1 t
-VERMONT YANKEE
' NUCLEAR POWER CORPORATION k~
Ferry Road, Brattleboro, VT 05301-7002
+
ENGINE I OFFICE 580 MAIN ST RE ET 00LTON MA 01740 1508) 779-6711 August 22,1994 BVY# 94-84 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, D.C. 20555
References:
(a)
License No. DPR-28 (Docket No. 50-271)
(b)
NRC Bulletin 93-02 Supplement 1, " Debris Plugging of Emergency Core Cooling Suction Strainers", dated 2/18/94 (c)
Letter, VYNPC to USNRC, "60 Day Response to NRC Bulletin 93-02 Supplement 1", BVY 94-44, dated 4/19/94
Subject:
Confirmation of Requested Actions,Bulletin 93-02 Supplement 1 This letter is written in response to the reporting requirements described in NRC Bulletin 93-02, Onpplement 1. The Bulletin described concerns related to the potential loss of Emergency Core Cooling Systems due to suction strainer clogging and requested licensees to implement certain interim actions pending final resolution of this issue. Reference (c) described Vermont Yankee's planned actions and a schedule for their completion.
The Bulletin also requested a confirmatory response when the requested interim actions were completed. This letter confirms the completion of Vermont Yankee's
. planned actions identified in Reference (c).
These actions included classroom training, simulator training, operating procedure revisions and development of a new event based off-normal operating procedure ent!tled "ECCS ' Suction Strainer Plugging."
1 Although not mentioned in the text, the schedule attached to Reference (c) listed a revision to the Emergency Operating Procedure (EOP) Study Guide as one of our planned actions. The Study Guide was listed in the event that a substantive
. revision to the EOPs would be required.~ A subsequent review determined there was 9408290108 940822
-PDR ADOCK 05000271 0-PDR hg 0
VERMONT YANKEE NUCLEAR POWER CORPORATION U.S. Nuclear Regulatory Commission August 22,1994 Page 2 no need to revise the EOPs at this time and thus, no change to the Study Guide was necessary. The new off-normal operating procedure adequately addresses the subject issue.
We trust that the information provided is adequate to address your concerns in this area, however, should you have any questions or require additional information, please do not hesitate to contact us.
Sincerely, Vermont Yankee Nuclear Po e orporation i
4 J. Gary Weigand President & Chief Executive Officer cc:
USNRC Region I Administrator USNRC Resident Inspector - VYNPS USNRC Project Manager - VYNPS STATE OF VERMONT
)
)
SS WINDHAM COUNTY
)
Then personally appeared before me, J. Gary Weigand, who being duly sworn, did state that he is President and Chief Executive Officer of Vermont Yankee Nuclear Power Corporation, that he is authorized to execute and file the foregoing document in the name and on the behalf of Vermont Yankee Nuclear Power Corporation and that the statements therein are true to the best of his knowledge and belief.
?MNA (l Stw
,{pdith A. Harris, Notary Public
~
My Comri'ission Expires 2/10/95