Harry Tauber Group Vice President Detroit Ecison RDE=>e June 22, 1983 EF2 - 63,942 Divector of Nuclear Reactor Regulation Attention: Mr. B. J. Youngblood, Chief Licensing Branch No. 1 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C.
20555
Dear Mr. Youngblood:
Feference: Enrico Fermi Atomic Power Plant, Unit 2 NRC Docket No. 50-341
Subject:
Revision of Scheduled Fuel Lead Date This is to confirm that Edison has revised its best estimate for the completion date of Fermi 2.
The new fuel load date is December 30, 1983.
Detroit Edison continues to make every effort to complete construction and resolve remaining licensing issues in a timely manner. We therefore, request your continued cooperation in obtaining NRC staff review, as necessary, to resolve outstanding items.
Sincerely, cc: Mr. B. Little Mr. M. D. Lynch
\\
8306280438 830622 PDR ADOCK 05000341 A