ML20072A617
| ML20072A617 | |
| Person / Time | |
|---|---|
| Site: | Farley |
| Issue date: | 01/14/1983 |
| From: | Clayton F ALABAMA POWER CO. |
| To: | NRC OFFICE OF RESOURCE MANAGEMENT (ORM) |
| Shared Package | |
| ML20072A622 | List: |
| References | |
| NUDOCS 8301240082 | |
| Download: ML20072A617 (2) | |
Text
-_
M;iling Addr:ss Alabama Power Company 600 North 18th Street Post Office Box 2641 Birm;ngham, Alabama 33291 Telephone 205 783-6081 F. L Clayton, Jr.
b C7/ogggdl"'
Alabama Pbwer the southern electrc system January 14, 1983 Docket No. 50-364 Director, Office of Management Information and Program Control U. S. Nuclear Regulatory Commission
./
Washington, D.C.
20555
Dear Sir:
RE: JOSEPH M. FARLEY NUCLEAR PLANT Unit 2 Monthly Operating Data Report Attached are two (2) copies of the December,1982 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 2, required by Section 6.9.1.10 of the Unit ? Technical Specifications. As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21, 1977, a
" Narrative Summary of Operating Experience" is included in the attached report.
If you have any questions, please advise.
Yours very truly I
Y 6% t F. L. Clayton, Jr.
FLCJr/KWM:bhj Enclosures xc: Mr. Ted Cintula (1 copy)
Director, IE (10 copies)
Director, RII (1 copy) hh
~
83012400EE2 830114 PDR ADOCK 05000364
_R PDR
p..
JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2 NARRATIVE
SUMMARY
OF OPERATIONS DECEMBER, 1982 The Cycle I - Cycle II Refueling Outage continued into the month of December. The unit was shutdown on December 10, 1982 for the performance of the turbine overspeed trip test.
The following safety-related maintenance was performed in the month of December:
1.
Performed miscellaneons maintenance on diesel generators.
2.
Adjusted valve pressure setting on Power Operated Relief Valve PCV444B.
3.
Repacked #7 River Water Pump.