 Paga 9 of 9, Rev. 7 APPh!NDIX EP 104-3 ,

EMPWMt3M!55U!5ETIMIWi

b. , .

' - Projected whole Body '1hyroid Authorized Function Dese

  • Dose g
l. Life Saving and Reduction of Injury 75 rem
  • 375 rem Emergency **

Director

2. Operation of RIuipment to

. Mitigate an Emergency 25 rem

  • 125 rem - e ntgency**

l Director

3. Protection of Health and Safety t of the Public 5 rem 25 rem energency l Director i

I 4.Other Emergency 10 CFR 20 10 CPR 20 FJnergency l Activities limits limits Director

(

5.Re-Entry /Re- Admin,istrative Administrative .

C' covery Guide Lines. Guide Lines N/A Activities .

  • References EPA-520/1-75-001 Table 2.1
    • Such exposure shall be on a voluntary basis 9

.. e ee

=-

I e

O d

e

s. -_ . .. . . _ , - - - - - - - . ,.....e-~-- - - - - - - - - - - - - - - - + - - - - - - - . - - - - . .

- . y - y., ..,-.2--- - - - -.; ~~. .. , .. _ ...... . ~.-.,-.-.------... -...- _, ..

EP-105

.-- " . Pag 3 1 Cf 9, Rev. 7 GG:ljm

/$$8

(

Q u u

PFXM BOFITM UNITS 2 AND 3 eWw "

'N

!!MERGENCY PIAN IMPIENEVflNG PBOCEDURE EP-105 (ENERAL DTPGENCY RESPONSE PURPOSE

'Ib define the site response to a General Emergency.

RWERFNCFS ,

1. Peach Bottom.Atcmic Power Station Emergency Plan
2. NUREG 0654
3. EP-101 Classification of Emergencies APPFNDICFS .

I EP 105-1 General Emergency Checkoff List EP 105-2 Personnel Call Record EP 105-3 Fmergency Exposure Limits (Emergency Plan Table 6.1)

PRECNJTIONS l -

l 1. Planned radiation exposures should be limited to the admihistrative guide levels in Appendix EP 105-4 Emergency Exposure Limits. .

l IMPDIA'IF. ACTIOE 1 -

l.0 Shift Supervision shall:

1.1 Asstane the role of Interim Emergency Director.

1.2 Activate Emergency Teams as necessary if not already i accomplished at an earlier emergency action level.

1

' ~

1.3 Contact ~the Station Superintendent and the Shift Technical Mvisor, inform them of the situation.

1 1.4 Fill out Appendix EP 105-1 Standard Prcanpt Notification Form and give it to the Comnunicator (PO or higher classification) 1.5 Direct Comnunicator to connence notification of the appropriato parties as specified in Section' 2.1 of this procedure. 'nm ccmnunicator shall man the NDC RFD Telephono on a

- r .- - m , - _

  • ' I .

~

EP-105

- . Pag 2 2 cf 9, Rev. 7

  • i continuous basis if required by A-31. If comunicator is required b,

for urgent plant operations related to the emergency, the concurrance for securing the phone should be obtained from

  • the NRC prior to securing this telephone.

1.6 If not already accorplished at the ALERT or SI'IE EMERGENCY

  1. ' ' stage, direct the shift clerk to activate the 60 minute call list using EP 209 APP P. If shift clerk is not available, this function may be assigned to any available individual.

l.7 Direct one of the on-shift Isc Technicians to activate the

'nechnical Support Center and the anergency Operations Facility 4

inaccordancewithf201and203if'notalreadyactivated. ,

1.8 Direct the Radiation Protection Team Leader to initiate on and offsite radi'ation surveys, as necessary, in accordance with EP 205B, Radiation Survey Groups, if not already done.

l

' l.9 Assign ~an Operations Support Center Ccordinator' (senior PO or APO available) if not already done and direct available shift personnel to report to the Operations Support Center and to activate it in accordance with EP 202, if habitable. If the Ooerations Support Center is NOT habitable, direct shift personnel to report to the Control Roan.

1.10 Closely monitor conditions to determine present hazards to i

personnel and potential accident conditions that may develop.

1.11 If release has occurred, dispatch a plant survey team ment >er to obtain a site boundary dwe rate as soon as practicable.

1.12.If necessary, initiate inplementation of EP-317 and

'EP-316, Direct Reconmendations to County Bnergency. Manage-ment Agencies, and Cumulative Population Dose Calculations.

2.0 Connunicator'shall

2.1 Perform notifications on Appendix EP 105-1 using the Standard Pronpt Notification Message included.

See EP 209, Appendix A, for telephone ntsnbers.

