ML20072B836

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Rept 50-327/94-300 & 50-328/94-300.Corrective Action:Labeling Requests for Inverter Precharge Pushbutton Were Initiated & Temporary Tags Were Placed on Each Precharge Pushbutton
ML20072B836
Person / Time
Site: Sequoyah  
Issue date: 08/05/1994
From: Powers K
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9408160267
Download: ML20072B836 (5)


Text

-

i 9

l l

d Tenresssie Valley Authonty, Post Office fkw 2000, Soddy Dasy, Tenrossee 37379 2000 Ken Powers Vre Prewtont. Segnyah Ndar Ptant August 5, 1994 U.S.

Nuclear Regulatory Commission ATTN Document Control Desk Washington, D.C.

20555 Gentlemen:

In the Matter of

)

Docket Nos. 50-327 Tennessee VLlley Authority

)

50-328 SEQUOYAH NUCLEAR PLANT (SQN) - INSPECTION REPORT NOS. 50-327, 328/94-300

- REPLY TO NOTICE OF VIOLATION (NOV) 50-327, 328/94-300-01 contains TVA's reply to Thomas A. Peebles' letter to Oliver D.

Kingsley, Jr. dated July 6, 1994, which transmitted the subject i

NOV.

The violation is associated with the failure to implement an established procedure concerning the labeling of plant equipment.

A list of commitments is included in Enclosure 2.

If you have any questions concerning this submittal, please telephone J.

W. Proffitt at (615) 843-6651.

l i

Sincerely, Ken Powers Enclosures cc:

See page 2

1200g, O

9408160267 940005 PDR ADOCK 05000327 y p G

PDR

(

l i

U.S.

Nuclear Regulatory Commission Page 2 l

August 5, 1994 1

cc (Enclosures):

Mr.

D.

E.

LaBarge, Project Manager U.S. Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 NRC Resident Inspector Sequoyah Nuclear Plant 2600 Igou Ferry Road Soddy-Daisy, Tennessee 37379-3624 Regional Administrator U.S.

Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323-2711 l

I b

ENCLOSURE 1

)

RESPONSE TO NRC INSPECTION REPORT NOS. 50-327, 328/94-300 THOMAS A.

PEEBLES' LETTER TO OLIVER D. KINGSLEY, JR.

DATED JULY 6, 1994 Violation 50-327, 328/94-300-01

" Technical Specification 6.8.1 requires, in part, that written procedures be established, implemented, and maintained for activities recommended in Appendix A of Regulatory Guide 1.33, " Quality Assurance Program Requirements," Revision 2, February 1978.

This includen procedures required for the safe operation and maintenance of nuclear power plants including equipment control instructions.

l

" Contrary to the above, the licensee failed to implement established procedure Site Standard Practice, (SSP)-6.56, " Labelling and Identification Tag Request Form Programs," as described below:

1.

SSP-6.56, Section 4.0, requires that approved labelling devices such as tags or labels be provided whenever it is necessary to identify components for operational purposes.

On June 6, 1994, NRC inspectors identified that the approved, l

permanent label plates for the precharge pushbutton on all eight Unit One and Two vital 120 volt AC inverters had been removed. The precharge pushbuttons were required to start the inverter and did not have any permanent or temporary identification.

2.

SSP-6.56, Appendix D, prohibits the use of temporary labelling methods such as magic marker or pen markings as a means of equipment identification.

On June 6, 1994, NRC inspectors identified three breakers in the 125 Volt Battery Board Room I that had equipment information added to the permanent label plate in handwritten ink pen.

NRC inspectors also identified a fourth permanent breaker label plate in the 125 Volt Battery Board Room I that was lined out and relabelled in handwritten ink pen.

"This is a Severity Level IV violation (Supplement I.D)"

Reason for the Violation l

The reason for failure to follow the procedure involving the labeling of plant components was personnel error.

In Example No.

1, the inverter precharge pushbutton was previously labeled correctly.

The label included an authorized operator aid.

During December 1992, an effort to reduce the number of operator aids was in progress and the inverter precharge pushbutton operator aids were identified for elimination. A

system operating instruction was revised to include the operator aid information, allowing the operator aid to be removed.

When the labels for the inverter procharge pushbuttons were removed, the individual failed to recognize that after removing the labels, temporary tags were required since the components were no longer labeled.

In Example No.

2, it was determined that some components have unauthorized information on the labels and/or components.

Specifically, a spare breaker was labeled as spare.

The label was marked through with " gas analyzer" written in ink on the label. The determination was made that the breaker was a spare breaker, and there was no indication as to why the label had been changed. Other labels included hand-written information that appeared to have been present for an extended period of time.

Personnel have been trained, and expectations have been conveyed to ensure that personnel are aware of the plant labaling requirements, including the requirement to not use unauthorized operator aids (e.g.,

hand-written notes on labels).

Corrective Steps That Have Been Taken and the Results Achieved Labeling requests for the inverter precharge pushbuttons were initiated, and temporary tags were placed on each of the precharge pushbuttons.

Labeling requests or service requests have been initiated, as appropriate, to correct the labels with the unauthorized markings.

Walkdowns of several 125-volt battery boards, 480-volt shutdown boards, and 6.9-ki.'ovolt shutdown boards were performed. The walkdowns did not identify any additional examples of missing labels.

Additionally, Nuclear Assurance has been monitoring the labeling and operator aid programs as part of the Oporations Performance Evaluation. This evaluation concluded that a large number of components do not have labels on the secondary side of the plant or have temporary markings to identify the equipment.

The majority of these components are associated with skid-mounted equipment and have not previously been labeled. The evaluation indicated that a large number of temporary identification tags exist on plant equipment, indicating that unlabeled components are being identified.

The evaluation further reveals that the labeling program is in place and is being implemented to provide permanent labels on equipment.

A standing order has been issued to operations personnel summarizing the labeling and unauthorized markings issue, including the key requirements of the labeling program.

Corrective Steps That Will be Taken to Avoid Future Violations An action plan will be developed to address the issue of unauthorized markings on plant labels. A site dispatch will be issued providing a summary of the labeling and unauthorized markings issue, including the key requirements of the labeling program.

Date When Full Compliance Will be Achieved i

TVA will be in full compliance when the action plan associated with j

unauthorized markings on plant labels is completed.

4

  • d e

ENCLOSURE 2 COMP (MENTS INSPECTION hu.' ORT 94-300 1.

An action plan will be developed to address the issue of unauthorized markings on plant labels. This action will be completed by October 7, 1994.

2.

A site dispatch will be issued providing a summary of the labeling and unauthorized markings issue, including the key requirements of the labeling prnqram.

This action will be completed by September 9, 1994.

l l

l i

_ _ _ _ _ _ _ _ _ _