Consum m power Executive Manager O
Y Milland Project Office General Offices: 1946 West Pernall Road, Jackson, MI 49201 e (517) 788-0774 60 M9
~ PRINCIPAL STAFF
~
f/RA s
3 June 24, 1983
{/M
- AO 7$?i SLO n$
ggj ac
@Sbt Mr J J Harrison Ni Midland Project Section bi 8
U S Nuclear Regulatory Commission fA li FLLE fro s Region III 799 Roosevelt Road Glen Ellyn, IL 60137 MIDLAND ENERGY CENTER GWO 7020 REMEDIAL SOILS WORK AUTHORIZATION File:
0485.16 UFI:
42*05*22*04 Serial:
CSC-6765 12*32 This letter documents 6/22/83 telecon between R. Wieland of CPCo and Dr. R. Landsman of NRC Region III.
It is CPCo's intention to perform the following BWST preliminary work under the previously approved work activities 312150007 and 322150007:
1.
Install expansion anchors for formwork.
2.
Install concrete mudmat for new BWST foundation.
3.
Cut holes in valve pit for concrete access.
4.
Grout in rebar dowels at bar ends.
Dr. Landsman concurred that this activity could be performed provided that no formwork, rebar or concrete is placed except as noted above.
The formwork, rebar, and concrete will be placed only after approval of activities 312150011 and 322150011, which are currently under NRC review.
00 9 JAM /RHW/klm
~