r bm8 Docket No. 50-346 TOLEDO EDISON License No. NPT-3 Serial No. 1-359 RCHAAo P. CROUSE
?El0*
May 20, 1983 ma esasm Mr. C. E. Norelius, Director Division of Project & Resident Programs United States Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137
Dear Mr. Norelius:
Toledo Edison acknowledges receipt of your March 24, 1983 letter (Log No.
1-759, Inspection Report No. 50-346/83-06), summarizing the Enforcement Conference on March 9, 1983, at the Davis-Besse site. Toledo Edison agreed to submit a written response describing corrective actions in the areas of maintenance and drawing control.
Toledo Edison's letter of April 29, 1983 (Serial 1-352) formally submits to you the programs outlined at the March 9, 1983 Enforcement Conference.
Very truly yours,
//
= = -
RPC:SGW:nlf cc: DB-1 NRC Resident Inspector 8306270379 830520 PDR ADOCK 05000346 G
PDR M8[
THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652
/0 JUN 6 1983