Informs That Response to NRC 821126 Request for Info Re App R Guidance Concerning Associated Circuits Related to Fire Protection Safe Shutdown Will Be Forwarded in Early Sept 1983
ML20072F364
Person / Time
Site: Midland
Issue date: 03/16/1983
From: Jackie Cook
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Harold Denton
Office of Nuclear Reactor Regulation
References
21604, NUDOCS 8303240027
Download: ML20072F364 (1)


Text

.

1

@ Consumem Power

= wc.

Company v,- ~,u,.,- ~ ju,s e.e.,s y and Construction General offices: 1945 West Parnell Road, Jackson, MI 49201 e (517) 788 0463 March 16, 1983 Harold R Denton, Director Office of Nuclear Reactor Regulation Division of Licensing US Nuclear Regulatory Commission Washington, DC 20555 i

MIDLAND NUCLEAR C0 GENERATION PLANT MIDLAND DOCKET NOS 50-329, 50-330 NRC GUIDANCE AND REQUEST FOR INFORMATION ON ASSOCIATED CIRCUITS RELATED TO FIRE PROTECTION SAFE SHUTDOWN (APPENDIX R)

FILE: 0485.1, B9.5.1 SERIAL: 21604

REFERENCES:

(1) H R DENTON (NRC) LETTER TO J W COOK, DATED NOVEMBER.26, 1982 WITH ENCLOSURE (2) J W COOK LETTER TO H R DENTON (NRC) SERIAL 20387, DATED DECEMBER 17, 1982 On November 26, 1982, the NRC transmitted its guidance on associated circuits along with a request for information in the enclosure to the NRC correspon-dence of Reference 1 above. This guidance is related to Section III.G of j

10 CFR 50, Appendix R.

Because the engineering studies required to support a response to the NRC questions will require many months to complete, an engineering schedule of activities had to be developed before we could advise the Staff when our response to their questions could be forwarded. We advised the NRC of this in our correspondence of December 17, 1982 (Reference 2)

We have completed our engineering scheduling for associated circuits and wish to advise the Staff that our response to the NRC's correspondence of Reference I will be forwarded in early September, 1983, after our engineering studies are completed in late August, 1983.

kit'Ldj JWC/RLT/dle CC RJCook, Midland Resident Inspector i

RHernan, US NRC oc0383-0373a100 8303240027 830316 PDR ADOCK 05000329 F