Requests Approval to Retain Torrey Pines Technology to Perform Independent Mgt Review of Project Mgt Per 821112 Show Cause Order.Contractor 830304 Proposal Not Encl
ML20072E843
Person / Time
Site: Zimmer
Issue date: 03/07/1983
From: Dickhoner W
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20072E802 List:
References
NUDOCS 8303230084
Download: ML20072E843 (2)


Text

?

ENCLOSllRE 3

.)

G;{~$h$$

I '

5 THE CINCINNATI GAS & ELECTRIC COMPANY CI CINCINNATI.OMIO 4530t

w..gge,.c.

ArMNClPM. STAFF f3,,

March 7, 1983 h

E A/RA PAO-O/

OPRP M

$toa ---

ECAv DR.wsp r

U.S. Nuclear Regulatory Commission DE' Region III ML l _

j 799 Roosevelt Road D1 J_t Lp pgj Glen Ellyn, Illinois 60137 Attention:

Mr. James G. Keppler Regional Administrator Gentlemen:

Re:

Wm. H. Zimmer Nuclear Power Station, Unit 1, Order to Show Cause and Order Immediately Suspending construction, Docket No. 50-358 s

On November 12, 1982 an Order to Show Cause was issued which suspended all safety-related activi':ies on the Zimmer project.

The order directed us to obtain an independent management review of the project and to submit a comprehensive plan to complete the project.

On March 2, 1983 we interviewed Messrs. John Stelbel and George Wessman of Torrey Pines Technology as to their capability to perform the independent review of the Zimmer project management in accordance with Section IV.B. (1) (a) of ^.he Order to Show cause.

i I:nclosed are two copies of their proposal dated March 4,1983: we are retaining two copies for our files.

t We believe Torrey Pines Technology has the necessary l

capability, independence, and technical and managerial competence t

to perform the independent review and request that you expedite your approval of this reviewer.

As stated in the special comments i

column of your Zimmer Plan of Action, this phase is only preliminary to the recommendations regarding future management of the project; therefore, lengthy procedures for public participation should not be necessary.

IdAR 10 W 8303230004 830311 4

PDR ADOCK 05000358 A

PDR

t 1

i f

^

U.S. Nuclear Regulatory commission Attn:

Mr. James G. Keppler Psge 2 March 7, 1983 Re:

Wm. H.

Zim er Nuclear Power Station our contact with Torrey Pines Technology was made prior to the receipt of your letter dated March 2 (which was received in my office on March 3) governing communications.between CG&E and independent organizations conducting reviews or audits under the Commission's Order.

All future contacts and communications, where applicable, will be governed by your March 2 letter.

Yours very truly, THE CINCINNATI GAS & ELECTRIC COMPANY T