Advises That No Bunker-Ramo Electrical Penetration Assemblies Utilizing Hard Epoxy Module Design Installed or Planned to Be Installed,Per IE Bulletin 82-04, Deficiencies in Primary Containment Electrical Penetration Assemblies
ML20072B923
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 02/28/1983
From: Crouse R
TOLEDO EDISON CO.
To: Deyoung R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
REF-SSINS-6820 1-328, IEB-82-04, IEB-82-4, NUDOCS 8303080047
Download: ML20072B923 (1)


Text

Docket No. 50-346 TOLEDO EDISON License No. NPF-3 Serial No. 1-328 RcHAno P. CnouSE v<. a.s nc fduClear February 28, 1983 m m23S322i Richard C. DeYoung, Director Office of Inspection & Enforcement United States Nuclear Regulatory Commission Washington, D. C.

20555 liear Mr. DeYoung:

On December 3, 1982 (Log No. 1-715), Toledo Edison received IE Bulletin 82-04: Deficiencies in Primary Containment Electrical Penetration Assemblies.

Toledo Edison has determined that no Bunker Rama electrical penetration assemblies utilizing the hard epoxy module design are installed at Davis-Besse Nuclear Power Station, Unit No. 1.

Also, Toledo Edison does not plan to install such assemblies in the future.

This completes the requested actions by Toledo Edison pertaining to IE Bulletin 82-04.

If we can be of further assistance in this matter, please feel free to contact us.

Very truly yours, 8 P Cs'/e RPC:RFP:nlf cc: DB-1 NRC Resident Inspector 8303080047 830228 PDR ADOCK 05000346 O

PDR THE TOLEDO EDISON COMPANY EOISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 h