Requests 60-day Extension for Responding to 830511 Request for Addl Info Re NUREG-0737,Item II.K.3.28, Qualification of Automatic Depressurization Sys Accumulators. Extension Due to Personnel Changes & Addl Time Needed by Ae
ML20072G332
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/21/1983
From: Pilant J
NEBRASKA PUBLIC POWER DISTRICT
To: Vassallo D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.K.3.28, TASK-TM LQA8300163, NUDOCS 8306280444
Download: ML20072G332 (2)


Text

-

1 p.,

j,y GENERAL OFFICE Nebraska Public Power District

    • "?ete##0Je$$'*"^M^***"""

LQA8300163 June 21,1983 Director of Nuclear Reactor Regulation Attention:

Mr. Domenic B. Vassallo, Chief Operating Reactors Branch No. 2 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Reference:

1.

Letter from D.

B. Vassallo to J. M. Pilant dated May 11,1983, " REQUEST FOR ADDITIONAL INFORMATION - NUREG 0737, ITEM II. K. 3. 28, QUALIFICATION OF ADS ACCUMULATORS"

Dear Mr. Vassallo:

Subject:

ADS Accumulator Qualification -

Extension of Time Reference 1 requested that the District respond to a request for additional information on ADS Accumulators (II.K.3.28) by June 27,1983.

In preparing the response on this issue, the following has been determined:

Due to the length of time II.K.3.28 has been active, l

a.

there has been a change in District personnel working on this issue.

As a result, a complete re-review of all associated documentation is necessary.

b.

In order to adequately respond to Reference 1, the i

l services of our Architect-Engineer is required and this effort cannot be completed by June 27 l

In a telecon June 20, 1983, the staff indicated that on the bases above, an extension of time may be justified; therefore, the j

District requests a 60-day extension of time in responding to l

l 0$o &

h PDR hO

} O

/.

/

l'... - e Mr. Domenic.B. Vassallo Pega 2 June 21,1983.

Reference 1 We do not feel that an extension of time would pose an undue risk to the health and safety of the public, but that it would facilitate a complete and thorough response on this item.

Should you have any questions relative to this request, please contact my office.

Sincerely, LM Jay

1. Pilant Division Manager of Licensing &

Quality Assurance JMP/gme:kc20/5 1