Informs That Addl Work Needed in Listed Areas of Draft Emergency Plan.Traffic & Access Control Point Section of Plan Must Be Completed So Entire Draft Can Be Analyzed. Related Correspondence
ML20072G466
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 06/22/1983
From: Riel G
NEWBURY, MA
To: Lomasney M
COSTELLO, LOMASNEY & DENAPOLI, INC.
References
ISSUANCES-OL, NUDOCS 8306280512
Download: ML20072G466 (2)


Text

RELATED CORRESPONDhW TOWN OF NEWBURY Docket Nos.

{

j POUCE DEPARTMENT 50-4431/444 OL 25 HIGH ROAD NEWBURY. MA55. 01950 n,

GK)RGE RIEL cws a P.ne.

June 22, 1983 Mr. Martin Lomasney Costello, Lomasney & deNapoli, Inc.

115 Middle Street Manchester, New Hampshire Re:

Draft Emergency Planning Document for'Newbury, Massachusetts

Dear Mr. Lomasney:

I have reviewed the draft emergency plan that you have prepared for the Town of Newbury and feel that a considerable amount of work needs to be done on the document. It is extremely important that the Traffic and Access Control Point section of the plan be completed in order that that the entire draft can be throughly analized.

~

Several other afeas of the draft plan need additional work, and they include but are not limited to the following:

1.

Notification 2.

Emergency Communications 3.

Public Education and Information 4.

Emergency Facilities and Equipment 5.

Accident Assessment 6.

Protective Response 7.

Radiological Exposure Control 8.

Public Health 9.

Recovery and Reentry 10.

Exercises and Drills 11.

Training l

The Town of Newbury is certainly willing to work with your firm I

in preparing a plan that will provide the best possible protection for the residents of the community, and I welcome the opprotunity to discuss with your firm the areas of the plan I feel need improvement.

8306280512 830622 ~

l PDR ADOCK 05000443 I

O PM b

A3 tha Town of Newbury is mandated to have any Emergency Response Plans approved at a Town' Meeting, it is important that work on the Re-Draft begin as soon as possible.

Very truly yours, orge L. Riel Civil Defense Director Town of Newbury cc:

Jack Dolan, Mass Civil Defense Jo Ann Shotwell, Esq.,

Assistant Attorney General Edward A. Thomas Federal Emergency Management Agency Board and Parties to NRC Proceeding

~