Text
F LoulSIANA 342 OaAnONOe sincer POWER & LIGHT P O. BOX 6008
- NEW OnLEANS. LOUISIANA 70174. (504) 366-2345 Eu?t sE$
June 15, 1983 W3183-212 Q-3-A35.07.53 Mr. John T. Collins, Regional Adatinistrator, Region IV 3]g y
U. S. Nuclear Regulatory Commission a.= _
611 Ryan Plaza Drive, Suite 1000 l>
Arlington, Texas 76012 JUN 2 01983 i
SUBJECT:
Waterford SES Unit No. 3
.S Docket No. 50-382 Significant Construction Deficiency Report No M )
"Possible Failure of General Electric Type HFA Relays" Fourth Interim Report
REFERENCE:
LP&L Letter W3I83-0142 dated April 29, 1983
Dear Mr. Collins:
The above referenced letter indicated submittal of a Final Report to the USNRC no later than June 15, 1983.
At the present time, corrective action is !ncomplete due to a delay in receipt of replacement coils needed for those coils already received that were not qualified. Corrective action completica is scheduled for the end of June, 1983 based on timely delivery of qualified replacement parts.
In view of the above, a Final Report will be submitted by July 26, 1983.
Very truly yours, mm F. J. Drummond Project Support Manager - Nuclear FJD/ MAL /st cc:
- 1) Director 3)
Mr. E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.