2.2 P.eport to the Emergency Director when the notifications are coupleted.

2.3 Man the RED NRC telephone if. cequ_ ired by A-31 until -

situation stabilizes and RED telephone ocununications may be secured.

3.0 Operations Support Center Coordinator or his designee shall:

3.1 Activat'e the Operations, Support Center, if it is habitable, in accordance with EP 202. If the Operations Support Center is NOP habitable report to the Control Room.

  • L- . ._,a,.__.__,__--- .._ _ __ , _ _ . . _ . _ _ _ . _ _ _ _ . _ _._.. _

EP-l'05

, Paga 3 of 9, Rev. 7 4.0 Radiation Protection Team Leader shall:

[ 4.1 Initiate on and off -site radiation. surveys in accordance g with EP 205B, Radiation Survey Groups when directed by the nnergency Director. If this person is also the HP Engineer he should report to the EOF to coordinate this function.

5.0 Shift IEC Technicians shall:

5.1 Activate the TSC and FIF (if not already activated during AIPRT or SIE EME:RGENCY stage) in accordance with En 201 and EP 203.

6.0 Shift Clerk shall:

6.1 If not already inplemented during ALERT or SIE DDW7NCY stage, contact individuals on EP 209 AFP P to call in those individuals to man the TSC and FIF (60 minute call , list).

Document contacts on EP 209 APP P.

6.2 Inform Interim Emergency Directo'r or Emergency Director when contacts are completed.

FOLICA-UP ACTIONS 1.0 Emergency Director shall: s I

1.1 Periodically evaluate the event classificatiori in accord-ance with EP 101, Classification of Emergencies. If the .

~

ocmditions change, deescalate to an appropriate classifi-

, cation. ,

1.2 Obtain results of the Cumulative Population Dose Calcu- -

lations-offs'ite radiation ' surveys from the Radiaticri Protection meam Leader. Obtain ensite and Plant Survey Radiation Surveys

. .from the Personnel Safety Team Leader. ,

1.3 Referring to EP-317, provide appropriate information from the previous evaluations and Protective Action recomendations to a Comunicator in the EOF for -

notification of the Bureau of Radiation Protection.

1.4 Perform actions as necessary to mitigate conditions of .the emergency situation. t 1.5 If not,already performed, determine which additional .

support personnel are necessary for emergency functions and direct the shift clerk or other assigned person to contact those personnel.

1.6 Provide site personnel with PA speaker announcements for any major changes in olant emergency status, such as changing

..( l emergency action levels.

l 1.7 Direct the evacuation of affected areas, as necessary.

g ..

3 +

wwen += .

Om-_

+ * -

  • =f * *-e r- +1 v e emap = noe-- e - e= e we-*- ear e e e-* re=e v === - e + - -ee e.e-- - * - p weeeu w *w m

F#-105

', Paga 4 cf 9, Rev. 7 Refer to the following procedures:

~

(

GP 15 Local Evacuation FP 303 Partial Plant Evacuation

'i EP 306 Evacuatim of the Information Center 2.0 Station Superintendent shall:

2.1 Report to the Technical Support Center or Control Room, for a briefing of the situation.

2.2 Assume the role of Emergency Director (if not already done) by formally relieving the Interim anergency Director. Announce that he has assumed the role of Emergency Director to the assembled Technical Support Center personnel.

2.3 verify the emergency classification.

'2.4 Verify that the mechnical Support Center, Emergency Operations Facility and the Operations Support Center have been activated.

3.0 Doerations Support Center coordinator shall: .

3.1 Motify the Interim Emergency Director when the Operations Support Center is activated.

3.2 Support the Control Room and Shift Supervision as necessary.

~

4.0 Radiation Protection Team Leader shall

!' 4.1 Notify the Emergency Director when the Faergency

  • Operations Pacility is activated.

4.2 Report progress and results of Cumulative Population l Dose Calculations and off site radiation surveys to the EMtgency Director, as necessary.

4.3 Notify the Site Emergency Coordinator of the need for assistance from Padiation Management Corporation.

5.0 Shift Clerk or other assigned person shall: ,

5.1 When requested, notify additional support personnel to report to the plant as directed by the Faergency Director. Refer to FP 209.

5.2 Notify Emergency Director or Site Emergency Coordinator when additional support personel have been notified.

( Document on AFP EP-105-2.

6.0 TM' 'nchnicians chall: (if not alre.vly performed ac por l

b, ,

-r_ _____: . . _ _ _ _rr~ LT_r~2_ ___r _ ~ _m _~ ~' ~ V_ ^ ~~ ' -

m ~_ _ _ " _ _ T '- '~~~~^~7"~'~~~"~

- Paga 5 cf 9, Rev. 7 EP-103 or Ep-104) , ,

( 'N 6.1 Inform the Emergency Director when centers'are activated.

