Motion for Leave to File out-of-time Reply to Proposed Findings of Fact & Conclusions of Law on Waterhammer.Addl Time Needed Due to Demands Imposed by Preparation of Other Documents
ML20072E556
Person / Time
Site: Byron  Constellation icon.png
Issue date: 06/21/1983
From: Copeland V
COMMONWEALTH EDISON CO., ISHAM, LINCOLN & BEALE
To:
Atomic Safety and Licensing Board Panel
Shared Package
ML20072E550 List:
References
REF-GTECI-A-01, REF-GTECI-PI, TASK-A-01, TASK-A-1, TASK-OR ISSUANCES-OL, NUDOCS 8306270020
Download: ML20072E556 (2)


Text

  • .-- n

' }- c, Q p. q-)

y g

~

500 "n ,1 \9837 gh

  1. /

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION WNd*

W BEFORE THE ATOMIC SAFET" AND LICENSING ?T;qBOARD u y f[

In the Matter of )

)

COMMONWEALTH EDISON COMPANY ) Docket Nos. 50-454 OL

) 50-455 OL (Byron Nuclear Power Station, )

Units 1 & 2) )

MOTION FOR LEAVE TO FILE OUT OF TIME Commonwealth Edison Company (" Applicant") hereby moves the Licensing Board to grant Applicant leave to file out of time the accompanying " Applicant's Reply to DAARE/ SAFE's Proposed Findings of Fact and Conclusions of Law Regarding Waterhammer". In support of this motion, Applicant states:

1. The undersigned attorney is largely responsible for producing Applicant's proposed findings on the emergency planning issue and the aforementioned Applicant's reply on the waterhammer issue, both of which were due on June 20, 1983. Because of the demands imposed by the preparation of the former document, the undersigned attorney was unable to timely complete the latter.

. 2. No party will be prejudiced by acceptance of this late filing.

l

$gg6gjob 0 $

9

r

.e. ,

For good cause shown, Applicant's motion for leave to' file out of-time the aformentioned document should be granted.

Respectfully submitted, Yh h.

One of the attorne't f for Commonwealth Edison Company ISHAM, LINCOLN & BEALE Three First National Plaza Chicago, Illinois 60602 (312) 558-7500 9

9 I