6.2 Man the 'ISC and EN data display (CCW) positions as directed by the Dnergency Director.

/ ~~~~

7.0 Personnel Safety Team Leader shall: '

7.1 T'eport progress and results of on-site and plant surveys.

7.2 Radiation surveys to the Emeroency Director as necessary. . .

/

e e

9 m m.

t O

O l

i e e * .m i

I I

l.._.. ..J.._ .

,_. _ . . , _ . . . . . . . - . L ._ . , _ . . _ , . _ _ _ _ . _ . . . _ . . _ _ _ _ . , _ _.. , _ , , , , . _ . , __

' FP--105 I' '

. ' Pagn 6 o'f 9, RI.v. 7 j

APPFNDIX TP 105-1 .

{ GFNF.RAL 94.'lYENCY NOTIFICATION C5ECKO?P LISP Messaqe: his (is) (is not) a drill. ' Wis (is) (is not) a drill. %is is Peach Pottom Atcmic Power Station calling to report a General Bnergency has been declared on Unit No. . Time and date of General anergency classification is . Se basic problem is .

We plant status is (stable) (improving) (degrading) (not known).

Bere (is presently) (has not been) (is potential for) (has been) a radioactive (airborne) (liquid) release-from the plant (at a level below that considered a public hazard) (at a level at which protective action is advisable) . Remended protective actions are . (none)

. We affected population area is (none) .

. My name is . his (is) (is .ot) a -

drill. %is (is) (is not) a drill.

Notifications:

Person Time of Comunicator's i Party .

Responding. Notification. Initials Station Superintendent

~

Imad Dispatcher I (Tell him to initiate s -

I call list "C")

Pennsylvania Dnergency Management Agencv*

(Blue phone ot ,- ,

Maryland Civil Defense ,

Agency (Blue phone or .

' ~

' York County anergency Management' Agency (Blue phone or. ,,.,- -

Lancaster County ,

Brergency Management Agency ~

(Blue phone or _

Chester County ,

Energency Management

~ Agency (Blue phone or .

! Harford County Civil Defense Agency. ---

s. ,

(Blue phone ot-(- _

i

\

\

s . - *

- EP-10f Page -7,of 9, Kw. 7 APPFNDIX F"P 105-1 (Cont'd)

GmE9AL EVE.RG9CY tK7PIFICATION CHFXNOW LIST

('

Cecil County Civil' Defense Agency ^.

(Glue phone or.

l -' .

Pennsylvania State

! Polica vak PA BRP (White Phone or .

NRC Operations Center **

(Red Phone)

PBADS Guard '

Sergeant . -

Time notification of parties above car.pleted .

Verified By Date Emergency Director --

s i File - Sys-3-1

  • Must notify PD% by use of cormercial telephone no. on backshifts.

(Blue phone not manned by PDM on backshifts.

    • If NIC previously notified during Alert or Site Brergency condition, ths assigned PO carrunicator continuously manning the red phone in Control Room should handle this notification aut .atically. ,However, check with . control Roan to be sure this notification is made. .

~

WA.

o

=

, c

<EP-le,g5 Paga 8 of 9, Rev. 7 l '

ADP1MnIX EP 105-2 ~ '

PERSO@lFL CALL R5URD

(' N.,

. \

Disposition of Call Name of Time No Estimated Call Person Called Called Answer nusy Time of Arrival-Womoleted 51v s m..

l .

ep l

File Sys-3-1

/

. d t

l l

_.- --._ ,- _ .- _a . .. ,. .= :. a _. _. g. g:__ _ .g3 _ ,. .

EP-105,

~

Pag 2 9 cf 9, Rev. 7 ADPENDIX EP 105-3 .

FMERGENCY EXPOSIFE LIMI'IS Projected Whole Body 'Ihyroid Authorized Function Dose Dose g

1. Life Saving and Faergency**

Reduction of Injury 75 rem

  • 375 rem Director 2.. Operation of F42ignent to Mitigate an Emergency **

Bnergency 25 rem

  • 125 rem Director
3. Protection of Health and Safety of the Emergency Public 5 rem 25 rem Director
4. Other Emergency 10 CFR 20 10 CPR 20 Emergency Activities limits limits Director
5. Re-Entry / Recovery Administrative Administrative .

Activities Guidelines _. Guidelines N/A

Reference:

EPA-520/1-75-001 Table 2.1

( **Such exposure shall be on a voluntary basis E